C04 - Abstract of Bids Breakdown (26BA007 Michigan City Breakwater Repairs) 31-Mar-2026.xlsx
XLSX spreadsheet 13 KB Posted
- Attached to
- Michigan City Breakwater Repairs
- Solicitation number
- W912P626BA007
About this file
This is a Bid Abstract for the Michigan City Harbor Detached Breakwater Repairs project (Solicitation W912P626BA007), issued by the Department of the Army Corps of Engineers Engineering District Chicago. The abstract presents pricing data from five contractors competing for base work and optional work scope, with bids received on March 31, 2026.
The base work scope includes mobilization/demobilization valued between $104,133 and $1,183,000 across bidders, and Type A stone placement for 700 tons (560 tons initial plus 140 tons additional) with unit prices ranging from $251 to $936 per ton. Optional work items consist of three separate Type A stone placement tasks totaling 600 tons (250 tons, 250 tons, and 100 tons respectively), with unit prices between $250 and $581.72 per ton. Total base bid amounts ranged from $417,173.32 to $1,544,391.00, while total bids including options ranged from $756,205.32 to $2,017,191.00. The five competing contractors are Midwest Marine Contractors, Roen Salvage Company, Great Lakes Docks and Materials, Agate Construction Co., and one additional unnamed contractor. The project involves marine dredging and stone placement services for harbor breakwater repairs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C04 Abstract of Bids - 1409 Michigan City Breakwater Repairs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Abstract
| Title: | Bid Abstract | |||||
| Project Name: | Michigan City Harbor Detached Breakwater Repairs FY25 | |||||
| IGE | Midwest Marine Contractors | Roen Salvage Company | Great Lakes Docks and Materials | Agate Construction Co. |
| ITEM | DESCRIPTION | QTY | U/M | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | |||
| BASE WORK | ||||||||||||||||
| 00 | 01 | MOBILIZATION / DEMOBILIZATION | 1 | JOB | $ 889,191.00 | $ 889,191.00 | $ 104,133.32 | $ 104,133.32 | $ 488,200.00 | $ 488,200.00 | $ 428,507.00 | $ 428,507.00 | $ 1,183,000.00 | $ 1,183,000.00 | ||
| 00 | 02 | STONE PLACEMENT | ||||||||||||||
| 00 | 02 | A | A | TYPE A STONE PLACEMENT - First 560 Tons | 560 | TONS | $ 936.00 | $ 524,160.00 | $ 447.20 | $ 250,432.00 | $ 251.00 | $ 140,560.00 | $ 400.00 | $ 224,000.00 | $ 255.00 | $ 142,800.00 |
| 00 | 02 | A | B | TYPE A STONE PLACEMENT - Over 560 Tons | 140 | TONS | $ 936.00 | $ 131,040.00 | $ 447.20 | $ 62,608.00 | $ 251.00 | $ 35,140.00 | $ 400.00 | $ 56,000.00 | $ 255.00 | $ 35,700.00 |
Total Base $ 1,544,391.00 $ 417,173.32 $ 663,900.00 $ 708,507.00 $ 1,361,500.00
| OPTION BID ITEMS | ||||||||||||||
| OPTION ITEMS | $ - 0 | |||||||||||||
| 00 | 03 | TYPE A STONE PLACEMENT - A | 250 | TONS | $ 788.00 | $ 197,000.00 | $ 561.72 | $ 140,430.00 | $ 250.00 | $ 62,500.00 | $ 400.00 | $ 100,000.00 | $ 255.00 | $ 63,750.00 |
| 00 | 04 | TYPE A STONE PLACEMENT - B | 250 | TONS | $ 788.00 | $ 197,000.00 | $ 561.72 | $ 140,430.00 | $ 250.00 | $ 62,500.00 | $ 400.00 | $ 100,000.00 | $ 255.00 | $ 63,750.00 |
| 00 | 05 | TYPE A STONE PLACEMENT - C | 100 | TONS | $ 788.00 | $ 78,800.00 | $ 581.72 | $ 58,172.00 | $ 250.00 | $ 25,000.00 | $ 400.00 | $ 40,000.00 | $ 255.00 | $ 25,500.00 |
Total Options $ 472,800.00 $ 339,032.00 $ 150,000.00 $ 240,000.00 $ 153,000.00
Total Base + Options $ 2,017,191.00 $ 756,205.32 $ 813,900.00 $ 948,507.00 $ 1,514,500.00