This is a solicitation notice for a construction project to install a detention pond and storm sewers in Schiller Park, Illinois. The United States Army Corps of Engineers, Chicago District is seeking bids for project W912P622B0010. Work includes installing storm sewers, excavating earth, and constructing manholes and catch basins. A detention pond will also be created on vacant land and connected to the new storm sewer system. The estimated cost range for construction is $1-5 million. Bids are due by January 4, 2023. This opportunity is reserved exclusively for small business concerns with a size standard of $39.5 million. The point of contact is Casimir Brzozowiec at the provided number and email.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Stormwater Improvements - Schiller Park, IL W912P622B0010
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 220 00
PRICE AND PAYMENT PROCEDURES
11/ 20, CHG 1: 02/ 21
PART 1 GENERAL
1.1 CONTRACT COST BREAKDOWN
1.2 SINGLE JOB PAYMENT ITEMS
1.2.1 Traffic Control and Protection (BidItem 0001BJ)
1.2.1.1 Payment
1.2.1.2 Unit of Measure
1.3 UNIT PRICE PAYMENT ITEMS
1.3.1 6" Storm Sewers, PVC, SDR 26, ASTM D2241 (Bid Item 0001AA)
1.3.1.1 Payment
1.3.1.2 Measurement
1.3.1.3 Unit of Measure
1.3.2 15" Storm Sewers, DIP (Bid Item 0001AB)
1.3.2.1 Payment
1.3.2.2 Measurement
1.3.2.3 Unit of Measure
1.3.3 24" Storm Sewers, DIP (Bid Item 0001AC)
1.3.3.1 Payment
1.3.3.2 Measurement
1.3.3.3 Unit of Measure
1.3.4 18" Storm Sewers, RCP, CL IV, ASTM C76 (Bid Item 0001AD)
1.3.4.1 Payment
1.3.4.2 Measurement
1.3.4.3 Unit of Measure
1.3.5 24" Storm Sewers, RCP, CL IV, ASTM C76 (Bid Item 0001AE)
1.3.5.1 Payment
1.3.5.2 Measurement
1.3.5.3 Unit of Measure
1.3.6 30" Storm Sewers, RCP, CL IV, ASTM C76 (Bid Item 0001AF)
1.3.6.1 Payment
1.3.6.2 Measurement
1.3.6.3 Unit of Measure
1.3.7 Restricted Depth Catch Basin, 4' Diameter, Type 11 Frame, Open
Lid (Bid Item 0001AG)
1.3.7.1 Payment
1.3.7.2 Measurement
1.3.7.3 Unit of Measure
1.3.8 Restricted Depth Manhole, 5' Diameter, Type 1 Frame and Closed
Lid (Bid Item 0001AH)
1.3.8.1 Payment
1.3.8.2 Measurement
1.3.8.3 Unit of Measure
1.3.9 Restricted Depth Manhole, 6' Diameter, Type 1 Frame and Closed
Lid (Bid Item 0001AI)
1.3.9.1 Payment
1.3.9.2 Measurement
SECTION 01 20 00 Page 1
AMD_0005 - 01/12/23
1.3.9.3 Unit of Measure
1.3.10 Restricted Depth Manhole, 7' Diameter, Type 1 Frame and
Closed Lid (Bid Item 0001AJ)
1.3.10.1 Payment
1.3.10.2 Measurement
1.3.10.3 Unit of Measure
1.3.11 Frame and Lids to be Adjusted (Bid Item 0001AK)
1.3.11.1 Payment
1.3.11.2 Measurement
1.3.11.3 Unit of Measure
1.3.12 Trench Backfill (Bid Item 0001AL)
1.3.12.1 Payment
1.3.12.2 Measurement
1.3.12.3 Unit of Measure
1.3.13 Earth Excavation (Bid Item 0001AM)
1.3.13.1 Payment
1.3.13.2 Measurement
1.3.13.3 Unit of Measure
1.3.14 10" Water Main Adjustment (Bid Item 0001AN)
1.3.14.1 Payment
1.3.14.2 Measurement
1.3.14.3 Unit of Measure
1.3.15 Erosion Control Barrier Wall (Bid Item 0001AO)
1.3.15.1 Payment
1.3.15.2 Measurement
1.3.15.3 Unit of Measure
1.3.16 18" Flared End Section (Bid Item 0001AP)
1.3.16.1 Payment
1.3.16.2 Measurement
1.3.16.3 Unit of Measure
1.3.17 24" Diameter Flap Gate (Bid Item 0001AQ)
1.3.17.1 Payment
1.3.17.2 Measurement
1.3.17.3 Unit of Measure
1.3.18 6" Water Main Adjustment (Bid Item 0001AR)
1.3.18.1 Payment
1.3.18.2 Measurement
1.3.18.3 Unit of Measure
1.3.19 Exploratory Excavation (Bid Item 0001AS)
1.3.19.1 Payment
1.3.19.2 Measurement
1.3.19.3 Unit of Measure
1.3.20 Curb and Gutter Removal (Bid Item 0001AT and Option Bid Item
0002AA)
1.3.20.1 Payment
1.3.20.2 Measurement
1.3.20.3 Unit of Measure
1.3.21 Sidewalk Removal (Bid Item 0001AU)
1.3.21.1 Payment
1.3.21.2 Measurement
1.3.21.3 Unit of Measure
1.3.22 Combination Concrete Curb and Gutter, Type B-6.12 (Base Bid
Item 0001AV and Option Bid Item 0002AB)
1.3.22.1 Payment
1.3.22.2 Measurement
1.3.22.3 Unit of Measure
1.3.23 Portland Cement Concrete Sidewalk, 5" (Bid Item 0001AW)
1.3.23.1 Payment
1.3.23.2 Measurement
SECTION 01 20 00 Page 2
1.3.23.3 Unit of Measure
1.3.24 Class D Patches, 8"(Bid Item 0001AX)
1.3.24.1 Payment
1.3.24.2 Measurement
1.3.24.3 Unit of Measure
1.3.25 Detectable Warnings (Bid Item 0001AY)
1.3.25.1 Payment
1.3.25.2 Measurement
1.3.25.3 Unit of Measure
1.3.26 Dowel Bars, 1 1/2" (Bid Item 0001AZ)
1.3.26.1 Payment
1.3.26.2 Measurement
1.3.26.3 Unit of Measure
1.3.27 Class D Patches, Type I-IV, 6" (Bid Item 0001BA)
1.3.27.1 Payment
1.3.27.2 Measurement
1.3.27.3 Unit of Measure
1.3.28 Hot-Mix Asphalt Removal (Base Bid Item 0001BB and Option Bid
Item 0002AC)
1.3.28.1 Payment
1.3.28.2 Measurement
1.3.28.3 Unit of Measure
1.3.29 Bituminous Materials (Prime Coat)(Base Bid Item 0001BC and
Option Bid Item 0002AD)
1.3.29.1 Payment
1.3.29.2 Measurement
1.3.29.3 Unit of Measure
1.3.30 Incidental Hot-Mix Asphalt Surfacing (Base Bid Item 0001BD and Option Bid Item 0002AE)
1.3.30.1 Payment
1.3.30.2 Measurement
1.3.30.3 Unit of Measure
1.3.31 Top Soil and Seeding (Bid Item 0001BE)
1.3.31.1 Payment
1.3.31.2 Measurement
1.3.31.3 Unit of Measure
1.3.32 Tree Removals (15" and Over) (Bid Item 0001BF)
1.3.32.1 Payment
1.3.32.2 Measurement
1.3.32.3 Unit of Measure
1.3.33 Inlet Filter (Bid Item 0001BG)
1.3.33.1 Payment
1.3.33.2 Measurement
1.3.33.3 Unit of Measure
1.3.34 Fence Removal (Bid Item 0001BH)
1.3.34.1 Payment
1.3.34.2 Measurement
1.3.34.3 Unit of Measure
1.3.35 Low Height Stone Retaining Wall Removal and Reset (Bid Item
0001BI)
1.3.35.1 Payment
1.3.35.2 Measurement
1.3.35.3 Unit of Measure
1.3.36 Decorative Fence (Option Bid Item 0002AF)
1.3.36.1 Payment
1.3.36.2 Measurement
1.3.36.3 Unit of Measure
1.3.37 30" Flared End Section (Bid Item 0001BK)
1.3.37.1 Payment
SECTION 01 20 00 Page 3
1.3.37.2 Measurement
1.3.37.3 Unit of Measure
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
SECTION 01 20 00 Page 4
SECTION 01 220 00
PRICE AND PAYMENT PROCEDURES
11/ 20, CHG 1: 02/ 21
PART 1 GENERAL
1.1 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 calendar days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
1.2 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this Contract for which Contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2.1 Traffic Control and Protection (BidItem 0001BJ)
1.2.1.1 Payment
This item shall pertain to the work associated with the installation and maintenance of all required vehicular and pedestrian traffic control and protection.
The Contractor shall obtain, erect, maintain and remove all signs, barricades, flashers, flagmen and other traffic and pedestrian control devices as may be necessary for the purpose of regulating, warning, protecting or guiding vehicular and pedestrian traffic and protection to obviate the danger of injury to the aforesaid vehicular and pedestrian traffic as well as the Contractor's and Subcontractor's work persons in the vicinity of the work area. The Contractor shall be solely responsible for Traffic and Pedestrian Control and all aspects of safety at or in the vicinity of the job site.
The Contractor shall place sufficient barricades around the construction areas during the working hours. All barricades shall be removed from the pavement at the end of the day so that there is no closure of lanes for traffic.
SECTION 01 20 00 Page 5
The Contractor shall comply with Traffic Control and Protection Standards of IDOT for flagmen, signing and barricades.
Traffic control shall be in accordance with the applicable sections of the Standard Specifications for Road and Bridge Construction, the applicable guidelines contained in the Illinois Manual on Uniform Traffic Control Devices for Streets and Highways, these Special Provisions, and any special details and Highway Standards contained herein and in the Plans.
At the preconstruction meeting, the Contractor shall furnish the name of the individual in his direct employ who is to be responsible for the installation and maintenance of the traffic control for this project. If the actual installation and maintenance are to be accomplished by a subcon-tractor, consent shall be requested of the Engineer at the time of the preconstruction meeting in accordance with Article 108.01 of the Standard Specification for Road and Bridge Construction. This shall not relieve the Contractor of the foregoing requirement for a responsible individual in his direct employ.
Special attention is called to Articles 107.09 and 107.14 of the Standard Specifications for Road and Bridge Construction and the following: (1) Highway Standards, (2) mimeographed supplemental specifications, mimeographed special provisions, and (3) other special provisions relating to traffic control.
The Contractor shall furnish, install, maintain, relocate and subse-quently remove all signs, signals, temporary pavement marking, traffic cones, barricades, warning lights, flagmen, and other devices which are to be used for the purpose of controlling traffic. Two-way movement on streets and access to abutting properties shall be maintained at all times.
The Contractor shall be responsible for insuring that all barricades, warning signs, lights and other devices installed by him are in place and operating twenty-four (24) hours each day, including Sundays and Holidays during the time this Contract is in force.
In the event of severe weather conditions, the Contractor will be required to furnish any additional personnel required to properly maintain all traffic control devices.
General Traffic Maintenance
It shall be the responsibility of the Contractor to maintain local access for businesses and homeowners and minimize impact to the local residence.
Contractor shall not close any streets
Parking is at a premium along the route of the project and angled parking exists along the north side of Soreng Avenue from 25th Avenue west to Emerson Drive. The Contractor must coordinate with the Village of Schiller Park the scheduling and production rate of the work to determine the extent of no parking areas at any given time. In addition residences along Soreng Avenue and Garden Court only have one point of ingress and one point of egress (Soreng is one way westbound and Garden Court is one way eastbound. Ingress and egress must be maintained at all times.
All streets within the area shall be opened back up to traffic by end of the construction work day. No excavation shall be left open over-night.
SECTION 01 20 00 Page 6
The Village of Schiller Park has trash pick-up on Tuesdays. Contractor shall maintain access to the alley behind Soreng Avenue during this time for trash collection.
One potential option for construction traffic is utilizing a flaggers to allow trucks to utilize Soreng Avenue eastbound (against the normal flow of traffic) and to make a right turn only on 25th Avenue. This option will need to be reviewed and approved by the Village.
1.2.1.2 Unit of Measure
Unit of Measure: LUMPS SUM
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.3.1 6" Storm Sewers, PVC, SDR 26, ASTM D2241 (Bid Item 0001AA)
1.3.1.1 Payment
Payment will be made for costs associated with installation of the pipe type and size including saw cutting pavement, excavation, bedding, backfill, granular backfill, pipe and fittings, connection to structures, dewatering as specified in Specification and shown on the plans. Work also includes incidental removal of existing pipe or manholes where it is in conflict with the pipe. Payment constitutes full compensation for all plant, labor, materials, equipment, tools, and incidentals necessary to complete the work.
The pipe bedding and backfill to twelve inches (12") above the top of pipe will be included in this item.
Pipe installation shall be in accordance with Section 31 of the "Standard Specifications for Water and Sewer Main Construction in Illinois."
1.3.1.2 Measurement
The measurement will be made over the centerline of the pipe measured from the center line of the structures, installed and in place for the various types and diameters of pipe as indicated in the plans and Specification.
1.3.1.3 Unit of Measure
Unit of Measure: Foot
1.3.2 15" Storm Sewers, DIP (Bid Item 0001AB)
1.3.2.1 Payment
At locations indicated on the Plans, ductile iron (DIP) sewer pipe of the size indicated shall be installed. The sewer material shall be Ductile Iron
SECTION 01 20 00 Page 7
Pipe, Class 52, cement-lined and tar-coated, meeting the requirements of Specifications ANSI/AWWA 21.51/C151, A21.52 and Federal Specification WW-P-421d with "push-on" joints meeting the requirements of specifications ANSI/AWWA A21.11/C111. Pipe installation shall be in accordance with Section 31 of the "Standard Specifications for Water and Sewer Main Construction in Illinois" and the "Standard Specifications."
The pipe bedding and backfill to twelve inches (12") above the top of pipe will be included in this item.
Payment will be made for costs associated with the installation of the pipe type and size including saw cutting pavement, excavation, bedding, backfill, granular backfill, pipe and fittings, connection to structures, dewatering as specified in Specification and shown on the plans. Work also includes incidental removal of existing pipe or manholes where it is in conflict with the pipe.
1.3.2.2 Measurement
The measurement will be made over the centerline of the pipe measured from the center line of the structures, installed and in place for the various types and diameters of pipe as indicated in the plans and Specification.
1.3.2.3 Unit of Measure
Unit of Measure: Foot
1.3.3 24" Storm Sewers, DIP (Bid Item 0001AC)
1.3.3.1 Payment
At locations indicated on the Plans, ductile iron (DIP) sewer pipe of the size indicated shall be installed. The sewer material shall be Ductile Iron Pipe, Class 52, cement-lined and tar-coated, meeting the requirements of Specifications ANSI/AWWA 21.51/C151, A21.52 and Federal Specification WW-P-421d with "push-on" joints meeting the requirements of specifications ANSI/AWWA A21.11/C111. Pipe installation shall be in accordance with Section 31 of the "Standard Specifications for Water and Sewer Main Construction in Illinois" and the "Standard Specifications."
The pipe bedding and backfill to twelve inches (12") above the top of pipe will be included in this item.
Payment will be made for costs associated with the installation of the pipe type and size including saw cutting pavement, excavation, bedding, backfill, granular backfill, pipe and fittings, connection to structures, dewatering as specified in Specification and shown on the plans. Work also includes incidental removal of existing pipe or manholes where it is in conflict with the pipe.
1.3.3.2 Measurement
The measurement will be made over the centerline of the pipe measured from the center line of the structures, installed and in place for the various types and diameters of pipe as indicated in the plans and Specification.
1.3.3.3 Unit of Measure
Unit of Measure: Foot
SECTION 01 20 00 Page 8
1.3.4 18" Storm Sewers, RCP, CL IV, ASTM C76 (Bid Item 0001AD)
1.3.4.1 Payment
This item includes the installation of RCP storm sewer pipe of the size indicated, at locations shown on the plans or as directed by Engineer.
The pipe shall conform to ASTM designation C 76, Class II, with C-990 joints.
Pipe installation shall be in accordance with Sections 50 and 51 of the "Standard Specifications for Water and Sewer Main Construction in Illinois".
The pipe bedding and backfill to the spring-line of the pipe are included in this item and shall be considered incidental to the cost of this item.
Payment will be made for costs associated with the installation of the pipe type and size including saw cutting pavement, excavation, bedding, backfill, granular backfill, pipe and fittings, connection to structures, dewatering as specified in Specification and shown on the plans. Work also includes incidental removal of existing pipe or manholes where it is in conflict with the pipe.
1.3.4.2 Measurement
The measurement will be made over the centerline of the pipe measured from the center line of the structures, installed and in place for the various types and diameters of pipe as indicated in the plans and Specification
1.3.4.3 Unit of Measure Foot
1.3.5 24" Storm Sewers, RCP, CL IV, ASTM C76 (Bid Item 0001AE)
1.3.5.1 Payment
This item includes the installation of RCP storm sewer pipe of the size indicated, at locations shown on the plans or as directed by Engineer.
The pipe shall conform to ASTM designation C 76, Class II, with C-990 joints.
Pipe installation shall be in accordance with Sections 50 and 51 of the "Standard Specifications for Water and Sewer Main Construction in Illinois".
The pipe bedding and backfill to the spring-line of the pipe are included in this item and shall be considered incidental to the cost of this item.
Payment will be made for costs associated with the installation of the pipe type and size including saw cutting pavement, excavation, bedding, backfill, granular backfill, pipe and fittings, connection to structures, dewatering as specified in Specification and shown on the plans. Work also includes incidental removal of existing pipe or manholes where it is in conflict with the pipe.
SECTION 01 20 00 Page 9
1.3.5.2 Measurement
The measurement will be made over the centerline of the pipe measured from the center line of the structures, installed and in place for the various types and diameters of pipe as indicated in the plans and Specification
1.3.5.3 Unit of Measure Foot
1.3.6 30" Storm Sewers, RCP, CL IV, ASTM C76 (Bid Item 0001AF)
1.3.6.1 Payment
This item includes the installation of RCP storm sewer pipe of the size indicated, at locations shown on the plans or as directed by Engineer.
The pipe shall conform to ASTM designation C 76, Class II, with C-990 joints.
Pipe installation shall be in accordance with Sections 50 and 51 of the "Standard Specifications for Water and Sewer Main Construction in Illinois".
The pipe bedding and backfill to the spring-line of the pipe are included in this item and shall be considered incidental to the cost of this item.
Payment will be made for costs associated with the installation of the pipe type and size including saw cutting pavement, excavation, bedding, backfill, granular backfill, pipe and fittings, connection to structures, dewatering as specified in Specification and shown on the plans. Work also includes incidental removal of existing pipe or manholes where it is in conflict with the pipe.
1.3.6.2 Measurement
The measurement will be made over the centerline of the pipe measured from the center line of the structures, installed and in place for the various types and diameters of pipe as indicated in the plans and Specification
1.3.6.3 Unit of Measure Foot
1.3.7 Restricted Depth Catch Basin, 4' Diameter, Type 11 Frame, Open Lid (Bid Item 0001AG)
1.3.7.1 Payment
A four-foot (4') diameter catch basin shall be constructed at the locations shown on the Plans and in accordance with the details shown on the Plans. The Contractor will be responsible for ensuring that the pipe openings are formed in the correct locations so that additional cutting of the precast structure is not necessary.
The removal of structures where a new structure is to be installed in the same location will not be paid for separately but shall be included in the cost of the new structure.
1.3.7.2 Measurement
Restricted Depth Catch Basins will be paid for per each of the size
SECTION 01 20 00 Page 10 installed per structure installed.
1.3.7.3 Unit of Measure
Each
1.3.8 Restricted Depth Manhole, 5' Diameter, Type 1 Frame and Closed Lid (Bid Item 0001AH)
1.3.8.1 Payment
A restricted depth manhole of the size indicated shall be constructed at the locations shown on the Plans and in accordance with the details shown on the Plans. The Contractor will be responsible for ensuring that the pipe openings are formed in the correct locations so that additional cutting of the precast structure is not necessary.
The removal of structures where a new structure is to be installed in the same location will not be paid for separately but shall be included in the cost of the new structure.
Text 1.3.8.2 Measurement
Restricted Depth Manholes will be paid for per each of the size installed per structure installed.t
1.3.8.3 Unit of Measure
Each
1.3.9 Restricted Depth Manhole, 6' Diameter, Type 1 Frame and Closed Lid (Bid Item 0001AI)
1.3.9.1 Payment
A restricted depth manhole of the size indicated shall be constructed at the locations shown on the Plans and in accordance with the details shown on the Plans. The Contractor will be responsible for ensuring that the pipe openings are formed in the correct locations so that additional cutting of the precast structure is not necessary.
The removal of structures where a new structure is to be installed in the same location will not be paid for separately but shall be included in the cost of the new structure.
Text 1.3.9.2 Measurement
Restricted Depth Manholes will be paid for per each of the size installed per structure installed.t
1.3.9.3 Unit of Measure
Each
SECTION 01 20 00 Page 11
1.3.10 Restricted Depth Manhole, 7' Diameter, Type 1 Frame and Closed Lid (Bid Item 0001AJ)
1.3.10.1 Payment
A restricted depth manhole of the size indicated shall be constructed at the locations shown on the Plans and in accordance with the details shown on the Plans. The Contractor will be responsible for ensuring that the pipe openings are formed in the correct locations so that additional cutting of the precast structure is not necessary.
The removal of structures where a new structure is to be installed in the same location will not be paid for separately but shall be included in the cost of the new structure.
Text 1.3.10.2 Measurement
Restricted Depth Manholes will be paid for per each of the size installed per structure installed.t
1.3.10.3 Unit of Measure
Each
1.3.11 Frame and Lids to be Adjusted (Bid Item 0001AK)
1.3.11.1 Payment
This item shall include the adjustment of existing manhole, catch basin, inlet, and valve vault frames at locations shown on the Plans or as directed by the Engineer. The pavement disturbed by the adjustment will be replaced with eight inches (8") of concrete base course to the grade of the hot-mix asphalt base course or level binder. The removal and replacement of the pavement shall be included as part of this item.
The adjustment of frames and grates on newly installed structures shall not be paid for separately but shall be considered as part of the respective pay item for the installation of the proposed structures.
1.3.11.2 Measurement
Frames and Lids to be adjusted will be measured for by each per structure adjusted.
1.3.11.3 Unit of Measure
Each
1.3.12 Trench Backfill (Bid Item 0001AL)
1.3.12.1 Payment
All trench backfill used under or within two feet (2') of pavements, sidewalks, driveways, and curb and gutter shall be Crushed Stone, Gradation CA-6. Maximum compaction must be obtained by Method 1
SECTION 01 20 00 Page 12
(mechanical compaction) as described in Article 550.07 of the "IDOT Standard Specifications for Road and Bridge Construction".
1.3.12.2 Measurement
Payment for this item will be based on actual in place measurements taken by the Engineer on the site but in no case will exceed the theoretical volume calculated by using the trench backfill table included in the details shown on the Plans.
1.3.12.3 Unit of Measure
CuYd
1.3.13 Earth Excavation (Bid Item 0001AM)
1.3.13.1 Payment
This item includes all of the mass excavating and grading work necessary on this Project to establish the subgrade elevations of the proposed ground detention pond. The work shall be performed in accordance with Section 202 of the "IDOT Standard Specifications for Road and Bridge Construction".
The work shall be performed in accordance with the proposed line and grades as shown on the plans.
The slopes of the earthen walls shall be as shown on the plans.
It is the Contractor's responsibility to determine all material quantities and apprise himself of all site conditions. The contract prices submitted by the Contractor shall apply to all excavation required for the completion of the project. No claims for extra work will be recognized unless ordered in writing by the Owner.
The pond excavation and grading shall be performed under dewatered conditions by constructing temporary ditches and/or culverts, and by dewatering or bypassing with pumps as necessary.
The subgrade shall be free of unsuitable material and shall be compacted to a minimum of ninety-five (95) percent of modified proctor density.
Testing for compaction shall be the responsibility of the Contractor. All test results shall be submitted to the Owner & Engineer.
Upon completion of the grading operations, the Contractor shall furnish and spread a 6" layer of topsoil on all disturbed areas.
During construction operations, the Contractor shall insure positive site drainage at the conclusion of each day. Site drainage may be achieved by ditching, pumping or any other method acceptable to the Engineer. The Contractor's failure to provide the above will preclude any possible added compensation requested due to delays or unsuitable materials created as a result thereof.
Whenever, during construction operations, any loose material is deposited in gutter flow lines, drainage structures, ditches, etc. such that the natural flow of water is obstructed, the obstruction shall be removed at the close of each working day. At the conclusion of construction operations, all drainage structures and flow lines shall be free from dirt
SECTION 01 20 00 Page 13 and debris. This work shall be considered incidental to the contract.
1.3.13.2 Measurement
This work will be paid for at the contract unit price per cubic yard of material removed from the site. The quantity will be based upon the difference in elevations form the existing conditions to the final as built elevations.
1.3.13.3 Unit of Measure
Cubic Yard
1.3.14 10" Water Main Adjustment (Bid Item 0001AN)
1.3.14.1 Payment
During the installation of the storm sewer, it may be necessary to adjust existing water mains due to potential grade conflicts. A section of water main of the same nominal diameter as existing shall be replaced at a raised or lowered elevation as necessary, depending on the conflict involved.
All adjusted pipe shall be ductile iron, Class 52, conforming to AWWA C151. All fittings shall be mechanical joints with restrained joints using retainer glands and tie rods. Restraint devices shall consist of multiple gripping wedges incorporated into a follower gland meeting the applicable requirements of ANSI/AWWA C110/A21.10. The devices shall have a working pressure rating of 350 psi. Mechanical joint restraint shall require conventional tools and installation procedures per AWWA C600, while retaining full mechanical joint deflection during assembly as well as allowing joint deflection after assembly. Proper actuation of the gripping wedges shall be ensured with torque limiting twist off nuts.
The Contractor shall contact the Village Water Department to schedule the water main shutdown 48 hours prior to the anticipated shutdown time. The Contractor shall have all necessary fittings and hardware required at the job site prior to the main being shut down. Once the shutdown is made, the Contractor shall work straight through until the adjustment is complete and the water main is placed back in service.
Water mains as installed shall meet the minimum sewer and water separation requirements. All water main pipe sections and fittings shall be thoroughly cleaned and swabbed with a concentrated chlorine solution prior to installation.
All fittings and Retainer glands will not be paid for separately but shall be included in the cost of this item. The necessary shut down of the water main will also be included in the cost of this item.
1.3.14.2 Measurement
This item will be paid per location where the water main is adjusted for the size of water main adjusted.
1.3.14.3 Unit of Measure
Each
SECTION 01 20 00 Page 14
1.3.15 Erosion Control Barrier Wall (Bid Item 0001AO)
1.3.15.1 Payment
This item pertains to the installation of an erosion control barrier wall around the proposed detention pond. The Barrier Wall shall include a 30-MIL Polyethylene fabric with anchor and sandbag as per IDOT Standard Specifications for Road and Bridge Construction and the Erosion Control Plan and details shown in the project plans.
Text 1.3.15.2 Measurement
This item shall be paid for per foot of barrier wall installed.
1.3.15.3 Unit of Measure
Foot
1.3.16 18" Flared End Section (Bid Item 0001AP)
1.3.16.1 Payment
This item includes the furnishing and construction of a precast reinforced flared end section at the locations shown on the plans. The flared end section shall be fabricated and installed in accordance with Article
601.05 of the IDOT Standard Specifications, and according to IDOT Standard 542301-03.
1.3.16.2 Measurement
This item will be paid per each flared end section furnished and installed.
1.3.16.3 Unit of Measure
Each
1.3.17 24" Diameter Flap Gate (Bid Item 0001AQ)
1.3.17.1 Payment
This item pertains to the installation of cast iron flap gate within manhole structures at locations shown on the plans. The flag gate shall be made to attach to the wall of the structure and shall be equipped with a rubber seat.
1.3.17.2 Measurement
This item will be paid per each flap gate of the size indicated furnished and installed.
1.3.17.3 Unit of Measure
Each
SECTION 01 20 00 Page 15
1.3.18 6" Water Main Adjustment (Bid Item 0001AR)
1.3.18.1 Payment
During the installation of the storm sewer, it may be necessary to adjust existing water mains due to potential grade conflicts. A section of water main of the same nominal diameter as existing shall be replaced at a raised or lowered elevation as necessary, depending on the conflict involved.
All adjusted pipe shall be ductile iron, Class 52, conforming to AWWA C151. All fittings shall be mechanical joints with restrained joints using retainer glands and tie rods. Restraint devices shall consist of multiple gripping wedges incorporated into a follower gland meeting the applicable requirements of ANSI/AWWA C110/A21.10. The devices shall have a working pressure rating of 350 psi. Mechanical joint restraint shall require conventional tools and installation procedures per AWWA C600, while retaining full mechanical joint deflection during assembly as well as allowing joint deflection after assembly. Proper actuation of the gripping wedges shall be ensured with torque limiting twist off nuts.
The Contractor shall contact the Village Water Department to schedule the water main shutdown 48 hours prior to the anticipated shutdown time. The Contractor shall have all necessary fittings and hardware required at the job site prior to the main being shut down. Once the shutdown is made, the Contractor shall work straight through until the adjustment is complete and the water main is placed back in service.
Water mains as installed shall meet the minimum sewer and water separation requirements. All water main pipe sections and fittings shall be thoroughly cleaned and swabbed with a concentrated chlorine solution prior to installation.
All fittings and Retainer glands will not be paid for separately but shall be included in the cost of this item. The necessary shut down of the water main will also be included in the cost of this item.
1.3.18.2 Measurement
This item will be paid per location where the water main is adjusted for the size of water main adjusted.
1.3.18.3 Unit of Measure
Each
1.3.19 Exploratory Excavation (Bid Item 0001AS)
1.3.19.1 Payment
Whenever in the opinion of the Engineer, it is necessary to explore and excavate in advance of a structure installation or pipe laying operation, or to determine the elevation and location of existing utilities, the Contractor shall make explorations and excavations for such purposes. The Contractor should factor in the cost associated with any stoppage of productivity due to completing this item. No additional compensation will be given for any loss of productivity due to exploratory excavation.
SECTION 01 20 00 Page 16
The Contractor shall notify the Engineer prior to initiating any exploratory excavation so that such work can be authorized. Any unauthorized excavation will not be paid for and will be backfilled at the Contractor's expense.
1.3.19.2 Measurement
This item shall be used to pay for any and all exploratory excavations.
Extra billings on a time and material basis will not be considered or accepted for utility work. Payment for this item shall be at the Contract unit price per Hour. This item will be paid for in increments of 0.5 hours.
1.3.19.3 Unit of Measure
Hour
1.3.20 Curb and Gutter Removal (Bid Item 0001AT and Option Bid Item 0002AA)
1.3.20.1 Payment
This item shall include the removal of the existing combination curb and gutter at locations indicated on the Plans and as directed by the Engineer.
The work shall be performed in accordance with Section 440 of the " IDOT Standard Specifications for Road and Bridge Construction".
Included in this item is the removal of all types of curb encountered on the Project. This includes but is not limited to barrier curb. Also included in this item is the removal and disposal of any asphalt that has been overlaid into the gutter of any curb that is designated for removal. This item shall also include any excavation beneath or in back of the curb and gutter necessary to install the proposed curb and gutter. All excavation necessary to reach the subgrade of the proposed curb and gutter shall be included in this item.
A full-depth saw-cut shall be made twelve inches (12") from the edge of pavement for the entire length of curb and gutter removal to allow for the neat removal of the curb and gutter and the placement of a gutter board in forming for the new curb.
All removal shall terminate at existing expansion joints or at saw-cut lines as determined by the Engineer. The existing pavements abutting the curb and gutter shall be protected while removal work is being done to avoid unnecessary pavement restoration.
1.3.20.2 Measurement
Curb and gutter removal shall be paid for per foot between the limits of the existing curb and gutter to remain.
1.3.20.3 Unit of Measure
Foot
1.3.21 Sidewalk Removal (Bid Item 0001AU)
1.3.21.1 Payment
This item shall include the removal of sidewalk at locations shown on the
SECTION 01 20 00 Page 17
Plans and as directed by the Engineer. The work shall be performed in accordance with Section 440 of the "IDOT Standard Specifications for Road and Bridge Construction".
The removal of concrete, brick, flagstone and hot-mix asphalt sidewalks shall all be included in this item. These sidewalks shall be excavated to the subgrade of the proposed sidewalk. All excavation necessary to reach the subgrade of the proposed sidewalk shall be included in this item.
1.3.21.2 Measurement
Sidewalk removal shall be paid for per square foot between the limits of the existing sidewalk to remain
1.3.21.3 Unit of Measure
Square Foot
1.3.22 Combination Concrete Curb and Gutter, Type B-6.12 (Base Bid Item 0001AV and Option Bid Item 0002AB)
1.3.22.1 Payment
This item shall include the placement of new combination concrete curb and gutter. The construction of the combination concrete curb and gutter shall be in accordance with the details for this item as shown on the Plans as well as in accordance with Section 606 of the " IDOT Standard Specifications for Road and Bridge Construction". Included in this item is the cost of any additional work or material to meet the existing curb and gutter size.
The curb shall be placed upon a compacted crushed stone bedding, Gradation CA-6, having a minimum thickness of two inches (2"). The cost for the 2" stone cushion shall be included in this item.
Between four (4) and twenty-four (24) hours after the curb has been placed, contraction joints two inches (2") in depth, shall be saw-cut at a maximum of a 15' spacing and at certain other locations as may be indicated by the Engineer. These joints shall then be sealed according to the requirements of Article 420.14(a) of the "Standard Specifications for Road and Bridge Construction". At locations where the proposed curb and gutter meets existing curb and gutter, 2 - 18" long, ¾" diameter, epoxy coated, steel dowel bars shall be drilled into the existing curb and gutter.
It shall be the Contractor's responsibility to provide for curb depressions to be constructed where public sidewalks are to be ramped at curb crossings. The depressions shall be constructed in basic compliance with the Accessibility Guidelines as detailed in the Americans with Disabilities Act (ADA).
The concrete shall be thoroughly tamped and spaded or mechanically vibrated and finished smooth and even. Areas of "honeycombing" along the vertical surfaces of the curb and gutter shall be removed and replaced at the Contractor's expense.
The void behind the curb and gutter shall be backfilled with crushed stone, gradation CA-7, in all areas where concrete or hot-mix asphalt
SECTION 01 20 00 Page 18 pavement is to be constructed. The placement of the required backfill material will be included in the placement of the curb and gutter.
1.3.22.2 Measurement
Curb and gutter shall be paid for per foot between the limits of the existing curb and gutter to remain.
1.3.22.3 Unit of Measure
Foot
1.3.23 Portland Cement Concrete Sidewalk, 5" (Bid Item 0001AW)
Text 1.3.23.1 Payment
This item shall include the placement of a five-inch (5") concrete sidewalk at locations shown on the Plans or as directed by the Engineer in accordance with Section 424 of the "IDOT Standard Specifications for Road and Bridge Construction".
The five inch (5") thick P.C.C. sidewalk shall be constructed to the limits and grade required to blend with adjoining surfaces. The sidewalk shall be placed upon a cushion of compacted crushed stone, Gradation CA-6, having a minimum thickness of two inches (2"). The cost for the 2" stone cushion shall be included in this item. Full depth expansion joints shall be placed between the sidewalk and the back of any adjacent curb, sidewalk, or buildings, at seventy-five foot (75') intervals in the sidewalk, and as directed by the Engineer.
1.3.23.2 Measurement
PCC Sidewalk shall be paid for per square foot of sidewalk installed between the limits of the existing sidewalk to remain
1.3.23.3 Unit of Measure
Square Foot
1.3.24 Class B Patches, 10" Class D Patches, 8" (Bid Item 0001AX)
1.3.24.1 Payment
This item shall pertain to the patching of the existing finished concrete pavement within the 25th Avenue ROW. The work shall be done in accordance with Section 442 of the Specifications for Road and Bridge Construction and IDOT Highway Standard 442101-09 with the exception that saw cutting of the pavement will not be paid for separately but shall be included in the cost of this item. This item shall pertain to the patching of the existing pavement within the 25th Avenue ROW. The work shall be done in accordance with Section 442 of the Specifications for Road and Bridge Construction and IDOT Highway Standard 442201-03 with the exception that saw cutting of the pavement will not be paid for separately but shall be included in the cost of this item. The patch shall be brought to an elevation of 2" below the existing surface to allow for the placement of a 2"layer of Hot-Mix Asphalt Surfacing which will be paid for separately.
SECTION 01 20 00 Page 19
1.3.24.2 Measurement
This work will be measured and the area computed in Square Yards. This price shall cover types I-IV of Class BD parches
1.3.24.3 Unit of Measure
Square Yard
1.3.25 Detectable Warnings (Bid Item 0001AY)
Text 1.3.25.1 Payment
This item shall include the placement of detectable warnings at locations shown on the Plans and as directed by the Engineer. This item shall be installed simultaneously with PORTLAND CEMENT CONCRETE SIDEWALK, 5".
Work shall be performed according to the Americans with Disabilities Act, IDOT Standard 424001-07, as well as Section 424 of the IDOT Standard Specifications for Road and Bridge Construction. Rectangular or radius tiles shall be installed as necessary to meet the requirements of these specifications.
The detectable warning shall be Vitrified Polymer Composite, Cast in Place, Detectable/Tactile Warning Surface Tile and shall be Federal Color No. 22144 (Brick Red) or Federal Color No. 20109 (Colonial Red), or approved equal.
This item shall not be a "Surface Applied" product.
Immediately following the installation of PORTLAND CEMENT CONCRETE SIDEWALK, 5", the detectable warning shall be pressed into the concrete.
The detectable warning shall be tamped with a vibrating mechanism upon installation, and the factory-installed plastic sheeting must remain in place during the entire installation process to prevent the splashing of concrete onto the finished surface of the tile. No concrete shall be removed in the area to receive the detectable warning to ensure a strong lock with the concrete. The top of the domes shall be set level to the adjacent concrete on the top and sides of the ramp. This item shall be installed in full accordance with the manufacturer's recommendations.
1.3.25.2 Measurement
Detectable warnings shall be paid for per square foot of tile installed
1.3.25.3 Unit of Measure
Square Foot
1.3.26 Dowel Bars, 1 1/2" (Bid Item 0001AZ)
Text 1.3.26.1 Payment
This item shall pertain to the drilling and placement of 1 1/2" dowel bars associated with the Class B Patches that will be installed. The placement and spacing of the dowel bars shall be in accordance with IDOT Highway Standard 424101-09.Text
SECTION 01 20 00 Page 20
1.3.26.2 Measurement
The quantities of Dowel Bars will be based upon the table in IDOT Highway Standard 424101-09.Text
1.3.26.3 Unit of Measure
Each
1.3.27 Class D Patches, Type I-IV, 6" (Bid Item 0001BA)
Text 1.3.27.1 Payment
This item will primarily be used for the trench restoration over utility installations and replacement with hot-mix asphalt. The work shall be performed in accordance with applicable Articles of Section 442 of the Standard Specifications.
The material will be removed to a depth sufficient to allow the placement of six inches of Class D Patches' and (3") of Hot-Mix Asphalt Surface Course placement. The material shall be the appropriately sized HMA, N50 mixtures shall be used for this pay item.
The limits of removal shall be marked by the Engineer. The patches shall be saw cut full-depth and any areas damaged outside the limits of removal shall be replaced by the Contractor at his own expense.
1.3.27.2 Measurement
This work will be measured and the area computed in Square Yards. This price shall cover types I-IV of Class D parches
1.3.27.3 Unit of Measure
Square Yard
1.3.28 Hot-Mix Asphalt Removal (Base Bid Item 0001BB and Option Bid Item
0002AC)
1.3.28.1 Payment
This item shall pertain to the removal of existing asphalt adjacent to where new curb and gutter has been replaced to allow for a transition from the new curb and gutter to the existing asphalt. The hot-mix asphalt shall be removed to a minimum depth of three-inches (3") or to match the existing adjacent hot-mix asphalt surface if greater than three-inches (3").
A neat straight edge shall be saw cut where the proposed asphalt meets the existing asphalt. The cost for the sawcutting is included in the cost of this item.
1.3.28.2 Measurement
The measurement will the in place area computed in square yards for the total increment of material removed. The area measured shall be paid for only once regardless of the number of passes needed to remove the material.
SECTION 01 20 00 Page 21
1.3.28.3 Unit of Measure
Square Yard
1.3.29 Bituminous Materials (Prime Coat)(Base Bid Item 0001BC and Option Bid Item 0002AD)
1.3.29.1 Payment
This item consists of the application of a bituminous prime coat (SS-1) on the existing hot-mix asphalt and/or concrete base surfaces prior to the installation of the hot-mix asphalt surface. The prime coat shall be placed in accordance with Article 406.05(b) of the " IDOT Standard Specifications for Road and Bridge Construction". The prime coat shall be placed a maximum of six (6) hours before the start of paving operations.
The Contractor shall be responsible for placing warning signs at all points of access to the primed surface except for residential driveways.
1.3.29.2 Measurement
The prime coat will be paid for based upon an application rate of 0.10 Gallons per square yard
1.3.29.3 Unit of Measure
Gallon
1.3.30 Incidental Hot-Mix Asphalt Surfacing (Base Bid Item 0001BD and Option Bid Item 0002AE)
Text 1.3.30.1 Payment
This item shall be installed in areas where existing asphalt was removed as part of the construction of the project. The hot-mix asphalt surface course shall be installed with a minimum thickness of three-inches (3") or to match the existing adjacent hot-mix asphalt surface if greater than three-inches (3"). The surface course shall be placed in accordance with Section 408 of the "IDOT Standard Specifications for Road and Bridge Construction".
Hot-Mix Asphalt Surface Course, Mix 'D', N50 shall be used for this pay item.
1.3.30.2 Measurement
The measurement will be the in place area computed in square yards for the total area where the asphalt is placed
1.3.30.3 Unit of Measure
Square Yard
1.3.31 Top Soil and Seeding (Bid Item 0001BE)
1.3.31.1 Payment
This item shall pertain to the restoration of all disturbed grass areas within the project limits. Work under this section shall include but not be limited to the following:
SECTION 01 20 00 Page 22
Stripping of topsoil from all proposed excavation and areas.
Stockpiling of sufficient topsoil for use in the final placement of topsoil and seeding at locations as directed by the Owner or Engineer.
Topsoil stockpiled for future use shall be relatively free from large roots, sticks, weeds, brush, stones larger than one (1) inch diameter or other litter and waste products including other extraneous materials not conducive to plant growth. Topsoil shall be stockpiled in sequence to eliminate any rehandling or double movements by the Contractor:
The Contractor shall note that elevations shown on the construction plans are finished grade elevations and that the topsoil thickness must be subtracted to determine earthwork elevations.
Topsoil placement to design finished grade elevations in all areas designated to be restored with seed (6" minimum or as otherwise noted).
The proposed seed is to be placed beneath beneath a blanket.
The seed shall be placed in accordance with Section 250 of the "Standard Specifications for Road and Bridge Construction".
The seeding shall be Seeding, Class 2E Salt Tolerant Roadside Mix (Special) 280 lbs./ac.
1.3.31.2 Measurement
The area to received topsoil and seeding will be measured and paid for per acre of topsoil and seeding.
1.3.31.3 Unit of Measure
Acre
1.3.32 Tree Removals (15" and Over) (Bid Item 0001BF)
Text 1.3.32.1 Payment
This item includes the removal of existing trees in the way of the work, greater than 15 inches in diameter at locations shown on the plans or where directed by the Engineer. All work and materials under this item shall be in accordance with Section 201 of the IDOT Standard Specification, except as modified, amended, or clarified by this Special Provision.
1.3.32.2 Measurement
Trees to be removed as a payment item will be measured per unit of diameter with one unit being equal to one inch (1"). The diameter shall be measured at a point 4.5 feet above the highest ground level at the base of the tree and will be determined by dividing the measured circumference of the tree by 3.1416. A multiple stem tree's branches having a diameter of six inches (6") or more at a point 4.5 feet above the highest ground level at the base of the tree will be measured for payment as individual trees. The accumulated total number of units will be the pay quantity.
1.3.32.3 Unit of Measure
Unit
SECTION 01 20 00 Page 23
1.3.33 Inlet Filter (Bid Item 0001BG)
1.3.33.1 Payment
This item shall include the furnishing, installation, and removal of a drainage structure inlet filter assembly, consisting of a frame and filter bag, to collect sediment in surface stormwater runoff at locations shown on the Plans or as directed by the Engineer and shall be in accordance with Section 280 of the IDOT Standard Specifications for Road and Bridge Construction and the details on the Plans.
1.3.33.2 Measurement
Inlet filters will be measured for by each per structure to which they are installed.
1.3.33.3 Unit of Measure
Each
1.3.34 Fence Removal (Bid Item 0001BH)
1.3.34.1 Payment
This item shall include the removal and disposal of the existing fence, posts, gates, and foundations as indicated on the plans
1.3.34.2 Measurement
Fence removal shall be paid for per foot between the limits of the existing fence to remain
1.3.34.3 Unit of Measure
Foot
1.3.35 Low Height Stone Retaining Wall Removal and Reset (Bid Item 0001BI)
1.3.35.1 Payment
This item pertains to the removal and resetting of a low height stone retaining wall that may be in the way of the installation of the storm sewer through the park. Prior to excavation in this area, the existing retaining wall is to be carefully removed and safely stored for replacement once the work in this area is completed.
1.3.35.2 Measurement
This item shall be paid for per foot between the limits of the existing wall to remain.
1.3.35.3 Unit of Measure
Foot
SECTION 01 20 00 Page 24
1.3.36…