Scope of Services
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions_and_Answers_WQM.pdf | ||
| PPQ-0_Past_Performance_Questionnaire.pdf | ||
| 15-5623_Wage_Determinations.pdf | ||
| Bid_Schedule_FY19_WQ_Monitoring.pdf | ||
| FAR_Provisions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Services for:
PROJECT: FY 2019 Maintenance Dredging
TITLE: Water Quality Monitoring Surveys
CONTRACTOR: TBD
CONTRACT: TBD
LOCATION: Alameda and Contra Costa County, CA
1. MAILING ADDRESS / POINTS OF CONTACT
The point of contact (TPOC) for technical questions at USACE is:
| Mr. | Christopher | Eng, | Environmental | Section | B | (CESPN‐ET‐PB) | |
| U.S. | Army | Corps | of | Engineers, | San | Francisco | District |
| 450 | Golden | Gate | Avenue, | 4th | Floor, | Room | 6751 |
| San | Francisco, | California | 94102 | ||||
| Phone: | (415) | 503‐6868 | |||||
| Email: | Christopher.K.Eng@usace.army.mil |
| All | correspondence, | submittals, | invoices, | etc. | shall | be | e‐mailed | to | the | contracting | officer’s | ||
| representative | (COR), | at | the | address | provided | below. | The | COR | is | the | contractual | point | of |
| contact | for | this | contract | (to | assists | in | the | technical | monitoring | and | administration | of | a |
| contract | only). |
| Mr. | Joseph | Viola, | A‐E | Services | Unit | (CESPN‐ET‐EC) | |
| U.S. | Army | Corps | of | Engineers, | San | Francisco | District |
| 450 | Golden | Gate | Avenue, | 4th | Floor | ||
| San | Francisco, | California | 94102 | ||||
| Phone: | (415) | 503‐6883 | |||||
| Email: | Joseph.J.Viola@usace.army.mil |
2. INTRODUCTION AND BACKGROUND
| This | scope | of | work | describes | the | tasks | that | will | be | performed | by | the | contractor | to |
| determine | maintenance | dredging | of | these | projects | are | to | be | conducted | by | the | U.S. | Army | |
| Corps | of | Engineers | San | Francisco | District | (USACE) | beginning | in | the | month | June | 2019 | for | |
| both | Richmond | Inner | Harbor | and | Oakland | Harbor. | Different | contractors | will | be | dredging | |||
| these | projects. |
| To | comply | with | the | water | quality | monitoring | program | pursuant | to | Water | Quality | ||
| Certification | (WQC) | Order | No. | R2‐2015‐0023 | for | the | 2015‐2019 | Maintenance | Dredging | ||||
| Program | issued | to | USACE | by | the | Regional | Water | Quality | Control | Board. | The | monitoring | will |
| be | performed | at | Richmond | Inner | Harbor | and | Oakland | Harbor. | The | data | collected | will | |
| help | analyze | impacts | of | controlled | decanting | during | dredging | on | water | quality | in | the | project |
area.
| The | Oakland | Inner | and | Outer | Harbor | is | located | in | the | City | of | Oakland | in | Alameda | County. |
| The | site | is | currently | bordered | by | industrial | and | marine | uses, | as | well | as | recreational | areas: | |
| Port | View | Park | and | Middle | Harbor | Shoreline | Park. | The | Richmond | Inner | Harbor | is | located | ||
| within | the | boundaries | of | Contra | Costa | County. |
3. DESCRIPTION OF WORK AND SERVICES REQUIRED
| The | contractor | shall | provide | the | services | of | a | team | and | mapping | technicians | with | |
| experience | in | water | quality | sampling | and | monitoring | in | the | San | Francisco | Bay | and | coast |
| of | California. |
| The | proposal | will | include | the | resume | of | each | proposed | project | team | member | to |
| demonstrate | the | aforementioned | qualifications. |
BASE TASK:
| Task | 1 | – | Water | Quality | Monitoring | for | Oakland | and | Richmond | Inner | Harbors | |
| Total | Monitoring | day | requirements | under | this | Base | Task | per | project | location: | ||
| 1 | (one) | pre‐dredge | day | (Day | 0) | |||||||
| 1 | (one) | pre‐decant | baseline | monitoring | (Day | 1) | ||||||
| 5 | (five) | decant | monitoring | days | (day | 2 | through | day | 6) | |||
| 5 | (five) | If | required | exceedance | decant | monitoring | days, | (day | 7 | through | day | 11) |
I. Constituents Monitored
| The | Oakland | Harbor | and | Richmond | Harbor | Federal | Navigation | Channel | FY19 | Dredging | ||
| Projects | requires | the | following | water | quality | monitoring | program | pursuant | to | Water | ||
| Quality | Certification | (WQC) | Order | No. | R2‐2015‐0023 | for | the | 2015‐2019 | Maintenance | |||
| Dredging | Program | if | controlled | decanting | is | requested | for | these | projects. | Controlled | ||
| decanting | is | any | discharge | of | water | entrained | with | the | dredged | sediment | from | any |
| barge/scow | into | which | the | dredged | sediment | is | placed. |
A. Aquatic life turbidity applicable criteria:
1. Turbidity ≤ 50 NTU (or up to 10 percent greater than turbidity at a
| background | reference | location | sampled | concurrently | with | the | dredging | |||||
| location, | if | the | background | turbidity | is | greater | than | 50 | NTU) | measured | at | |
| the | point | of | compliance, | which | shall | be | located | 500 | feet | down | current | of |
| the | dredging. |
II. Pre-dredge, Pre-decant, and Decant Monitoring Schedule
Note: This is day 0. (1 day of pre-monitoring reconnaissance) Day 0 counts as a pre monitoring mobilization, site reconnaissance day and post monitoring demobilization. This counts as one 12 hour pre-monitoring day
| A. Contractor | will | take | turbidity | measurements | within | the | water | strata | in | the | vicinity | |||
| of | where | dredging | will | be | taking | place, | as | described | in | the | Sampling | Approach, | a | day |
| before | dredging | operations | to | measure | the | background | conditions | within | the | |||||
| dredging | area. |
B. Turbidity measurements will be taken, as prescribed in Sampling Approach below,
| and | these | will | be | used | to | compare | decanting | to | non‐decanting | conditions | (just | the |
| clamshell | bucket | working | with | no | decanting). |
C. For five additional days, contractor will be allowed to decant and these
| measurements | will | be | taken | as | stated | in | the | sections | below. | Decanting | must | ||
| coincide | with | daylight | operations. | A | day | is | only | counted | if | decanting | occurs | for | at |
| least | two | hours, | at | a | minimum, | while | monitoring | is | taking | place. |
III. Frequency of Monitoring
Note: There will be a total of 11 monitoring days as shown in Paragraphs A through H below and each monitoring day is 12 hours long.
A. Day 1 (one day of monitoring)
| On | the | first | full | day | of | dredging, | the | contractor | will | not | be | allowed | to | |
| overflow/decant. | However, | the | monitoring | will | commence | as | described | in | ||||||
| paragraphs | B | trough | F | below | in | order | to | collect | data | and | to | establish | a | pre‐decant |
baseline.
| B. Day | 2 | through | day | 6 | (5 | days | of | monitoring) | ||||
| All | duties | as | described | in | this | paragraph | B | and | through | G | will | apply. |
| The | contractor’s | dredging | equipment | shall | be | operating | for | at | least | one | hour | prior | to |
| the | collection | of | turbidity | readings | to | ensure | readings | and | observations | are | |||
| representative | of | turbidity | conditions | during | normal | active | operations. |
| C. The | contractor’s | turbidity | monitoring | will | correspond | with; | 1) | slack | tide | and | 2) | |
| strong | ebb | or | flood | tidal | conditions | to | the | extent | these | times | adequately | reflect |
| periods | of | active | dredging | and | occur | during | daylight | hours. |
D. The contractor shall conduct quantitative and visual turbidity monitoring during daylight hours only as follows:
| 1. Take | and | record | readings | every | 10 | minutes | at | one | (1) | up‐current | and | two |
| (2) | down‐current | locations | during | the | first | day | of | dredging | and | the | first | |
| five | (5) | days | of | decant | monitoring. |
2. Record (written and photographic) of “visible” turbidity at the point of
| compliance | during | the | first | day | of | dredging | and | the | first | five | (5) | days | of |
| decant | monitoring. |
E. For safety reasons, no monitoring shall occur before sunrise or after sunset unless authorized by the USACE.
| F. The | contractor | shall | provide | daily | reports | (within | 24 | hours) | by | e‐mail | to | the |
| personnel | listed | in | Section | VIII.A. | and | upon | completion | of | the | five | (5) | monitoring |
| days | of | decant | monitoring, | the | contractor | shall | send | the | compiled | monitoring | data | |
| report | within | 24 | hours | of | completion | of | monitoring | activity. |
G. If there are no exceedances in turbidity within the five (5) days of decant
| monitoring, | the | contractor | shall | provide | reports | as | described | in | III.E. | and | wait | for |
| further | direction | from | USACE | before | demobilizing | or | continuing | to | decant. | |||
| Additional | monitoring | may | be | required | based | on | quality | of | data | and | site | conditions. |
| The | USACE | will | consult | with | RWQCB | and | BCDC | and | will | notify | the | contractor |
| whether | or | not | decanting | will | be | allowed | to | continue | or | not. |
H. Exceedance monitoring Day 7 through Day 11 (5 days of monitoring)
| Should | there | be | an | exceedence | in | turbidity | within | the | initial | five | (5) | days | of | decant |
| monitoring, | the | contractor | shall | continue | monitoring | for | 5 | days | following | the | steps | |||
| listed | in | “Exceedance | and | Exceedance | Protocol.” |
IV. Sampling Approach
A. The contractor shall establish turbidity conditions according to the following:
a. Contractor shall take turbidity measurements within the water strata, one
| day | before | dredging | operations | to | measure | the | background | conditions | within |
| the | dredging | area | (See | Section | E | for | locations). |
b. The contractor shall measure turbidity using a turbidity meter, starting at
| least | one | hour | after | the | dredging | equipment | has | been | operating, | to | ensure |
| readings | and | observations | are | reflective | of | turbidity | conditions | during | active |
operations.
c. The contractor shall verify the calibration of the turbidity meter and calibrate
| as | necessary | with | standardized | samples | prior | to | the | start | of | each | day’s |
| monitoring, | per | the | manufacturer’s | specifications. |
d. The contractor shall collect turbidity readings within the water strata:
1. near the surface (~2 feet below).
2. mid‐depth.
3. near the bottom (~2 feet above).
e. The contractor shall compare turbidity readings taken at the point of
| compliance | to | background | levels | within | the | same | water | column | strata | (i.e., | at | |
| each | point | in | the | water | strata | – | surface, | mid‐depth | and | near | bottom, | with |
| comparisons | of | the | points | of | compliance | compared | to | the | same | strata | at | the |
| current | background | station) | to | determine | compliance | with | turbidity |
standards.
f. The contractor shall visually observe turbidity beyond the point of compliance and record the findings at the same time the turbidity levels are measured.
g. The contractor will ensure that all decant events are notated in with date and time. Also, coordinates where the turbidity readings are being recorded.
| h. If | multiple | dredges | are | being | deployed | on | site, | USACE | may | require | two |
| separate | monitoring | efforts | (one | for | each | dredge) | depending | on | the | locations | |
| of | the | dredge | operations | (see | options | below). |
V. Monitoring Locations
| A. The | area | of | mixing | point | of | compliance | for | turbidity | during | clamshell | dredging | is | 500 | |
| feet | down | current | from | the | point | of | clamshell | dredging | and | thus | will | move | as | the |
| dredging | progresses. |
B. The contractor shall establish Monitoring Points at:
1. Measured Background – A minimum of 200 feet up current from the dredging
2. Measured Downstream Early Warning – 300 feet down current of the dredging
3. Measured Downstream Point of Compliance – 500 feet down current of the dredging
VI. Exceedence and Exceedence Protocol
| A. If | any | of | the | three | measurements | taken | at | the | down | current | point | of | compliance | ||
| when | decant | is | occurring | show | recorded | turbidity | is | greater | than | 50 | NTU | where | the | ||
| background | is | less | than | 50 | NTU, | or | if | more | than | a | 10 | percent | increase | in | turbidity |
| when | the | background | turbidity | is | more | than | 50 | NTU, | the | contractor | shall | notify | the | ||
| USACE | within | two | (2) | hours | and, | assuming | dredging | continues, | shall | continue | to | ||||
| monitor | per | the | protocol | described | above, | restarting | the | 5 | consecutive | day | |||||
| monitoring | series | on | the | day | of | the | initial | turbidity | exceedence. | Contractor | will | not | |||
| cease | monitoring | until | directed | by | USACE, | Regional | Water | Quality | Control | Board | |||||
| and | BCDC. | Therefore, | timely | communications | are | requested. |
B. If additional exceedences are reported, the USACE will consult with the Regional
| Water | Quality | Control | Board | and | BCDC | to | determine | whether | to | continue |
| monitoring | or | whether | to | terminate | decant | and | turbidity | monitoring. |
VII. Reporting
A. The contractor shall document any turbidity criteria exceedences, decant or dredging
| shut | downs | with | an | Incident | Report, | which | will | be | transmitted | by | to | the | |
| persons | listen | in | VIII.B. | within | 24 | hours. |
B. In addition turbidity data, contractor will report 1) dredging activity (e.g. tug and
| barge | movement) | activity | 2) | decanting | operations | 3) | digging | operations | 4) | tide | ||||
| level | (ebb, | slack, | flood | and | 5) | external | activity | that | are | not | related | to | dredging | such |
| as | passing | vessels | during | dredging | operations. |
C. The Incident Report shall document all exceedence and will include the date, time,
| location, | activity, | turbidity | data | collected, | name | of | person | collecting | the | data, | names | ||
| of | persons | notified | of | the | exceedence, | photographs | if | taken, | and | summary | of | how | the |
| exceedence | was | resolved | following | the | above | protocol. |
D. A summary table and graphs of daily data, along with the WQMP worksheets will be
| included | in | the | final | report. | This | submittal | will | also | be | provided | in | electronic | format |
| compatible | with | Microsoft | Excel. | Example | template: |
Date Dredging
(Digging) Start Time (hh:mm)
Dredging (Digging) Stop Time (hh:mm)
Decant Start Time (hh:mm)
Decant Stop Time (hh:mm)
Turbidity Monitoring Start Time
Turbidity Monitoring Stop Time
No. of Times Upcurrent/Ambient
| Station | Monitored |
| During | Decanting |
No. of Times Early Warning Station Monitored During Decanting
No. of Times Compliance Station Monitored During Decanting
VIII. Responsibility and Communication Plan
| A. The | party | responsible | for | monitoring | water | quality | for | the | project | will | attend | a | pre‐ |
| monitoring | meeting | with | USACE | at | least | 48 | hours | prior | to | commencement | of | the |
plan.
B. All exceedences, daily report logs, and other reporting must also be sent directly
| to | the | USACE | Points | of | Contact | for | turbidity | monitoring | by | e‐mail: | Mr. | Chris | Eng, |
| Environmental | Sciences | (415) | 503‐6868, | Christopher.K.Eng@usace.army.mil | and | the | |||||||
| RWQCB | point | of | contact, | echristian@waterboards.ca.gov. |
| OPTION: | The | option(s) | will | exercised | at | the | discretion | of | the | Contracting | Officer | subject | to | |||
| availability | of | funds. | If | exercised, | option(s) | would | be | exercised | prior | to | the | expiration | of | the | ||
| base | (prior | to | November | 30, | 2019). | The | overall | period | of | performance | will | not | be | |||
| extended, | all | exercised | options | require | to | be | performed | concurrent | with | the | other | |||||
| requirements | as | described | within | this | contract. | Unless | otherwise | amended, | the | |||||||
| performance | period | for | completion | of | the | options | will | be | as | stated | therein. | The | ||||
| Government | will | notify | the | contractor | 30 | calendar | days | prior | to | exercise | of | option(s). | The | |||
| pricing | of | the | options | will | be | evaluated | with | the | overall | price | to | ensure | there | is | no | evidence |
| of | unbalancing. |
| Option | monitoring | durations | (days) | are | as | described | in | Para. | III. Frequency of |
| Monitoring. Note: All | other | monitoring | requirements | as | described | in | this | scope | of |
| services, | will | apply | to | the | options. |
Pricing for the options shall address a total of 12 days of monitoring thereof:
Day 0 (1 (one) 12 hrs. day of pre-monitoring reconnaissance
| Day 1 (1 | (one) | 12 | hrs. | day | of | baseline‐monitoring) | ||||
| Day | 2 | through | day | 6 | (5 | days | 12 | hrs/day | of | monitoring) |
| Day | 7 | through | 11 | (5 | days | 12hrs/day | of | monitoring) | if | required |
| Option | 1 | for | one | additional | Water | Quality | Monitoring | for | Richmond | Inner | Harbor | ‐ | If |
| multiple | dredges | are | being | deployed | on | site, | USACE | may | require | two | separate | monitoring | |
| efforts | (one | for | each | dredge). | This | option | will | be | exercised | for | the | additional | concurrent |
| monitoring | effort, | if | this | occurs. |
| Option | 2 | for | one | additional | Water | Quality | Monitoring | for | Oakland | Harbor | ‐ | If | multiple |
| dredges | are | being | deployed | on | site, | USACE | may | require | two | separate | monitoring | efforts | |
| (one | for | each | dredge). | This | option | will | be | exercised | for | the | additional | concurrent | |
| monitoring | effort, | if | this | occurs |
4. DELIVERABLES/SUBMITTALS/REPORTS SCHEDULE
| A | comprehensive | report | for | each | project | shall | be | conducted | as | described | in | the |
| “deliverables” | section | below. |
| a. Water | Quality | Monitoring | – | Daily | Reports | (daily | e‐mails), | Draft | and | Final | ||
| Reports | (3 | hard | copies, | one | electronic | copy, | and | all | source | files). | Draft | report |
| is | due | within | 10 | calendar | days | of | survey | completion. | Upon | receipt | of | |
| comments, | Final | report | is | due | within | 30 | calendar | days | after | receipt | of |
comments.
5. RESPONSIBILITY FOR FIELD WORK
| The | contractor | shall | be | responsible | for | all | damages | to | persons | and | property | that | occur | as | a |
| result | of | actions | by | the | contractor’s | employees | in | connection | with | execution | of | the | work | ||
| under | this | contract. | The | contractor | shall | hold | the | United | States | Government | free | from | all | ||
| claims | and | suits | for | damages | as | a | result | of | this | work. | Damages | to | persons | and | property |
| proximately | resulting | from | the | negligence | of | federal | government | employees | are | excluded | |||||
| from | this | provision. |
6. METADATA AND TABULAR DELIVERABLES
| The | deliverables | shall | include | metadata | compliant | with | the | Federal | Geographic | Data | ||||||
| Committee | metadata | standard | for | each | data | set | that | is | part | of | the | report | or | that | was | used |
| in | making | the | report. |
| The | Federal | Geographic | Data | Committee | metadata | standard | is | described | in | documents |
| listed | on | this | page: | http://www.fgdc.gov/metadata/geospatial‐metadata‐standards |
| All | geospatial | information | shall | be | geo‐referenced. | All | CADD | and | GIS | files | shall | be | ||||
| registered | in | a | well‐known | coordinate | system. | Rectified | imagery | and | scanned | maps | shall | |||||
| include | a | file | (e.g. | a | world | file) | allowing | GIS | and | CADD | applications | to | import | them | as | geo‐ |
| referenced | images. |
| All | CADD | and | GIS | files | with | attribute | tables | shall | conform | to | the | Spatial | Data | Standards | for |
| facilities, | Infrastructure | and | Environment | (SDSFIE) | for: |
| Entity | types |
| Attribute | tables |
| Attribute | Names |
| Domain | Tables |
| The | SDSFIE | requirement | only | applies | to | GIS | data, | i.e. | vector | data | (such | as | points, | lines | and |
| polygons) | that | have | an | attribute | table. | It | does | not | apply | to | pre‐existing | data, | elevation | data | |
| or | image | data. | The | SDSFIE | is | available | at | http://www.sdsfie.org. |
7. TRANSMITTALS
| Transmittal | letters | shall | be | dated | and | signed | by | the | appropriate | contract | officer | ||
| representative | (contractor) | and | be | provided | to | the | Government | on | 8‐1/2" | x | 11" | paper. | An |
| electronic | copy | of | the | transmittal | letter | in | Microsoft | Word, | version | 2007 | or | newer | format |
| shall | also | be | provided | on | the | electronic | digital | media | submitted | to | the | Government. | As |
| applicable, | electronic | transmissions | shall | include: |
| An | external | label | on | each | media | unit | (i.e., | CD) | along | with | the | total | number | being | delivered. | |
| This | label | will | include | a | list | of | the | names | and | description | of | each | file | contained | on | the |
media.
Brief instructions for transferring files from the media.
| Certification | that | all | delivery | media | are | free | of | known | computer | viruses. | A | statement | ||
| including | the | name(s) | and | release | date(s) | of | the | virus‐scanning | software | used | to | analyze | ||
| the | delivery | media, | the | date | the | virus | scan | was | performed, | and | the | operator's | name | shall |
| also | be | included | with | the | certification. | The | release | or | version | date | of | the | virus‐scanning | |
| software | shall | be | the | current | version | and | capable | of | detecting | the | latest | known | viruses | at |
| the | time | of | delivery | of | the | digital | media. |
| A | statement | indicating | the | contract | officer | representative | (contractor) | will | retain | a | copy | of | |||
| all | delivered | electronic | digital | media | (with | all | files | included) | for | at | least | one | year | and, | |
| during | this | period | of | time, | will | provide | one | additional | copy | of | each | to | the | government, | if |
| requested, | at | no | additional | cost. |
| Instructions | concerning | how | to | generate | plotted, | or | hard | copy, | drawings | from | the | provided |
| plot | files. | For | geo‐referenced | maps, | notating | the | coordinate | system | is | required. |
List of any deviations from the government's standard layer/level scheme and file naming conventions.
| List | of | all | new | symbol | cells/blocks | created | for | the | project | which | was | not | provided | to | the |
| contractor | with | the | documents | and | reports. |
List of any non‐IGES crosshatch/ patterns used.
| List | of | all | new | figures, | symbols, | tables, | schedules, | details, | and | other | cells/blocks | created | for |
| the | project, | which | was | not | provided | to | the | contract | officer | representative | with | the | A/E/C |
| CADD | Standard | Release | 3.0 | and | any | associated | properties. |
| List | of | all | database | files | associated | with | each | drawing | as | well | as | a | description | and |
| documentation | of | the | database | format | and | schema | design | as | used. |
8. PERIOD OF SERVICE
Task 1: Total duration for the base contract is date of award through November 30, 2019.
| Option | 1: | Total | duration, | if | awarded, | through | November | 30, | 2019. |
| Option | 2: | Total | duration, | if | awarded, | through | November | 30, | 2019. |
9. PERFORMANCE STANDARDS
During the execution of the tasks outlined in this scope of work, the contractor shall:
a. Execute the work diligently and aggressively.
| b. Promptly | advise | the | TPOC | and | COR | of | all | significant | developments | which | may | affect |
| the | scope | of | the | contract. |
c. Prepare notes on all meetings, discussions, and telephone conversations between
| the | contractor | and | representatives | of | other | government | agencies, | their | contractors, | |||
| and | other | USACE | contractors | related | to | the | work | outlined | in | this | contract. | Written |
| summaries | of | significant | discussions | shall | be | provided | to | the | TPOC | and | COR. |
d. Promptly furnish to the appropriate USACE point(s) of contact all written
| communications | pertaining | to | the | work | described | under | this | contract | from | other |
| government | agencies, | their | contractors, | or | other | USACE | contractors; |
e. Take appropriate measures to obtain clarification of project and data assumptions
| and | design | criteria | requirements, | to | acquire | all | pertinent | information, | and | to |
| incorporate | such | information | in | the | work | being | performed; |
f. Be responsible for producing complete, competent, properly coordinated, well written and thoroughly checked documents within agreed upon schedules; and
| g. Be | responsible | for | the | quality | control | of | the | work | conducted | under | this | contract | and |
| have | a | logical | and | functional | quality | control | program | to | assure | that | errors | and | |
| deficiencies | in | all | submittals | are | non‐existent | to | minimal. |
h. The contractor will comply with Executive Order 13423 Section 1: To the greatest
| extent | practicable, | the | contractor | shall | conduct | work | in | an | environmentally, | ||||
| economically, | fiscally, | and | sustainable | manner | (Federal | Register: | Vol. | 72, | No. | 17; | |||
| Friday, | January | 26, | 2007). | The | contractor | may | also | be | asked | to | comply | with | |
| Executive | Order | 13423 | on | sustainability | (October | 6, | 2009) | as | more | specific | details | ||
| are | provided. | The | contractor | shall | state | how | this | shall | be | accomplished, | in | the | cost |
proposal.
10. QUALITY CONTROL
| The | contractor | must | provide | documented | quality | control | (QC) | on | all | work. | The | document | ||
| shall | be | well | written | in | standard, | proper | English, | plain | language, | and | active | voice, | generally | |
| conforming | to | a | widely | accepted | style | manual | consistent | with | the | products | such | as | the | |
| Government | Printing | Office | Style | Manual. | The | technical | level | of | writing | should | be | such | that | |
| the | material | is | fully | understandable | by | a | person | without | specific | training | in | the | field | at |
| hand | but | without | compromising | its | value | to | the | target | audience. | The | target | audience | ||
| includes | technical, | managerial, | executive, | and | senior | scientist | personnel | in | various |
| regulatory | and | related | government | agencies. | The | work | will | be | used | for | regulatory, | ||||
| permitting, | policy | and | related | issues | as | well | as | possible | follow‐up | research. | Jargon | specific | |||
| to | various | fields | should | either | be | clearly | explained | in | the | text | or | defined | in | a | glossary. |
11. MONTHLY SAFETY EXPOSURE REPORT
| The | contractor | shall | submit | the | “USACE | PRIME | CONTRACTOR, | Monthly | Record | of | Work‐ | |
| Related | Injuries/Illnesses | & | Exposure | in | electronic | spreadsheet | format | through | email. |
The form can be downloaded from:
https://team.usace.army.mil/sites/NAE/EP/W/WG/admin/Safety/Safety General/Monthly Record of Work‐Related Injuries Illnesses Exposure.xls
For further information regarding the “Monthly Safety Exposure Reports”, please contact:
| Mr. | Joseph | Viola | |||||
| U.S. | Army | Corps | of | Engineers, | San | Francisco | District |
| A‐E | Services | Unit | |||||
| 450 | Golden | Gate | Avenue, | 4th | Floor | ||
| San | Francisco, | California | 94102 | ||||
| Phone: | 415‐503‐6883 | ||||||
| Email: | Joseph.J.Viola@usace.army.mil |
12. MONTHLY PROGRESS REPORT
| The | contractor | shall | provide | a | monthly | progress | reports | throughout | the | duration | of | this | ||||
| project. | The | report | shall | be | a | brief | description | of | progress | to | date, | any | problems/issues | and | ||
| their | resolution. | The | report | may | be | submitted | as | a | word | documents | via | email. | Such | |||
| reports | shall | be | provided | to | the | TPOC | and | COR. | In | the | event | there | are | information | needs | |
| not | being | met | by | USACE | which | are | delaying | progress, | reports | of | such | shall | be | provided | ||
| monthly | to | the | TPOC | and | COR. |
13. ACCEPTANCE
| Acceptance | of | the | final | submittal | for | the | work | described | in | the | foregoing | paragraphs | will |
| be | made | by | the | contracting | officer. | No | other | government | representative | is | authorized | to | |
| change | the | scope | of | services | or | terms | of | the | contract. |
14. INVOICE AND PAYMENT
Invoices shall be submitted through email to:
Attn: Joseph Viola, A‐E Unit
| U.S. | Army | Corps | of | Engineers | |
| 450 | Golden | Gate | Avenue, | 4th | Floor |
| San | Francisco, | California | 94102 | ||
| Tel. | No. | 415‐503‐6883 | |||
| Email: | Joseph.J.Viola@usace.army.mil |
In addition please carbon copy (cc) the invoices to:
| Bick | Y. | Lee | |||
| U.S. | Army | Corps | of | Engineers | |
| 450 | Golden | Gate | Avenue, | 4th | Floor |
| San | Francisco, | California | 94102 | ||
| Tel. | No. | 415‐503‐6882 | |||
| Email: | Bick.Y.Lee@usace.army.mil |
| 15. | PROPOSAL | SUBMITTAL | PACKAGE | |||||||||||||
| A | cost | proposal | shall | be | submitted | for | the | work | described | in | this | scope | of | services. | The | cost |
| proposal | must | be | presented | in | such | a | manner | to | facilitate | the | government's | review | and |
analysis.
The submittal package shall contain:
| a. Cost | proposal |
| b. Technical | Proposal |
| i. Statement | of | contractor | qualifications | ||||
| ii. Staffing | plan | (including | availability) | including | resumes | of | key |
personnel