BID ABSTRACT.pdf
PDF 570 KB Posted
- Attached to
- NOYO HARBOR FY20 MAINTENANCE DREDGING PROJECT Federal contract opportunity
- Solicitation number
- W912P720B0008
About this file
This document is an abstract of offers for a federal construction contract solicitation. The solicitation seeks maintenance dredging services for the Noyo Harbor to achieve an authorized depth of 10 feet, with up to 1 additional foot of overdepth dredging. The work includes excavating dredge material from the harbor and transporting and disposing it at government-furnished upland sites. Offerors must remove all material and perform the work using their own labor, equipment, and resources within the performance period. Acceptance will be based on achieving the project depth throughout the entire project footprint. Four offers were received from Curtin Martin, AHTNA Design Build, Camenzind Dredging Inc., and the government estimate. Pricing and other details for each offeror's bid are included on the form for evaluation. The soliciting agency is the Department of the Army Corps of Engineers Engineering District San Francisco.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912P720B0008-0001pdf.pdf | ||
| W912P720B0008Noyo_River_FY20_PLANS (SOLICITATION).pdf | ||
| W912P720B0008 Noyo Harbor Dredging FY20 Specs (100 for Solicitation)1MAY20.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT OF OFFERS - CONSTRUCTION
CONTINUATION SHEET
1. SOLICITATION NUMBER PAGE OF
PAGES
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
4. OFFERS (Continued)2. PROJECT TITLE
NO.: NO.: NO.: NO.:
A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
A.
ITEM
NO.
B.
ESTIMATED
QUANTITY
C.
UNIT D. UNIT
PRICE
E. ESTIMATED
AMOUNT
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
OPTIONAL FORM 1419A (11-88)
ABSTRACT OF OFFERS - CONSTRUCTION CONTINUATION SHEET
1. SOLICITATION NUMBER
PAGE OF
PAGES
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
4. OFFERS (Continued)
2. PROJECT TITLE
NO.:
NO.:
NO.:
NO.:
A. OFFEROR
A. OFFEROR
A. OFFEROR
A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
3. CONTRACT ITEMS
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
A. ITEM NO.
B. ESTIMATED QUANTITY
C. UNIT
D. UNIT PRICE
E. ESTIMATED AMOUNT
E. ESTIMATED AMOUNT
D. UNIT PRICE
E. ESTIMATED AMOUNT
D. UNIT PRICE
E. ESTIMATED AMOUNT
D. UNIT PRICE
AUTHORIZED FOR LOCAL REPRODUCTION Previous edition is usable
OPTIONAL FORM 1419A (11-88)
8.2.1.3144.1.471865.466429
| 1. SOLICITATION NUMBER: W912P720B0008 |
| 2. PROJECT TITLE: |
NOYO HARBOR FY 20 MAINTENANCE DREDGING PROJECT
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): 20% |
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): 20% |
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): 20% |
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): |
| 4C. OFFERS (Continued) AMENDMENTS ACKNOWLEDGED.: Yes |
| 4C. OFFERS (Continued) AMENDMENTS ACKNOWLEDGED.: YES |
| 4C. OFFERORS (Continued) AMENDMENTS ACKNOWLEDGED.: YES |
| 4C. OFFERS (Continued) AMENDMENTS ACKNOWLEDGED.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 1 of 13.: 1.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13: |
| 3B. ESTIMATED QUANTITY: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 13 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 12 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 11 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 10 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 9 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 8 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 7 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 6 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 5 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 4 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: 1579550.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: 899000.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: 1116126.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: 1258290.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: TOTAL |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 3 of 13.: 3.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 325550.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13: 19.15000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 357000.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13: 21.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 397460.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13: 23.38000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 1258290.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13.: 56.37000000 |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3B. ESTIMATED QUANTITY: 17000.00000000 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 2 of 13.: 2.00000000 |
| 3B. ESTIMATED QUANTITY: 1.00000000 |
| 3C. CONTRACT ITEMS. UNIT: JOB |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 Of 13.: 300000.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 300000.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 of 13: 718666.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 718666.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 of 13: 542000.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 542000.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 of 13: 1254000.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 1254000.00000000 |
| PAGE OF: 1.00000000 |
| PAGES: 1.00000000 |
| Offeror number. Column 1 of 4.: |
| Offeror number. Column 2 of 4.: |
| Offeror number. Column 3 of 4.: |
| Offeror number. Column 4 of 4.: |
| A. OFFEROR: Curtin Martin |
| A. OFFEROR: AHTNA DESIGN BUILD |
| A. OFFEROR: CAMENZIND DREDGING, INC |
| A. OFFEROR: GOVERNMENT ESTIMATE |
File details come from the government source that posted it. Updated .