Pricing Matrix Guide Jan 2026.pdf
PDF 386 KB Posted
- Attached to
- Green Bay Harbor Dredging SATOC
- Solicitation number
- W912P626BA009
About this file
This document is a How-to Guide for completing the Green Bay Harbor Dredging Single-Award Task Order Contract (SATOC) Pricing Matrix. The guide provides detailed instructions for contractors to price maintenance dredging services across five ordering periods, with three quantity ranges for each Contract Line-Item Number (CLIN). The pricing matrix covers mobilization/demobilization (CLIN 0001AA) as a lump-sum per event and maintenance dredging (CLINs 0001AB through 0006) priced per cubic yard for specific dredging locations and placement areas.
Key instructions include entering fully burdened unit prices that include all costs, pricing each CLIN independently, and providing prices for all ranges and ordering periods. The Government will use a weighted evaluation method to compare prices, with pre-assigned weights for each range reflecting estimated work likelihood. Contractors are warned against leaving cells blank, zero-pricing ranges, embedding mobilization costs in dredging prices, or modifying protected cells. The final pricing will be used directly for future task orders, with no repricing or re-balancing allowed after contract award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Green Bay Dredging FY26 Price Matrix Map.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
How-to Guide: Completing the Green Bay Harbor Dredging SATOC Pricing Matrix
1. Purpose of This Guide
This How-to Guide provides detailed, step-by-step instructions for completing the Green Bay Harbor Dredging SATOC Pricing Matrix Excel workbook.
The pricing matrix is the sole pricing vehicle used by the Government to:
Evaluate offers for award of the SATOC
Establish firm unit prices for future task orders
Prevent unbalanced bidding
Allow fair, apples-to-apples comparison across all offerors
Failure to follow these instructions may result in pricing that is non-comparable, mathematically unbalanced, or subject to clarification or rejection.
2. General Rules for Completing the Matrix (Read First)
Before entering any prices, contractors must understand the following fundamental rules:
1. Only enter values in cells intended for contractor input
Do not modify formulas, weights, quantities, headings, or shaded cells.
Cells not intended for input are locked or pre-populated for Government use.
2. All prices must be fully burdened
Include labor, equipment, fuel, overhead, profit, insurance, bonds, supervision, and all incidental costs.
No assumptions will be added later via task order negotiations.
3. Unit prices must stand on their own
Do not shift costs between CLINs (e.g., loading mobilization costs into dredging CLINs).
Each CLIN must be priced independently and realistically.
4. The pricing matrix is not a bid schedule for a single project
It represents a range of potential future work scenarios across multiple years.
You are pricing capability, not a specific dredging job.
3. Overview of the Pricing Matrix Structure
The pricing matrix is organized horizontally by Ordering Periods and vertically by CLINs and Quantity Ranges.
3.1 Contract Line-Item Numbers (CLINs)
The matrix includes the following CLINs:
CLIN 0001AA – Mobilization and Demobilization
CLINs 0001AB through 0006 – Maintenance Dredging and Placement
Each dredging CLIN corresponds to a specific placement area (Areas A–F per the solicitation drawings and map).
Each CLIN is priced separately for each ordering period and quantity range.
3.2 Ordering Periods
The contract contains five (5) distinct ordering periods, representing potential work across the life of the SATOC.
Contractors must provide pricing for all five ordering periods.
Pricing may increase or decrease between periods based on anticipated escalation, efficiency, or market conditions.
Leaving any ordering period blank is not permitted.
3.3 Quantity Ranges
For each CLIN and ordering period, the matrix includes three (3) quantity ranges.
These ranges represent potential task order sizes, not guaranteed volumes.
Range 1 – Small-volume scenario
Range 2 – Medium-volume scenario
Range 3 – Large-volume scenario
You must enter a unit price for each range, even if you expect pricing to be similar.
3.4 Weights (Government Use Only)
Each range includes a pre-assigned weight that reflects the Government’s estimated likelihood that work will fall within that range.
Contractors must not edit, override, or reinterpret these values
4. Step-by-Step Instructions
Step 1: Enter General Information
At the top of the pricing matrix:
Enter the NAME OF OFFEROR
Enter the DATE
No other header fields should be modified.
Step 2: Pricing CLIN 0001AA – Mobilization and Demobilization
4.2.1 What This CLIN Represents
CLIN 0001AA represents one complete mobilization and demobilization event, including:
Transportation of plant and equipment
Assembly and disassembly
Site access, staging, and removal
Crew mobilization and demobilization
Any costs necessary to begin and complete dredging operations
This CLIN is priced on a lump-sum, per-event basis.
4.2.2 How the Ranges Work for Mobilization
For CLIN 0001AA, the three ranges represent the number of times the Government may order a mobilization during a single ordering period:
Range 1: One (1) mobilization event
Range 2: Two (2) mobilization events
Range 3: Three (3) mobilization events
Each range requires a unit price, but that unit price is always the price for ONE mobilization event.
Important:
You are not entering a total price for multiple mobilizations.
You are entering the price for one mobilization under each scenario.
4.2.3 What Unit Price to Enter
For each ordering period and each range:
Enter your all-inclusive lump-sum price for one mobilization/demobilization
You may:
Use the same price across all ranges or
Adjust pricing to reflect efficiencies or risks associated with multiple mobilizations
4.2.4 Why This Structure Exists (Key Clarification)
The Government recognizes that the number of mobilizations cannot be predicted in advance.
The weighted range structure:
Allows evaluation based on the most likely scenarios
Prevents front-loading or artificially deflating prices
Discourages unbalanced bidding
Ensures all offers are evaluated on a consistent basis
Contractors should focus on pricing a fair and reasonable mobilization event, not attempting to “game” the likelihood of mobilization frequency.
Step 3: Pricing CLINs 0001AB through 0006 – Maintenance Dredging
4.3.1 What These CLINs Represent
CLINs 0001AB through 0006 cover maintenance dredging and placement, priced on a per cubic yard (CY) basis.
Each CLIN corresponds to:
A specific dredging location
A specific placement area
Distinct operational and logistical considerations
4.3.2 How to Enter Unit Prices
For each CLIN, each ordering period, and each quantity range:
Enter a unit price per cubic yard (CY)
This unit price is what the Government will pay if the task order quantity falls within that range
4.3.3 Understanding the Quantity Ranges
The quantity ranges represent total dredged volume for a task order, not incremental pricing.
Example (Illustrative Only):
If the ranges are:
Range 1: 0 – 30,000 CY
Range 2: 30,000 – 70,000 CY
Range 3: 70,000 – 80,000 CY
And the task order quantity is 45,000 CY:
The Range 2 unit price applies to all 45,000 CY
Pricing does not tier across ranges
4.3.4 Pricing Expectations
Unit prices may decrease with higher volumes to reflect economies of scale
Prices must remain reasonable and defensible
Extreme price swings between ranges may be evaluated for balance and realism
5. Common Mistakes to Avoid
Contractors should not:
Leave cells blank
Zero-price any range
Embed mobilization costs inside dredging CLINs
Assume the Government will normalize or adjust prices
Modify weights, formulas, or quantities
Price one range unrealistically to offset another
6. How the Government Uses This Matrix
The Government will:
1. Apply the stated weights to each range
2. Calculate a weighted evaluation price
3. Compare total evaluated prices across all offerors
4. Use awarded unit prices directly for future task orders
No repricing or re-balancing will occur after award.
7. Final Contractor Checklist
Before submission, confirm that:
☐ All CLINs are priced
☐ All five ordering periods are completed
☐ All ranges contain unit prices
☐ Mobilization is priced as a single-event lump sum
☐ Dredging is priced per cubic yard
☐ No protected cells were modified