W912P7-09-B-0005_Rev COMBINED_UPDATED_SF1442_5Aug09.pdf

PDF 559 KB Posted

Attached to
RECOVERY--Port of Redwood City Channel Maintenance Dredging, San Mateo County, California, Project Code 15100
Solicitation number
W912P7-09-B-0005
Issued by

About this file

Amendment 2 - Redwood City Channel Maintenance Dredging San Mateo County California - PDF.

View the file

Other files

File Type Posted
BID RESULTS.pdf PDF
W912P7-09-B-0005_Amendment 0003.pdf PDF
2 OF 5.cal —
3 of 5.cal —
Readme_Redwood City O M 2009.txt TXT text file
Redwood City Harbor O M 2009_Amend2.maxFR —
COVERSHEET - AMEND_2-Coversheet.cal —
4 of 5.cal —
5 of 5.cal —
W912P7-09-B-0005_Amendment 00001.pdf PDF
5 of 5.cal —
Readme_Redwood City O M 2009.txt TXT text file
4 of 5.cal —
1 of 5.cal —
3 of 5.cal —
RedwoodRevised_06Aug2009.pdf PDF
2 OF 5.cal —
Redwood City Harbor O M 2009.maxFR —
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

L3ET9SNM

Typewritten Text

ENCL)REVISED SF1442, Section 00010 Bid Schedule, Section 01 11 00 - Summary of Work, Section 00 00 00 - Table of Contents, Section 35 20 23 - Dredging, and Section 35 20 25 - Hamilton Off Loading, Section 35 20 24 - Aquatic Disposal, Drawing Sheet Reference Number 1, Section 01 32 23 - Hydrographic Survey.

W62A2B91816775

UNRESTRICTED

REDWOOD CITY CHANNEL MAINTENANCE DREDGING, SAN MATEO COUNTY, CALIFORNIA

JOB DESCRIPTION: The work consists of maintenance dredging of the Federal channel located at or near the Port of Redwood City arbor Channel, San Mateo County, California. All dredging, material transportation and material placement shall be in ccordance with the project plans, specifications, permits, regulatory guidance and applicable contract clauses. Dredged material excavated from the Redwood City Harbor Channel shall be transported and off loaded at the Hamilton Wetland Restoration Project (HWRP) and disposed at the Alcatraz Disposal Site, SF-11. The Government will provide off loading at the HWRP. The Contractor may provide proposals for fully permitted beneficial use upland alternatives other than those placement sites listed

H a herein.

ESTIMATED COST RANGE OF PROJECT: $5,000,000 - $10,000,000

X

JAMES E GARROR 415-503-6988

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

5-August-2009

(RFP)

(IFB)

CALL:

B. TELEPHONE NO.

TEL:

(Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442

Prescribed by GSA

(REV. 4-85)

11. The Contractor shall begin performance within _______3 calendar days and complete it within ________130 90 calendar days after receiving award, X notice to proceed. This performance period is mandatory, negotiable. (See _ ________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the work required are due at the place specified in Item 8 by __1:00 p.m._ local time 8 September 2009 _____ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______ 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

8. ADDRESS OFFER TO

PAGE OF PAGES

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

(hour) Sealed envelopes containing offers

FAX:

(If Other Than Item 7)

6. PROJECT NO.

7. ISSUED BY CODE

W912P7-09-B-0005

TEL: FAX:

5. REQUISITION/PURCHASE REQUEST NO.

W912P7

US ARMY ENGINEER DISTRICT, SAN FRANCISCO

CONTRACTING DIVISION

1455 MARKET ST., 17TH FLOOR SUITE 1741

SAN FRANCISCO CA 94103-1398

FAR (48 CFR) 53.236-1(e)

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY: 26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR (Include area code) 15. TELEPHONE NO.

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your offer on this solicitation, is hereby accepted as to the items listed. This award con-to furnish and deliver all items or perform all work, requisitions identified summates the contract, which consists of (a) the Government solicitation and on this form and any continuation sheets for the consideration stated in this your offer, and (b) this contract award. No further contractual document is contract. The rights and obligations of the parties to this contract shall be necessary.

governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by refer-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

(Must be fully completed by offeror) OFFER

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this

W912P7-09-B-0005

PORT OF REDWOOD CITY HARBOR

CHANNEL MAINTENANCE DREDGING

THE CONTRACTOR SHALL FURNISH ALL PLANT, LABOR MATERIAL, EQUIPMENT, ETC.

NECESSARY TO PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS AND

CONDITIONS SET FORTH IN THE CONTRACT TO INCLUDE ALL ATTACHMENTS

THERETO.

BID SCHEDULE - GOVRENMENT FURNISHED SITE

ITEM NO DESCRIPTION QTY UNIT UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 LS $ _________ $__________

0002 Dredging at Redwood City Harbor Channel including transport of the dredged material to Hamilton Off-loader

0002AA Standard Dredging to –30 ft, MLLW 291,200 CY $____________ $____________ at Redwood City Harbor Channel, 210,200

0002AB Overdepth Dredging to –31, ft MLLW 175,000 CY $____________ $____________ Redwood City Harbor Channel, 126,000

Item 0002 subtotal Price (Items 0002AA to 0002AB ) $____________

0003 Dredging at Redwood City Harbor Channel including transport and disposal of the dredged material at the Alcatraz Disposal Site, SF-11

0003AA Standard Dredging to –30 ft, MLLW 81,250 CY $____________ $____________ at Redwood City Harbor Channel

0003AB Overdepth Dredging to –31, ft MLLW 48,750 CY $____________ $____________ Redwood City Harbor Channel, Item 0003 subtotal Price (Items 0003AA to 0003AB ) $____________

GOVERNMNET FURNISHED SITE

TOTAL BID EVALUATION $____________

(Items 0001 + 0002AA + 0002AB +0003AA +0003AB)

00010 - 1

THE CONTRACTOR SHALL FURNISH ALL PLANT, LABOR MATERIAL, EQUIPMENT,

ETC. NECESSARY TO PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE

TERMS AND CONDITIONS SET FORTH IN THE CONTRACT TO INCLUDE ALL

ATTACHMENTS THERETO.

BID SCHEDULE – CONTRACTOR FURNISHED SITE

In order to be responsive to this solicitation, prices shall be submitted on all of the items in the Pricing Schedule, above. At the bidder’s discretion, a bid may also be submitted under this Alternate Pricing Schedule. In the event a bidder elects to submit a price under the Alternate Pricing Schedule, all of the individual items in the Alternative Pricing Schedule shall be completed. At the time of bid the bidder must submit proof acceptable to the Contracting Officer that the Alternate Site is both permitted and has sufficient capacity to handle the estimated volume of material specified in the Bid Schedule- Contractor Furnished Site plus non-paid material in the allowable dredging prism.

Disposal of all materials at a permitted upland disposal site.

ITEM NO DESCRIPTION QTY UNIT UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 LS $ _________ $__________

0002 Dredging at Redwood City Harbor Channel including transport of the dredged material to Hamilton Off-loader and placement at the Contractor Furnished Site

0002AA Standard Dredging to –30 ft, MLLW 291,200 CY $____________ $____________ at Redwood City Harbor Channel, 210,200

0002AB Overdepth Dredging to –31, ft MLLW 175,000 CY $____________ $____________ Redwood City Harbor Channel, 126,000

Item 0002 subtotal Price (Items 0002AA to 0002AB ) $____________

0003 Dredging at Redwood City Harbor Channel including transport and disposal of the dredged material at the Alcatraz Disposal Site, SF-11

0003AA Standard Dredging to –30 ft, MLLW 81,250 CY $____________ $____________ at Redwood City Harbor Channel

0003AB Overdepth Dredging to –31, ft MLLW 48,750 CY $____________ $____________ Redwood City Harbor Channel, Item 0003 subtotal Price (Items 0003AA to 0003AB ) $____________

00010 - 2

CONTRCTOR FURNISHED SITE

TOTAL ALTERNATE EVALUATION PRICE

(Items 0001 + 0002AA + 0002AB +0003AA +003AB ) $_________

00010 - 3

CONTRACT AWARD

A contract will be awarded on the basis of price and other factors to the lowest responsive, responsible bidder in accordance with FAR 52.214-19. Contract award will be made based on the lowest cost to the O&M Dredging Program. In the event a bidder or bidders submit bids under the Alternate Pricing Schedule, the lowest responsive bid submitted under the Pricing Schedule (Total Evaluation Price) will be compared to the lowest bid submitted under the Alternate Pricing Schedule (Total Alternate Evaluation Price).

Notes:

*QUANTITY IS AN ESTIMATED AMOUNT, SEE SECTION 00700, FAR 52.211-18 AND

EFARS 52.211-5000, 52.211-5001, FOR SUBDIVIDED BID ITEMS AND FOR VARIATION

IN ESTIMATED QUANTITIES CONTRACT CLAUSE.

1. Prices must be submitted on all individual items of the Pricing Schedule. Failure to do so may be cause for rejection of bids. Prices may at each Bidder’s discretion be submitted on all individual items of the Alternate Pricing Schedule.

2. If a modification to a price based on unit price is submitted which provides for a lump sum adjustment to the total estimated price, the applications of the lump sum adjustment to each unit price in the Pricing Schedule must be stated. If it is not stated, the bidder/offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the Pricing Schedule.

3. The lump sum, "LS", line items above are not "estimated quantity" line items and therefore are not subject to the Variation in Quantity contract clause.

4. EFARS 52.214-5000 ARITHMETIC DISCREPANCIES

(a) For the purpose of initial evaluation of bids, the following will be utilized in the resolving arithmetic discrepancies found on the face of Pricing Schedule as submitted by the bidder:

1) Obviously misplaced decimal points will be corrected;

2) Discrepancy between unit price and extended price, the unit price will govern;

3) Apparent errors in extension of unit prices will be corrected;

4) Apparent errors in addition of lump-sum and extended prices will be corrected.

(b) For the purpose of bid evaluation, the Government will proceed on the assumption that the bidder intends the bid to be evaluated on basis of the unit prices, the totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.

(c) These correction procedures shall not be used to resolve any ambiguity concerning which bid is low.

5. Bidders must complete and submit attached “Dredging Plant and Equipment Schedule”, forms P.1 and P.2 as part of their solicitation package for bid evaluation. Failure to do so may cause the

00010 - 4

00010 - 5 bid to be considered nonresponsive. The Contractor shall demonstrate that all necessary equipment will be available and committed to this contract.

6. DREDGED QUANTITIES: For payment purposes, all quantities for which the Government will pay under this contract shall be based on the Government pre and post dredge surveys.

7. HAMILTON OFF LOADER OPERATION The Hamilton off Loader is operated by the Manson-Dutra Joint Venture [MDJV] under Contract NO. WP 912P7-07-C-0001, Oakland Navigation Improvement -50 ft Deepening Project Phase 3E, Oakland Inner and Outer Harbor, Alameda and San Francisco Counties. Bidders are advised that the dredged material to be disposed of at the HWRP will be off loaded with a hydraulic offloader, and pumped through several booster pumps and through approximately 35,000 to 40,000 lineal feet of pipeline. As such, the successful bidder is cautioned that its work plan and execution will require coordination with the MDJV and will further require certain equipment and production limitations as described in these contract documents. For coordination of additional requirements and/or further details relating to the Hamilton Off Loader, please contact Manson- Dutra JV, Attention: Terry Hammerwold, Telephone number 415/ 884-2973.

8. BASIS of AWARD: A contract will be awarded to the lowest responsive, responsible bidder in accordance with FAR 52.214-19.

9. In the event a bidder or bidders submit bids under the Bid Schedule – Contractor Furnished Site, the lowest responsive, responsible Contractor Furnished Site – Total Evaluation Bid received will be compared to the lowest responsive, responsible Government Furnished Site – Total Evaluation Bid received. Award will be made to the lowest responsive, responsible bid identified from this comparison.

Port of Redwood City Channel Maintenance Dredging

Technical Specifications San Mateo County, California

DIVISION 1 - GENERAL REQUIREMENTS

TABLE OF CONTENTS

Section 01 11 00 Summary of Work Section 01 32 01 Project Schedule Section 01 32 23 Hydrographic Surveying Section 01 33 00 Submittal Procedures Section 01 35 26 Safety and Occupational Health Requirements Section 01 45 02 Quality Control System (QCS) Section 01 45 04 Contractor Quality Control Section 01 50 00 Temporary Control Facility Section 01 57 20 Environmental Protection

DIVISION 35 – WATERWAY & MARINE CONSTRUCTION

Section 35 20 23 Dredging Section 35 20 23.23 Hopper Dredge Silent Inspector Section 35 20 23.13 Scow Silent Inspector Section 35 20 24 Aquatic Disposal Section 35 20 25 Transportation for Hamilton Off-loader

APPENDICES

Appendix 01 Coastal Zone Management Act Consistency Determination - O&M

Dredging

Appendix 02 Waste Discharge Requirements – O&M Dredging

Appendix 03 Safety Checklists for Floating Plant and Mobile Construction Equipment Inspection

Appendix 04 Letter of Agreement for Consistency Determination NO.CN 9-06

Appendix 05 Dredge Monitoring System Operational Requirements (DDLS)

Appendix 06 Worker's Compensation Claims

Appendix 07 Dredged Material Disposal Site Log

Appendix 08 Silent Inspector Data Form

Appendix 09 Summary Guide for Completing USACE Contractor Monthly

Appendix 10 Acronym

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 INTRODUCTION

This section describes the project specific work to be completed under the contract and the project specific restrictions that apply to the contract.

1.2 PAYMENT PROCEDURES

No separate payment will be made based on this specification section.

1.3 WORK SUMMARY

The work consists of operation and maintenance dredging of the Port of Redwood City Harbor Channel, San Mateo County, California. All dredging, material transportation and material placement shall be in accordance with the project plans, specifications, permits, regulatory guidance and applicable contract clauses. Dredged materials excavated from the Redwood City Harbor Channel as described in item no. 0002 (0002AA and 0002AB) of the bid schedule shall be transported and off loaded at the Hamilton Wetland Restoration Project (HWRP). The Government will provide off loading at the HWRP. Dredged materials excavated from the Redwood City Harbor Channel as described in item no. 0003 (0003AA and 0003AB) shall be transported, delivered and disposed at the Alcatraz Disposal Site, SF-11, as described in paragraph in 3.7, Section 35 20 23, and paragraph 3.4.3 and 3.5.3, Section 35 30 24. The Contractor may provide proposals for fully permitted beneficial use upland alternatives other than those placement sites listed herein.

1.4 SEQUENCE OF WORK

1.4.1 Reaches shall be completed sequentially, starting from the inner-most reach out towards the Bay.

1.4.1.1 The Contractor must take all material in a Reach, to the same disposal site, until the contract quantity for that Reach and/or the disposal site is completed. To change disposal sites or Reaches, the contractor must request a condition or post-dredge survey, so the volume taken to the respective disposal sites can be accurately calculated, and then receive permission from the Contracting Officer before continuing dredging in the area surveyed. The contractor must submit a dredging plan with a schedule, indicating what material, volume and Reach, is going to be taken to HWRP, and what material, volume and Reach, is going to be taken to Site-11. This plan must be approved by the contracting Officer prior to the start of dredging.

1.4.2 All dredging, transport and disposal operations shall be in accordance with the regulatory

Page 1 of 5 Summary of Work Section 01 11 00 guidance included in the appendices of these specifications. The Contractor shall commence dredging within 25 days of NTP.

1.4.3 Time Restriction: The environmental window starts on June 1, 2009 and ends on December 31, 2009. No dredging and disposal operations shall occur beyond the environmental window. If permitted the dredging and disposal operation shall start on September 1 October 7, 2009 and complete on December 31, 2009.

1. 5 PERMITS.

1.5.1 Under Contract Clause “PERMITS AND RESPONSIBILITIES,” the Contractor is obligated to obtain and comply with all licenses and permits required by Federal, State, and local laws, codes, and regulations.

1.5.2 The Government has obtained the necessary dredging permits and approvals, including certification from the State Regional Water Quality Control Board and the Environmental Protection Agency, for dredging and disposal of dredged materials at the Government-furnished Hamilton Wetland Restoration Site.

1.5.3 The Contractor shall be responsible for making his own arrangements for permits, other than those listed herein, required for completing the work under this contract.

1.6 ORDER OF WORK.

1.6.1 General. With reference to Contract Clause "SCHEDULE FOR CONSTRUCTION CONTRACTS" and Special Clause "COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK," the Contractor shall mobilize adequate labor, equipment, materials, and supplies and make a determined and continuous effort to complete the contract work within the time specified.

1.7 PUBLIC SAFETY.

Under the Contract Clause "PERMITS AND RESPONSIBILITIES", the Contractor shall provide guards as required to provide protection in the interest of public safety. Whenever the Contractor's operations create a condition hazardous to the public, he shall furnish at his own expense and without cost to the Government, such guards as are necessary to give adequate warning to the public of any dangerous conditions to be encountered, and he shall furnish, erect, or maintain such lights, signs and other devices as are necessary to prevent accidents and to avoid damage or injury to the public. Flagmen and guards, while on duty and assigned to give warning to the public that the dredging is being accomplished, and of any dangerous conditions to be encountered as a result thereof, shall be equipped with red wearing apparel and a red flag.

Signs, flags, lights, and other warning and safety devices shall conform to applicable city, county, and state requirements. Should the Contractor appear to be negligent in furnishing adequate warning and protective measures, the Contracting Officer will direct attention to the existence of a hazard, and the necessary warning and protective measures shall be furnished and installed by the Contractor without additional cost to the Government. The installation of any

Page 2 of 5 Summary of Work general illumination shall not relieve the Contractor of his responsibility for furnishing and maintaining all devices necessary to provide protection to all parties concerned.

1.8 MEETINGS.

1.8.1 Pre-Dredge Conference: After award of contract, a pre-dredging conference will be held at such time and location as determined by the Contracting Officer for purposes of discussing and developing mutual understanding between the Contracting Officer or his authorized representative and the Contractor's Representatives regarding the terms, conditions, and requirements of the contract. Members of the conference from the Government will include the quality assurance staff, the Contracting Officer or his authorized representative, and construction staff. Members from the Contractor shall include the dredge master, chief hydrographic surveyor, and the quality control staff. The discussion will include, but will not be limited to, the following:

• Contractor supervisory and quality control project staff.

• Correspondence procedures.

• Accident Prevention Plan.

• Pollution control program.

• Quality Control and Hydrographic Surveying.

• Project scheduling and payment procedures.

• Resident Management System (RMS-QC).

• Other subjects that may be of interest to the contracting parties.

• Schedule of Weekly Meeting.

1.8.2 Weekly Meetings: Weekly construction/survey/coordination/progress meetings shall be held between the Contractor, Contracting Officer or authorized representative, and Government personnel. Minutes of the weekly meeting shall be prepared by the Contactor’s CQC Manager and submitted to the Contracting Officer within 24 hrs.

1.9. PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS.

1.9.1 General. The Contractor's attention is directed to the possible existence of pipelines or public utilities or private improvements shown or not shown on the drawings which may be buried within the limits of the work or adjacent thereto and the existence of several bridges crossing the river. Care shall be taken to preserve and protect any such improvements from injury or damage during construction operations. Utilities or improvements, whether buried or not, which cannot be determined to exist through visual inspection by the Contractor, if inadvertently damaged by the Contractor's operations, shall be promptly repaired or replaced by the Contractor, and an equitable adjustment in the amount due under the contract will be made as provided in the contract. The Contractor shall assume full responsibility for reimbursing the owners for any damage to their properties, utilities, or improvements, or interference with their services caused through his operations. The Contractor is not relieved from the responsibility set forth in Contract

Page 3 of 5 Summary of Work

Clause "SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK," except as provided above.

1.10 LAYOUT OF WORK.

The Contractor shall lay out his work from Government-established monuments and gages as shown on the drawings and shall be responsible for all measurements in connection therewith.

The Contractor shall furnish, at his own expense, all templates, platforms, equipment, markers and labor as may be required in laying out any part of the work from the gages established by the Government. The Contractor will be held responsible for the execution of the work to such lines, grades and gages as may be established or indicated by the Contracting Officer. It shall be the responsibility of the Contractor to maintain and preserve all monuments and other marks established by the Contracting Officer until authorized to remove them. It is incumbent upon the contractor or their surveyor to check the accuracy of monuments as the Government does not guarantee their accuracy. If such marks are destroyed by the Contractor or through his negligence prior to their authorized removal, they may be replaced by the Contracting Officer at his discretion. The expense of replacement will be deducted from any amounts due, or to become due, to the Contractor.

1.11 SAFETY OF STRUCTURES.

The Contractor shall use reasonable and proper care in the prosecution of the work to assure the stability of piers and other structures lying on or adjacent to the site of work, insofar as they may be jeopardized by the dredging operations and on account of moving or mooring of equipment. The Contractor shall make good all damages resulting from the moving and mooring of his equipment and from dredging operations insofar as such damages may be caused by variations in locations and/or depth of dredging below that ordered by the Contracting Officer.

1.12. PAYMENT.

No separate payment will be made for the work covered under this section of the specifications, and all costs in connection therewith will be considered a subsidiary obligation of the Contractor.

1.13 CONTRACTOR PERFORMANCE EVALUATIONS.

In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor's performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. The USACE uses the web-based Construction Contractor Appraisal Support System (CCASS) to document contractor's performance and prepare performance reports. After an evaluation (interim or final) is written up by the USACE, the Contractor may access, review and comment on the evaluation for a period of 30 days. Accessing and using CCASS requires Public Key Infrastructure (PKI) certification. The certification is a Department

Page 4 of 5 Summary of Work

Page 5 of 5 Summary of Work of Defense requirement and was implemented to provide security in electronic transactions. This certification is purchased from an External Certificate Authorities (ECA) vendor. Contractor access to CCASS is required for Contractor participate in the performance evaluation process.

PKI certification is required for Contractor access to CCASS. PKI certification is the sole responsibility of the Contractor. Current information about the PKI certification process and known PKI vendors can be found on the web site: http://www.cpars.csd.disa.mil/.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

SAFETY IS A TEAM EFFORT

SECTION 01 32 23

HYDROGRAPHIC SURVEYING

1.1 DESCRIPTION OF WORK.

The Contractor shall use hydrographic surveys to perform Quality Control (QC) of the dredging, to update the Project Schedule, the Dredging Plan, to determine the volume of material removed for progress payment requests and to provide information to the Contracting Officer or to the Contracting Officer’s Representative (COR) for managing this contract.

1.1.1 The Contractor shall comply with the procedures, standards and quality control criteria in EM 1110-2-1003 in performing hydrographic surveys for this contract.

1.1.2 If there is a conflict between these specifications and EM 1110-2-1003, the more stringent requirements shall apply.

1.2 REFERENCES.

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

Department of the Army, U.S. Army Corps of Engineers

EM 1110-2-1003 Hydrographic Surveying EM 1110-1-2909 Geospatial Data and Systems

1.3 SUBMITTALS.

Government approval is required for submittals with a "G" designation. Submittals having an “I” designation are for information only. The following shall be submitted in accordance with SUBMITTAL PROCEDURES Section:

SD-01: Preconstruction Submittals

Equipment Data G 01 32 23 - 1.5.4 Software G 01 32 23 - 1.6

SD-06: Test Reports

Basic Survey Documentation Submittal I 01 32 23 - 3.3.1 Progress Payment Survey Documentation G 01 32 23 – 3.3.3

1.4 RESPONSIBILITIES.

Hydrographic Surveying Page 1 of 10 Section 01 32 23

The Contractor shall provide all resources necessary to perform all contract-required surveys and to process and use the surveying data.

1.5 SURVEY EQUIPMENT.

The Contractor shall furnish and utilize ample, adequate surveying equipment and controls to provide assurance that all material existing within the required dredging area has been removed and the disposal area shaped, as required. Hydrographic surveying equipment will include, but not be limited to, echo sounding, motion sensing, horizontal positioning, tide monitoring and velocity probing equipment as prescribed in EM 1110-2-1003 Table 9-6 or 10-1 and chapter 16, as appropriate.

1.5.1 Sounding: The Contractor shall perform echo sounding for depth with an integrated hydrographic survey system utilizing a standard to the industry depth sounder adjustable for speed of sound corrections. The manufacturer’s stated precision for the depth sounder shall be

0.1 foot or less.

1.5.2 Positioning: Positioning shall be accomplished by a fully integrated and automated hydrographic survey system utilizing a standard to the industry Differential Global Positioning System (DGPS) with a manufacturer’s stated positional accuracy of one (1) meter or less. DGPS corrections shall be obtained from the same geostationary satellite station or base station for all surveys.

1.5.3 Tide Monitoring: The Contractor shall provide an approved tidal level monitoring system. This system shall be adjusted to correspond with the dredging area tidal zone and shall be located as indicated in the contract documents. Real Time Kinematic (RTK) Differential GPS may be used to obtain accurate, real-time elevations (depths) without observing tidal data.

1.5.4 Equipment Data: Prior to the start of dredging operations, the Contractor shall submit data on the surveying equipment to the Contracting Officer, for information only. Typical information shall, as a minimum, include the name, model, and year of manufacture of the electronic equipment, the electronic frequencies of the horizontal positioning and depth finding equipment, and the manufacturer's stated positioning accuracy and capability of the equipment proposed for usage. The vessel/equipment that performs a survey shall be recorded in the Survey QC Log, Attachment 1 to this Section.

1.6 SOFTWARE

The Contractor shall use site design or survey software in the integrated hydrographic survey system. The software shall support the varied Corps dredging templates outlined in Chapter 15 of EM 1110-2-1003 and shall be capable of computing dredged quantities using an Average End Area (AEA) volume technique; the Government will calculate volumes using Hypack. Prior to the start of dredging operations, the Contractor shall submit data on the surveying software to the Contracting Officer, for information only.

PART 2 PRODUCTS – NOT APPLICABLE

Page 2 of 10 Hydrographic Surveying Section 01 32 23

PART 3 EXECUTION

3.1 SURVEYING PROCEDURES.

The Contractor shall perform surveys using the line files provided by the Government and the vertical and horizontal controls specified in the contract documents. The hydrographic surveying procedures, including, but not limited to positioning modes, electronic position system calibration, accuracy requirements, depth measurements calibration, and data reduction, adjustment, processing and plotting shall conform, at a minimum, to the procedures specified in EM 1110-2-1003 and the procedures specified herein.

3.1.1 QC Surveys: The Contractor shall conduct QC surveys at least once per week during weeks in which there is dredging or disposal but may schedule surveys more frequently to maintain the quality of the dredging and disposal. The Contractor shall also conduct QC surveys when directed by the Contracting Officer.

3.1.2 Progress Payment Surveys: The Contractor shall use 200-210 KHz survey data to measure quantities for payment requests. The top of the return signal trace shall be the point of interpretation of soundings. Progress payment survey shall include a separate longitudinal profile of the left and right toes and the project centerline for correlation with the cross-line surveys.

3.1.3 Government Observers: The Contractor shall furnish, upon request of the Contracting Officer, suitable transportation from all points on shore designated by the Contracting Officer to and from the various pieces of plant, and to and from the dredging and disposal areas. Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific transportation facilities may be furnished and maintained by the Contracting Officer, and the cost thereof will be deducted from any amounts due or to become due the Contractor.

3.1.3.1 The Contractor shall keep the Government informed about Contractor surveying activities, including provisions for onsite Government observers. The Government will have the option of accompanying the Contractor on these surveys.

3.1.3.2 The Contractor shall notify the Government two working days prior to performing a progress payment survey.

3.1.4 Onsite Quality Assurance (QA): When directed by the Contracting Officer, the Contractor shall perform QC surveys and provide cross-sectional views of the edited, tide-level-adjusted survey data to the Government on site. When directed by the Contracting Officer, the Contractor shall provide print outs of the cross-sectional plots on site.

3.1.5 Calibration and Controls:

3.1.5.1 Calibration: The Contractor shall determine how often to calibrate taking into account time on station, size and variability of the area being surveyed, weather, tides, maritime traffic, Page 3 of 10 Section 01 32 23 etc. The location/position/time of velocity probes and/or bar checks shall be recorded in the Survey QC Log.

3.1.5.2 Onsite Vessel-to-Vessel Calibration: If requested, the Government survey vessel will participate in one vessel-to-vessel onsite calibration session with the Contractor’s survey vessel.

Survey lines taken from the Vessel-to-Vessel Calibration shall be compared and checked on site for accuracy and consistency. The calibration session will be scheduled by the Government in conjunction with the Contractor.

3.1.6 Survey Line Integrity: Survey soundings shall not deviate more than plus or minus 10 feet off station alignment. Obstructions, such as docks, wrecks and docked ships, shall be identified and the Contractor shall conduct additional soundings on the backside of obstructions, where possible, to complete sounding lines. Incomplete and inaccurate data, such as, lines outside survey position limits, shall be resurveyed, preferably on the same survey day.

3.2 GOVERNMENT SURVEYS.

The Government will use 200-210 KHz survey data to measure quantities for payments.

3.2.1 Pre-dredge Survey: The bathymetric drawings in the contract are believed to accurately represent conditions existing at the time indicated on the plans but the depths shown thereon will be updated, as required, by a pre-dredge Government survey taken prior to the start of dredging.

The Government will perform the survey for all Reaches, which are identified in the Dredging section of these specifications. A separate pre-dredge survey will not be performed for each Reach individually or at staggered times. The Government will provide the Contractor copies of the pre-dredge survey raw and edited data files. All data shall have the Julian date as file extensions.

3.2.2 Post-dredge Survey: As soon as practicable after completion of a Reach, the completed work will be thoroughly examined at the Government’s cost and expense by soundings.

3.2.2.1 Request for Survey: The Contractor shall notify the Government 7 days in advance of completing a Reach. The Contractor shall ensure that the Reach is ready for a final acceptance survey before requesting the Government to perform the post-dredge survey of the Reach. The Contractor shall submit in writing a Request for Reach Acceptance Survey (in Attachment 2 to this Section) accompanied by raw and edited survey data and cross-sectional plots showing no material in the channel above project depth.

3.2.2.2 Acceptance of Reach (es) will be in writing from the Contracting Officer based on the Government post-dredge survey data. Determination of quantities removed, and to be paid for, in the areas specified, after once having been made, will not be reopened, except on evidence of collusion, fraud, or obvious error.

3.2.2.3 Reach Rejection: If the Government post-dredge survey finds the reach to be unacceptable, the Contractor shall resume dredging until the work is complete.

Page 4 of 10 Hydrographic Surveying

3.2.2.3.1 The Contractor is responsible for time required for dredging to remove shoals, lumps or other lack of contract depth and for the time required to resurvey the rejected Reach.

3.2.2.3.2 When the dredging is complete, the post-dredge survey process, starting with the Contractor’s written Request for Reach Acceptance Survey, is then repeated except that the Contractor is liable for subsequent Government survey costs. The Contractor shall be assessed $7,000 per day that the Government spends on post-dredge surveys of a Reach that is rejected after the first Government post-dredge survey. The Government’s efforts include time spent on station waiting, surveying time and post-survey data processing and reporting. A partial day of survey efforts by the Government will be billed as a full day.

3.2.3 Contractor Survey Certification.

3.2.3.1 Contractor’s Representative: The Contractor shall provide a representative on board the Government survey vessel for all pre- and post-dredge surveys. The representative shall be knowledgeable of hydrographic surveying procedures, techniques, equipment, calibration methods and accuracy limitations. The representative shall observe and review, in progress, the adequacy and accuracy of the survey for payment purposes and for the potential existence of collusion, fraud or obvious error in the data. The onsite review shall include a comparison of the Government survey data and the Contractor’s survey data for the same area.

3.2.3.2 Survey Certification: Immediately upon completion of a Government pre- or post-dredge survey, the Contractor’s representative shall attest to an acceptable survey by signing the Certification of Government Survey, Attachment 2 to this section. This certification will be based on the representative’s onsite review of the survey and determination that the survey contains no evidence of collusion, fraud or obvious error.

3.2.3.3 Unacceptable Survey: In the event the Contractor’s representative observes (and quantifies) specific documentary evidence of collusion, fraud or obvious error, the survey will be immediately rerun. The resurvey will be run over the full Reach and will supersede previously run surveys in their entirety. If the resurvey is unacceptable, the Contractor shall meet with the Contracting Officer to expeditiously resolve the issue(s) causing rejection of the survey. The Contractor shall be liable for the Contractor’s costs, including but not limited to standby costs, for the time required to resolve acceptability of the survey.

3.2.3.4 Reinstating Unacceptable Survey: The Contractor may certify a survey previously judged unacceptable; however, the Contractor shall reassess/reevaluate within 24 hours after the unacceptable survey was performed and prior to the initiation of a resurvey based upon identified collusion, fraud or obvious error.

3.2.3.5 Refusal to Certify: This paragraph describes the consequences should the Contractor refuse to attest to the acceptability of a Government survey without identifiable collusion, fraud or obvious error.

3.2.3.5.1 Uncertified Pre-dredge Survey: The Contractor shall not commence dredging until the Contractor and the Contracting Officer have met and resolved the basis for the refusal to

Page 5 of 10 Section 01 32 23 certify. The Contractor shall be liable for any dredging performed prior to obtaining an acceptable survey. If a resurvey is performed and accepted, prior dredging will not be measured, estimated or paid for.

3.2.3.5.2 Uncertified Post-dredge Survey: The Contractor’s work will not be accepted and the contract completion date will not be extended. The Government will not measure, estimate or paid for any material accretion, which might occur over time. If the work has not been accepted as complete on or before the contract completion date, the Government will assess liquidated damages until the post-dredge survey is certified and the work is accepted as complete and in compliance with contract requirements.

Certification Costs: The Contractor shall be liable for the Contractor’s own costs, including but not limited to standby costs, for the time required to resolve the refusal to certify when there is no evidence of collusion, fraud or obvious error and the resultant delays shall not be the basis for a time extension of the contract.

3.2.4 QA Surveys: The Government may perform surveys to assure the quality of the dredging and disposal operations.

3.3 SURVEY DATA

3.3.1 Basic Survey Documentation: The Contractor shall submit raw and edited electronic point files, the field notes, tide records and the Survey QC Log for all Contractor-performed surveys. The Contractor shall submit data for each Contractor-performed survey within two (2) working days of survey completion.

3.3.1.1 Survey QC Log: The Contractor shall complete a Survey QC Log for all Contractor-performed surveys. The Survey QC Log shall include, as a minimum, the survey personnel, equipment, controls, layout, calibrations, the weather/sea conditions, survey soundings accomplished and the names of the files with the survey data. The Survey QC Log shall be included with the electronic submission and a copy shall be attached to the daily CQC Report. In addition, for progress payment surveys, the Contractor, or a designated representative, shall sign the Certification of Progress Payment Survey (Block 3) and attach a copy to the payment request.

3.3.1.2 Electronic Submission: Within two working days of the completion of a survey, the Contractor shall provide the Basic Survey Documentation on write-once CD-ROMs to the Government. All electronic survey data shall contain a string of information in the title that clearly identifies the contents of the data. The string shall uniquely identify the project and reach and the data itself shall have the Julian date as file extensions. The Contractor will, if possible, also provide the survey data in an email attachment, usually in a zip file. The Government will provide email addresses at the Pre-construction Conference.

3.3.2 Field Data: The Government may require additional information as described below.

3.3.2.1 CAD Drawings: If required by the Contracting Officer to support the weekly review of the Dredging Plan, the Contractor shall submit an updated work plan for dredging as a CAD

Page 6 of 10 Hydrographic Surveying drawing in hard and electronic (dwg) form. The drawing shall contain project channel data and show the areas dredged, over time, and the areas to be dredged in the next week.

3.3.2.2 Cross-section Plots: The Contractor shall provide cross-sectional plots as directed by the Contracting Officer. Each cross-section will show the project template including project depth, side slopes extending from the project depth line, and the contract pay lines. A legend with the dates of each survey shall be included.

3.3.2.3 Other Data: The Contractor shall provide survey data comparisons, usually hard copies of cross-sectional overlays, or other survey material/data as directed by the Contracting Officer.

3.3.3 Progress Payment Survey Documentation: Within five (5) working days of a progress payment survey, the Contractor shall submit the documentation described below in electronic and printed form.

3.3.3.1 Tabulations: The Contractor shall submit the calculations and a tabulation of quantities.

3.3.3.2 Cross-sectional Plots: The Contractor shall provide the cross-sectional plots, one cross-section per 8½ X 11 sheet, in hard copy and in electronic pdf files. Each section will show the project template including project depth, side slopes extending from the project depth line and the maximum pay line. The pre-dredge and progress payment survey lines will be shown on the same section and shall be clearly discernible from each other.

3.3.3.3 Electronic Record: Electronic copies of surveys performed including point files, calculations and a plot of the soundings shall be provided. The electronic point file shall be the same file that the Contractor uses for volume computations. The raw, unedited data, along with all files and associated data used for editing, along with a copy of the survey documentation, updated as necessary, shall be submitted on write-once CD-ROMs to the Government. The Contractor shall provide a description of any changes that have been made to the originally submitted survey documentation. The Contractor will, if possible, also provide the survey data in an email attachment, usually in a zip file.

3.3.3.4 Printed Record: Printed copies of volume tabulations and the cross-sectional plots shall be submitted with the Contractor’s payment request. The Contracting Officer will reject payment requests for dredging that are not supported by verified survey data and calculations.

3.3.3.5 Data Review: The Government will review the survey documentation for clarity and completeness before accepting the progress payment request for processing in accordance with contract clause 52.232-27: Prompt Payment for Construction Contracts.

3.3.4 Final Payment Survey Documentation: The survey documentation to be submitted with a final payment request is identical to the requirements for Progress Payment Survey Documentation except that the Contractor shall use the Government post-dredge survey data instead of the Contractor’s progress payment survey data.

3.4 QUANTITY CALCULATIONS

Page 7 of 10 Section 01 32 23

Page 8 of 10 Hydrographic Surveying

3.4.1 Volume Calculations: The Contractor shall calculate the volume of material dredged using the AEA volume technique in EM 1110-2-1003 as per the Contour Method dredge payment template. The Contractor shall submit the calculations and a tabulation of the quantities described below with each payment survey.

3.4.1.1 Available Material: The material available before dredging will be calculated from the Government pre-dredge survey data.

3.4.1.2 Payable Quantity: The payable quantity is the difference between the available material and the quantity remaining to the maximum pay line. Material quantities shall only be computed over the dredged areas.

3.4.1.3 Progress Payment Quantity: The material quantity for progress payments will be ninety percent (90%) of the payable quantity calculated using the Contractor’s progress payment survey and the Government’s pre-dredge survey, less any previously paid quantities.

Final Payment Quantities: The final payment quantities will be 100% of the payable quantity calculated from the Government pre-dredge and post-dredge surveys. The Government surveys shall be used unless there is evidence of collusion, fraud, or obvious error, documented.

3.5 PAYMENTS.

Work included in this section of the specifications for which no specific contract line item is included in the Pricing Schedule of the contract shall be considered an associated subsidiary obligation. No separate payment will be made for associated subsidiary obligations.

-- End Section --

Attachment 1 Survey Quality Control (QC) Log

Contract Name. Contract #.

Block 1 – Personnel and Equipment

Surveyor. Vessel Name/Length.

Survey Technician. Vessel Operator.

Survey Assistant, if any. Other Personnel, if any.

Surveying SW/Version. Line File ID.

Depth Sounder. Motion Compensator.

Tidal Level Recording Unit. Velocity Probe.

DGPS.

Other Equipment.

Block 2 – Survey Parameters

Survey Date. Survey Purpose.

Survey Location. Weather/Sea State.

Tide Gauge Location. DGPS Location.

Survey File ID. Stations Surveyed.

Calibration Time/Location: Bar Check and/or Velocity Probe.

Calibration Notes:

Obstacle Locations.

Observations.

Remarks, if any.

Block 3 – Certification of Progress Payment Survey

I certify that the payment survey was performed by me or under my direct supervision and that the survey was conducted in accordance with the systematic/procedural methods and techniques described in the contract documents. The observed, recorded and edited data are fully and finally acceptable for determining and measuring contract performance and payment. Any exceptions are noted in the box to the right.

Signed.

Exception(s) to the Certification

Block 4 – Government Observations

Government Observer, if any. Government Observations, if any.

Page 9 of 10 Section 01 32 23

Attachment 2

Contract #. _______________________________________ Survey of Reach #. ______________ Survey Date. ___________________ Certification of Government Survey* I have fully observed the performance of the Government survey and have determined, based on my review of EM 1110-2-1003 requirements and of Contractor survey data for the same area, that the data contains no evidence of collusion, fraud, or obvious error.

The recorded data, including calibration corrections thereto, have been obtained in accordance with the systematic/procedural methods and techniques described in the contract documents. All known and unknown systematic and random errors have been minimized consistent with: (1) the relative precision errors of the equipment utilized; and