W912P722B0003 Amendment 0001.pdf
PDF 157 KB Posted
- Attached to
- RICHMOND INNER HARBOR FY22 MAINTENANCE DREDGING PROJECT Federal contract opportunity
- Solicitation number
- W912P722B0003
About this file
This document provides details on a federal contract opportunity for maintenance dredging services. The solicitation seeks bids for annual maintenance dredging of the Richmond Inner Harbor to a depth of 37 feet below the mean lower low water level, plus one additional foot of overdepth dredging. Dredged materials can be disposed at a contractor-provided upland site for use as cover or foundation, or at the government-furnished ocean disposal site. The solicitation is designated as a small business set-aside with an estimated value between $10-25 million. Bids are due by May 13th, 2022 and will be publicly opened via WebEx on May 13th. The work is being conducted by the Department of the Army Corps of Engineers San Francisco District.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912P722B0003 OF 1419.pdf | ||
| USACE San Francisco Bay Programmatic SFBRWQB WDR and WQC_2020_to_2024.pdf | ||
| W912P722B0003 Request for Information Responses Part II.pdf | ||
| USACE San Francisco Bay Programmatic BCDC LOA and CN_2020-2024.pdf | ||
| W912P722B0003 Amendment 0001 Section 00 73 00.pdf | ||
| W912P722B0003 Amendment 0001 Revised Plans.pdf | ||
| W912P722B0003 Amendment 0001 Revised Section 01 35 26.pdf | ||
| W912P722B0003 Request for Information.pdf | ||
| W912P722B0003 Reissued WDR and WQC.pdf | ||
| W912P722B0003 Richmond Inner Harbor Specifications.pdf | ||
| W912P722B0003 Richmond Inner Harbor Plans.pdf | ||
| W912P722B0003 BCDC Consistency Notification.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
W912P722B0003 AMENDMENT 0001
Please see page 2 for further details. The bid date remains unchanged.
All offerors are required to acknow ledge this amendment and provide a signed copy of this amendment (SF30) w ith their bid submission. If this amendment is not acknow ledged or signed, the bid w ill be considered non-responsive.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-May-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P722B0003
X 9B. DATED (SEE ITEM 11)
13-Apr-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-May-2022
CODE
CONTRACTING DIVISION
450 GOLDEN GATE AVE, 4TH FL
SAN FRANCISCO CA 94102
W912P7 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P722B0003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001 INFO
The purpose of this Amendment 0001 is to provide for the following revisions to the specification sections and plans:
Section 01 35 26 - Government Safety Requirements (Dredging)
• Revise Paragraph 1.12.7 – Worker Compensation Claims
Section 00 73 00 – Special Contract Requirements
• Add REQUIRED INSURANCE SCHEDULE (Construction) (AUG 2008)
Plans
• Revise survey date on note 1 for Sheet G-02
• Update Sheet C-01 – C-04 with 30 Mar 2022 survey
Revised specification sections and plans are included with Amendment 0001.
(End of Summary of Changes)