This federal solicitation seeks competitive bids to replace a cooling system and filtration equipment at a fish barrier facility in Romeoville, Illinois. The project requirements include replacing an existing cooling tower and filtration system with an air-cooled chiller package and plate and frame heat exchangers. The solicitation is restricted to small businesses with a size standard of $39.5 million. The estimated price range for the construction work is between $500,000 and $1 million. Applicable prevailing wage rates are provided. Electronic bid submissions are due by the date and time specified in the solicitation and must be uploaded through the Army's file sharing service.

View the file

Other files for this federal contract opportunity

Other files attached to USACE CHICAGO DISTRICT - Replace IIB Cooling System, newest first.
File Type Posted
Bid Opening Results.pdf PDF
W912P620B0028-0002_22SEPT20.pdf PDF
W912P620B0028_Dispersal_Barrier_IIB_Cooling System_Upgrade_RTA_SPECS(26-Aug-20).pdf PDF
W912P620B0028_Dispersal_Barrier_IIB_Cooling System_Upgrade_RTA_Plans(26-Aug-20).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W81G6601831404

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

REFERENCE INVITATION FOR BIDS NO. W912P620B0028, "Replace IIB Cooling System in Romeoville, IL"

A. The hour and date specified for receipt of Offer is NOT extended as a result of this amendment.

--SEE CONTINUATION PAGE--

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P620B0028

X 9B. DATED (SEE ITEM 11)

26-Aug-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0001

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Sep-2020

CODE

U.S. ARMY ENGINEER DISTRICT, CHICAGO

231 SOUTH LASALLE STREET SUITE 1500

CHICAGO IL 60604-1437

W912P6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P620B0028

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

SUMMARY OF CHANGES - AMDT 0001

B. AMENDED SPECIFICATION SECTIONS: The following Specification Sections have been revised. The revised sections are enclosed hereunder and replace the previously furnished sections.

a. 01 10 00 General Provisions: Paragraph 1.13 Minimum Amount of Insurance Required: Main change involved paragraph c. This paragraph discusses all the items that the selected insurance company must provide and compensation quantities.

b. 23 64 26: Paragraph 2.6.8 was removed because it is not needed for the project and the submittal register was updated to match the change made.

C. REVISED DRAWING SHEETS: The following Drawing Sheets have been revised and are hereunder enclosed, replacing the previously furnished respective sheet.

a. MD-101: The existing close loop pumps were bubbled to indicate to be removed.

b. M-603: Mechanical Schedules: The pulsar and rectifier pumps’ total dynamic head was corrected.

c. M-101: (1) The pipe schedule was corrected in note 3; (2) Note 7 was removed.

D. IMPORTANT BID NOTES: The following Sections have been revised. The revised sections are enclosed hereunder and replace the previously furnished sections.

a. BID GUARANTEE: All inquiries pertaining to this solicitation shall be submitted no later than 1:00PM CT on 21 Sept 2020.

b. VIRTUAL BID OPENING: The date and time of the Virtual Pre-Bid Meeting has been moved to 17 September 2020 at 10:00AM CT.

E. CONTRACTOR’S INQUIRIES: By this Amendment, the Chicago District, USACE responds to Contractor’s inquiries as follows:

INQUIRY #1: I am requesting if the Corps can clarify with a plan drawing what is required for the heat tracing as listed in Section 23 64 26, page 15, paragraph 2.6.8 and where it is required.

USACE RESPONSE INQUIRY #1: The para. 2.6.8, spec section 23 64 26 will be removed. A heat trace system is not needed for this job.

INQUIRY #2: I noticed on the chiller schedule notes it asks for "Variable Evaporator Flow". Looking at the piping diagram for the chilled water plant, I notice that the design is not laid out in a variable Primary configuration. I cannot notice a bypass with a control valve or any modulating control valves on the Heat Exchangers. I could just be seeing this incorrectly, so I was wondering if the intent here is to have variable primary flow? If not is the variable evaporator flow a requirement?

USACE RESPONSE INQUIRY #2: Yes, it is a variable flow evaporator. The chiller loop pump is equipped with VFD unit and it's part of the chiller unit package. The chiller loop piping layout, shown on the drawings, is external from the chiller unit and it does not show the closed loop pump. The VFD unit is shown on sheet M-501.

INQUIRY #3: Advise if any modification need to be done by the contractor to the existing Smith Root control system.

USACE RESPONSE INQUIRY #3: No modification of the existing SRI control system is required. However, the existing temperature, pressure or flow sensors that communicate with SRI control system, should be reused. The pump speed adjustment should be performed through the VFD units (no changes to the SRI control system should be done). The contractor needs to verify which sensors communicate with the existing SRI control system and re-install them on the new piping.

INQUIRY #4: Advise if the floor needs to be patched after the existing cooling tower is removed.

USACE RESPONSE INQUIRY #4: Patch existing cooling tower pad with grout.

INQUIRY #5: M-603 and M-604 have schedules for the pumps and associated VFDs, however, Drawing M-602 seems to show the existing pumps and VFDs to remain. Advise if the pumps and/or VFDs need to be replaced.

USACE RESPONSE INQUIRY #5: The existing close loop water pumps and the VFD units shall be replaced.

Sheet MD-101 will be revised to capture that requirement. Sheet MD-102 shows the pump's VFD units to be removed.

INQUIRY #6: The piping serving existing pumps does not have insulation. Confirm that the new piping between the pump inlet and heat exchanger does not need insulation.

USACE RESPONSE INQUIRY #6: The return pipe lines are required to be insulated.

INQUIRY #7: Advise on the thickness of the concrete wall the 6” pipes need to penetrate and if the wall needs to be scanned prior to coring.

USACE RESPONSE INQUIRY #7: Walls are 1' thick. Contractor shall avoid coring through reinforcement.

INQUIRY #8: Drawing M-101, Note #3 states all cooling pipes and associated fittings shall be CPVC SCH40. On the previous Barrier projects the piping was CPVC SCH80. Advise if it is to be CPVC SCH80.

USACE RESPONSE INQUIRY #8: Spec section 23 64 26, para. 2.3.1, required the CPVC pipes to be SCH80.

Note 3 on sheet M-101 will be revised to comply with the specifications.

INQUIRY #9: Drawing M-101, Note #7 states contractor to verify the connection points inside the pulser cabinets prior to the new pipes installation. Advise why the connection points need to be verified if the contractor is not making any connections in them.

USACE RESPONSE INQUIRY #9: The note will be removed.

F. AMENDMENT ACKNOWLEDGMENT: Please note that ALL amendments must be acknowledged.

SECTION 00 22 13 - SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

The following have been modified:

IMPORTANT BID NOTES

THE ABOVE SOLICITATION SECTION 00 10 00 IS TO BE USED BY BIDDERS TO SUBMIT THEIR BIDS.

IT IS ALSO CONSIDERED THE “BID SCHEDULE” AS TERMED THROUGHOUT THE SOLICITATION.

1. BID CONDITIONS

a. The Contractor shall bid ALL items that are contained in the Bid Schedule, with no exceptions. Should a Contractor fail to fully complete the bid schedule, its bid will not be considered responsive to the solicitation and eligible for the resultant contract award. Therefore, the bidder’s total price for the work shall be based on the TOTAL of all BASE items included in the Bid Schedule. The Contractor shall enter both its unit price and extended price for each Bid Item.

b. From this Solicitation, the Government intends to award one firm-fixed price contract to the responsive, responsible bidder submitting the lowest aggregate price for all Base Items. The intent is immediately award the base items at the time of award.

c. Split or multiple awards will not result from this Solicitation.

d. Bidders are required to acknowledge the receipt of all amendments to the Solicitation on the Standard Form 1442 in the space provided OR, by completing Blocks 8 and 15 of the Amendment Form itself (Standard Form 30), or by email to Amy M. Phillips at amy.m.phillips@usace.army.mil.

e. SF 1442 BACK (Page 2 of the Solicitation): Bidders shall fully complete all the required areas located on Page 2 of the Solicitation document (SF 1442 Back) - refer to Block’s 14 through 20C.

f. Section 00 45 00 (Representations and Certifications): The bidder must complete the applicable boxes found at Section 00 45 00 of this Solicitation and submit the completed Section along with all other documents required by this Solicitation. In order to place a bid in response to this Solicitation, the bidder must be registered in an “active status” at the System for Award Management (SAM) (registration can be completed on line for free at www.sam.gov). Accordingly, any bid furnished from contractor without an active registration at SAM may be considered non-responsive to the material requirements of this Solicitation and ineligible for award.

2. SUBMISSION OF BIDS:

All sealed bids must be delivered electronically per the instructions contained within this solicitation. The bid opening will be conducted telephonically via the below conference call-in number. Bids must be received by the time specified in the solicitation, otherwise they will be deemed late and unacceptable. The bid opening teleconference will begin promptly thirty (30) minutes after the bid submission time. The conference call-in number is as follows:

Conference Call-In Number: 1-877-336-1839 Access Code: 7322572 Security: 4321

The Contracting Officer with assistance from the assigned Contract Specialist will download all of the bid submissions and record all of the pertinent information prior to the conference call. The bid opening teleconference will begin promptly 30 minutes after the submission time and at that time the bid opening officer will 1) read the names of the submitting contractors and their bids, and 2) read the independent government estimate. Once the information has been disseminated, the call will come to an end. The bid abstract will be posted to the beta.sam website by close of business of the day bids are opened.

Bids: ALL SUBMISSIONS TO THIS BID ANNOUNCEMENT SHALL BE SUBMITTED ELECTRONICALLY THROUGH DOD SAFE. No paper copies, CD-ROMs or facsimile submissions will be accepted. Electronic Bid Submission is required through the Army’s Electronic File Sharing Service, DOD SAFE (https://safe.apps.mil). The DOD SAFE Application is used to send large files to individuals that would normally be too large to send via email.

There are no user accounts for SAFE. Authentication is handled via email. Anyone has access to DOD SAFE, and the application is available for use by anyone. The SAFE “Getting Started Guide” has information on how to utilize the system (https://safe.apps.mil/about.php). Instructions for uploading are as follows:

1. Send an email to the Contracting Officer and Contract Specialist to receive the link to drop off your proposal. This will need to be completed five (5) business days prior to uploading your bid.

a. Amy M. Phillips, Contract Specialist at amy.m.phillips@usace.army.mil

b. Heather Bauer, Contracting Officer at heather.d.bauer@usace.army.mil

2. You will receive an email with the link to submit your drop-off. The link will be provided no later than two

(2) business days prior to the bid due date.

3. Short Note to the Recipients: Click the Add Files or Drag and Drop your files. For file description, enter

W912P620B0028-FIRMNAME.

4. Click Upload button to send documents.

Guest users will need to check their email to verify their email address before the recipients will be notified.

****************************************ADMT 0001******************************************

3. BID GUARANTEE:

Bidders are required to submit a Bid Guarantee for this project in accordance with the Federal Acquisition Regulation Clause 52.228-1, “Bid Guarantee” – Refer to Solicitation Section 00 21 13 for the full text of this Clause.

A bid guarantee shall be submitted at 20% of the bid price or $3M whichever is the lesser. Any bidder failing to submit a Bid Guarantee will be considered non- responsive to the Solicitation and ineligible for award.

QUESTIONS: PLEASE NOTE INTERESTED BIDDERS MUST SUBMIT THEIR CONTRACTING AND

TECHNICAL INQUIRIES TO Amy M. Phillips at email: amy.m.phillips@usace.army.mil. – BE SURE TO INCLUDE THE SOLICITATION NUMBER W912P620B0028 AND PROJECT TITLED “2B Cooling System Upgrade” ON THE SUBJECT LINE OF YOUR EMAIL.

NOTE: ALL QUESTIONS SHALL BE SUBMITTED BY 1:00PM CT ON 21 SEPTEMBER 2020 TO BE

ANSWERED VIA AN AMENDMENT PRIOR TO THE BID OPENING DAY AND TIME. (Re: 52.214-6 Explanation to Prospective Bidders).

****************************************ADMT 0001******************************************

****************************************ADMT 0001******************************************

VIRTUAL PRE- BID MEETING

A virtual pre-bid meeting will be held for this project on 17 September, 2020 at 10:00a.m. (Central Time) by use of Webex..

When it’s time to join the meeting on the aforementioned date and time, please use the following weblink:

https://usace.webex.com/meet/ganiyat.f.leffler

Meeting number: 968 099 313 Meeting password: 4084984

Following the prebid meeting, Contractors are urged to visit the site independently.

At the pre- bid meeting, Government representatives will highlight specific contract requirements. The objective is to provide an information exchange between potential bidders and the Government to avoid the possibility of misinterpretation of the contract requirements. The Corps of Engineers strongly encourages all potential bidders to attend the pre- bid meeting and, in the interest of making the meeting more meaningful, prospective bidders are urged to present any written questions concerning the project bid documents, bidding, and construction requirements or other related matters prior to the pre- bid meeting. Send written questions to Amy M. Phillips at amy.m.phillips@usace.army.mil – BE SURE TO INCLUDE THE SOLICIATION NUMBER W912P620B0028

AND PROJECT TITLE ON THE SUBJECT LINE OF YOUR EMAIL.

With respect to questions, written questions may be submitted at the beginning of the pre-bid meeting and oral questions may be submitted from the floor, will only be addressed if they are clarifications of information provided in the solicitation and in subsequent amendments issued before the scheduled prebid meeting and site visit. Answers, interpretations, and decisions made at the meeting will not become official unless and until verified by an amendment to the solicitation issued prior to the receipt of bids. Following the meeting, prospective bidders will be permitted to inspect the site where services are to be performed and to satisfy themselves as to all general and local conditions that may affect the cost of performance of the contract to the extent such information is reasonably obtained.

****************************************ADMT 0001******************************************

(End of Summary of Changes)

END OF AMENDMENT NO. 0001

(The aforementioned Specification Sections and Drawing Sheet follow)

Fish Dispersal Barrier IIB Cooling System Upgrade W912P620B0028

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 10 00

GENERAL PROVISIONS

06/15

PART 1 GENERAL

1.1 REFERENCES

1.2 CERTIFICATES OF COMPLIANCE

1.3 RESPONSIBLITY OF THE CONTRACTOR

1.4 SUBMITTALS

1.5 DRUG FREE WORKPLACE

1.6 REAL ESTATE

1.7 CONSTRUCTION PROGRESS PHOTOGRAPHS

1.7.1 Photographic Documentation

1.7.1.1 Digital Photographic Media

1.7.2 Photography of Specific Work Items

1.7.3 Construction Complete Photographs

1.7.4 Payment and Acceptance

1.8 INSPECTION

1.9 CONDITION OF EXISTING STRUCTURES

1.10 PRESERVATION OF HISTORICAL, ARCHAEOLOGICAL AND CULTURAL RESOURCES

1.11 MINIMUM AMOUNT OF INSURANCE REQUIRED

1.12 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.13 PERMITS AND RESPONSIBILITIES

1.14 COORDINATION WITH OTHERS

1.15 SPECIAL SAFETY REQUIREMENTS

1.16 ELECTRICAL HAZARDS ON SITE

1.17 ONE CALL SYSTEMS FOR EXCAVATORS

1.18 ELECTRICAL POWER LINES

1.19 BORROW/DISPOSAL SITES AND QUARRIES

1.20 TAX EXEMPTION

1.21 BARRICADES AND WARNING SIGNS

1.22 PRECONSTRUCTION CONFERENCE

1.23 PROGRESS MEETINGS

1.24 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CCONTRACTS

1.25 SECURITY REQUIREMENTS

1.25.1 CLAUSE 2 - Access and General Protection/Security Policy and

Procedures

SECTION 01 10 00 Page 1

AMD_1 - 08/31/20

1.25.1.1 CLAUSE 2b - Contractors Who Do Not Require a CAC, But Require Access to a DoD Facility or Installation

1.25.2 CLAUSE 7 - Operation Security (OPSEC) Training per AR 530-1, (Operations Security)

1.25.3 CLAUSE 13 - Exposure to Classified and/or Sensitive Materials and/or Sensitive or Restricted Areas

1.25.4 CLAUSE 14 - Facility Clearance and Individual Clearances at the Appropriate Level

1.25.5 CLAUSE 15 - E-Verify Program

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

-- End of Section Table of Contents --

SECTION 01 10 00 Page 2

SECTION 01 10 00

06/15

GENERAL PROVISIONS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of materials with specification requirements must be executed in two copies.

Each certificate must be signed by an official authorized to certify on behalf of the manufacturing company and must contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply.

Copies of laboratory test reports submitted with certificates must contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet specific requirements.

1.3 RESPONSIBLITY OF THE CONTRACTOR

The Contractor shall be responsible for the professional quality, technical accuracy and the coordination of all designs, drawings and specifications furnished by the Contractor under this contract. The Contractor shall, without additional compensation, correct or revise designs, drawings and specifications.

Neither the Government's review, approval or acceptance of, nor payment for, any of the services required under this contract shall be construed

SECTION 01 10 00 Page 3 to operate as a waiver of any rights under this contract or of any cause or action arising out of the performance of this contract, and the Contractor shall be and remain liable to the Government in accordance with applicable law for all damages to the Government caused by the Contractor's negligence in connection with designs, drawings and specifications, furnished under this contract.

The rights and remedies of the Government provided for under the contract are in addition to any other rights and remedies provided by law.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following must be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Condition of Existing Structures

Coordination with Others ; G, CN

Drug Free Workplace

List of E-Verified/Eligible Candidates ; G, GSE

SD-06 Test Reports

Construction Progress Photographs ; G, CN

SD-11 Closeout Submittals

Construction Complete Photographs ; G, CN

1.5 DRUG FREE WORKPLACE

Refer to FAR CLAUSE 52.223-6 entitled DRUG FREE WORKPLACE in Section 00 70 0 - Conditions of the Contract. Submit within 45 calendar days of Contractor's receipt of the "Development and Submission of Initial Project Submittals".

1.6 REAL ESTATE

All required right-of-way, storage areas and/or other additional real

SECTION 01 10 00 Page 4 estate that has been obtained is included on the contract drawings.

In the event the Contractor requires any additional access roads and storage areas, they may obtain and utilize them at their own expense. All additional real estate agreements shall clearly relieve the Government of any potential responsibility for damages or liability resulting from the Contractor's use of such grounds. Additional agreements obtained by the Contractor should be furnished to the Contracting Officer and be coordinated and acknowledged sufficient prior to application and execution.

Additional real estate agreements may also be obtained by the Government after the solicitation. If utilized, the Contractor is required to abide by all terms and conditions as set forth in the agreements.

1.7 CONSTRUCTION PROGRESS PHOTOGRAPHS

Provide photographs documenting the work progress during construction.

Monthly photography must be performed between the first and fifth of each month during construction.

Submit photographs to the Contracting Officer no later than the tenth of each month the photographs are taken.

1.7.1 Photographic Documentation

Provide a minimum of six views from varying positions to document the monthly work accomplished. Additional views and positions may be required by the Contracting Officer to document the monthly work progress. Any additional photographs required must be done at no additional cost to the Government.

1.7.1.1 Digital Photographic Media

Photographs must be a minimum of four megapixels in JPEG format and submitted on CD-ROM or DVD. Submit two copies of all disks. All disks must be labled accordingly:

a. Contract Title,

b. Contract Number, and

c. Photography Date.

d. File name shall include date, location, and brief description.

SECTION 01 10 00 Page 5

1.7.2 Photography of Specific Work Items

Unique and specialty features of this contract also require progress and construction complete photography:

Identify special work features of the contract requiring additional photography.

1.7.3 Construction Complete Photographs

Pursuant to the final inspection by the Contracting Officer, submit photographs documenting the final conditions at the completion of the contract.

Submit photographs in the same quantity, media and labeling as the construction progress photographs.

Submit construction complete photographs within ten business days after final inspection by the Contracting Officer.

1.7.4 Payment and Acceptance

No separate payment will be made for providing approved progress and completion photographs required under this contract. All costs in connection therewith shall be considered a subsidiary obligation of the Contractor.

The progress photographs and the final conditions photographs will be jointly reviewed for accuracy and completeness by the COR and the Contractor prior to submission of each monthly pay estimate. If the Contractor fails to maintain the progress photographs as specified, the COR must deduct from the monthly progress payment an amount representing the estimated cost of the progress photographs.

1.8 INSPECTION

The presence or absence of a Quality Assurance representative shall not relieve the Contractor of responsibility for the proper execution of work in accordance with the plans and specifications.

1.9 CONDITION OF EXISTING STRUCTURES

Prior to commencement of operations by the Contractor at the site, a detailed survey will be made of all existing structures that may be affected by the Contractor's operations. The survey will be conducted in coordination with local interests, Contractor, Corps of Engineers

SECTION 01 10 00 Page 6

Representative, and private parties concerned and will be sufficient in scope to provide advance agreement among all concerned as to the condition of the existing structures. Participate in pre-construction surveys of existing structures as deemed necessary to permit determination and accurate assessment of any subsequent damage to existing structures that may be incurred during the period of the contract.

1.10 PRESERVATION OF HISTORICAL, ARCHAEOLOGICAL AND CULTURAL RESOURCES

If, during construction activities, the Contractor observes items that might have historical or archaeological value, such observations must be reported immediately to the COR so that the appropriate authorities may be notified and a determination can be made as to their significance and what, if any, special disposition of the finds should be made. Cease all activities that may result in the destruction of these resources and prevent employees from trespassing on, removing, or otherwise damaging such resources.

1.11 MINIMUM AMOUNT OF INSURANCE REQUIRED

In accordance with FAR CLAUSE entitled INSURANCE - WORK IN A GOVERNMENT INSTALLATION, the following minimum insurance coverages and limits are required. The term "Installation" referred to in this clause is deemed to mean Corps of Engineers project site or Federal property.

a. Evidence of the following minimum insurance coverages and limits, with concurrent policy expiration dates, must be received by the Department of the Army, Corps of Engineers before the Contractor can begin work. This evidence must be on a fully-completed, signed and dated ACORD Certificate of Insurance. In addition, policy endorsements must be issued by or in behalf of the insuring company or companies naming the Department of the Army, Corps of Engineers, Metropolitan Water Reclamation District of Greater Chicago, its commissioners, officers, agents, and employees; and the Burlington Northern and Santa Fe Railroad Company of Romeoville, IL as Additional Interest Insured regarding the work. The endorsements must also provide that the Department of the Army, Corps of Engineers receive direct written notice at least 30 calendar days before the effective date of any material changes to, any cancellation of, or any non-renewal of these coverages during the time period of the Contractor's work. These endorsements must also be received by the Department of the Army, Corps of Engineers before the Contractor can begin work.

b. Should the coverages expire or be terminated during the time period of the Contractor's work, the Department of the Army, Corps of

SECTION 01 10 00 Page 7

Engineers must receive an ACORD Certificate of Insurance as evidence of renewal or replacement insurance coverage and the supporting policy endorsements as specified above. The required evidence of renewal replacement insurance must be received by either the Contracting Officer or Contracting Officer's Representative at least 10 calendar days before the coverage expires or is being terminated.

c. All insuring companies must be rated A- or Excellent or better, by A.M. Best Company, an independent insurance rating service. The ACORD Certificate must list the A.M. Best Company insurance company code of listed insurance companies being offered.

Comprehensive General Liability (Occurrence policy form only) General Aggregate $ 210,000,000 Products/Completed Operations $ 102,000,000 Each Occurrence $ 101,000,000 Fire Damage Legal Liability $ 50,000

Comprehensive Automobile Liability (Including Hired Automobile Liability and Non-Owned Automobile Liability) Combined Single Limit $ 51,000,000

Employers' Liability Each Occurrence $5 ,0 00,000 Policy Limit $5 ,0 00,000 Each Employee $5 ,0 00,000

Workers Compensation (As required by state law or Federal law) $5,000,000

Umbrella Liability (Occurrence policy form only) Each Occurrence and Aggregate $5,000,000

Railroad protective liability work (within 50 feet) Each Occurrence $2,000,000 Bodily injury property damage aggregate $6,000,000

1.12 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

This clause specifies the procedure for the determination of time

SECTION 01 10 00 Page 8 extensions for unusually severe weather in accordance with the CONTRACT CLAUSE entitled "DEFAULT (FIXED PRICE CONSTRUCTION)". In order for the Contracting Officer to award a time extension under this clause, the weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

BUSINESS DAYS BASED ON A FIVE DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

16 14 8 9 6 5 4 3 3 5 7 13

Upon acknowledgement of Notice to Proceed (NTP) and continuing throughout the contract, record on the daily Contractor Quality Control report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled business day.

The number of actual adverse weather delay days must include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delays exceeds the number of days anticipated in paragraph 2, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather business days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction)".

1.13 PERMITS AND RESPONSIBILITIES

Obtain all permits/licenses required for this project as required under CONTRACT CLAUSES paragraph entitled "PERMITS AND RESPONSIBILITIES".

1.14 COORDINATION WITH OTHERS

Schedule and coordinate operations affecting other Contractors, Government hired labor forces, utilities, and/or property within the work limits.

SECTION 01 10 00 Page 9

Schedule with lead time sufficient for coordination of all involved parties as necessary for timely completion of each contract feature. As evidence of this compliance with this General Provision, furnish the COR with a copy of each coordinated schedule prior to commencing operations affecting such other Contractors, utilities, and/or property.

1.15 SPECIAL SAFETY REQUIREMENTS

Comply with all applicable Federal, state and local safety requirements including, but not limited to, those provided in EM 385-1-1 .

If applicable at the time of construction, all contractors must follow the Centers for Disease Control and Protection (CDC) Guidelines related to the Covid-19 pandemic, State Executive Orders, and any local rules/required procedures to prevent the spread of Covid-19.

1.16 ELECTRICAL HAZARDS ON SITE

The Contractor is advised that routine barrier operations may introduce stray, pulsed direct current into the land, water, and structures adjacent to the barrier facility. Maximum observed stray current levels during step, reach, and touch potential testing have been as high as 346 Volts peak to peak. This corresponds to 346 mA over a 1000 ohm resistor. The current located on and around the site is pulsed direct current which can be measured with a digital oscilloscope capable of producing a visual readout of the wave form to assess the peak to peak voltage. A conventional voltage meter without the ability to visualize the wave form will be inadequate to adequately assess the peak to peak voltage of the pulsed direct current on site. The stray current intensity at any given locale may be dependent upon factors such as soil moisture, canal water conductivity, and operational characteristics of the barrier facility.

The contractor will be expected to develop, submit, and implement a plan to effectively mitigate occupational risks posed by the stray current as part of their Activity Hazard Analysis (AHA). Documents related to previously-conducted stray current field testing are located in Attachment 1 and 2 of this Section. Attachment 1 is an assessment of ground currents that present a safety hazard to those working on the site. Attachment 2 is a survey of currents in to water and in water at and adjacent to the fish barriers. However, the Contractor is advised that such documentation represents conditions present at the time observations were made and, thus, the data presented should not be construed as being predictive of conditions present at any other time.

1.17 ONE CALL SYSTEMS FOR EXCAVATORS

One call systems, established by law, are operated by owners of

SECTION 01 10 00 Page 10 underground facilities for excavators. Upon notification by an excavator through a one call system, all participating operators of underground facilities in a covered area will identify and locate their facilities.

One call systems will be identified by contacting the following:

ILLINOIS

JULIE UTILITIES PROTECTION SERVICES

1-800-892-0123

1.18 ELECTRICAL POWER LINES

Study the construction plans and site and know in detail all locations of power lines within the rights of way. Prior to performing any construction operation adjacent to power lines, appropriate danger signs must be provided where any equipment scheduled for use on the site is capable of contacting such lines. Confirm the location of underground lines, contact the appropriate council listed in paragraph ONE CALL SYSTEMS FOR EXCAVATORS. Aerial power lines must either be shut off and a positive means taken to prevent the lines from being energized, or clearances required by EM 385-1-1 , Safety and Health Requirements Manual, must be maintained. Work must not proceed into dangerous areas without an additional workman being assigned the crew to watch the movements of other personnel and equipment to assure that designated clearances are maintained.

1.19 BORROW/DISPOSAL SITES AND QUARRIES

This paragraph, Borrow/Disposal Sites and Quarries, applies only to the ability of the Contractor to utilize a particular borrow/disposal site or quarry, and does not address the use of materials from that site or quarry. Nothing in this paragraph, Borrow/Disposal, shall relieve the Contractor of complying with the specific testing requirements for material taken from any borrow/disposal sites or quarries as set forth in the technical provisions of this Contract.

a. Definitions. For purposes of this general provision, the following definitions apply:

(1) Government-Suggested borrow/disposal site or quarry means a site or quarry suggested by the Government for use by the Contractor concerning which all applicable Federal, state and local environmental statutory and regulatory requirements may or may not have been satisfied.

(2) Commercial/existing borrow/disposal site or quarry means a site or quarry which is either in the business of providing borrow

SECTION 01 10 00 Page 11 material or has been used as a disposal site for other purposes and is available for use; and concerning which all applicable Federal, state and local environmental statutory and regulatory requirements have been satisfied.

(3) Contractor-chosen borrow/disposal site or quarry means a site or quarry chosen by the Contractor for use concerning which none or not all of the applicable Federal, state and local environmental statutory and regulatory requirements have been satisfied.

b. If a borrow/disposal site or quarry is identified in the contract specifications as Government-Suggested, it is the responsibility of the Contractor to ascertain whether or not all Federal, state and local environmental statutory and regulatory requirements have been satisfied. If any of such requirements have not been satisfied, the Contractor is required to follow the procedures set forth in paragraph d(4) below. Use of such a site or quarry must be approved by the Contracting Officer.

c. If the Contractor chooses a commercial/existing borrow/disposal site or quarry, the Contractor is not required to ensure that all applicable Federal, state and local environmental statutory and regulatory requirements have been satisfied, but is required to provide to the Government either, as a minimum, a letter from the owner/operator of the commercial/existing borrow/disposal site or quarry certifying that all environmental and operating permits have been acquired, or actual copies of all such environmental and operating permits. Use of such a site or quarry must be approved by the Contracting Officer. Adhere to all rules, regulations and business practices required by the owner/operator.

d. If a Contractor decides to use a Contractor-chosen borrow/disposal site or quarry, it is the Contractor's responsibility to ensure that all applicable Federal, state and local environmental statutory and regulatory requirements have been satisfied. Use of such a site or quarry must be approved by the Contracting Officer, and such approval shall not be granted unless all applicable requirements have been met and such use of the site does not pose significant environmental impacts.

(1) The specific requirements which must be met by the Contractor before a Contractor-chosen (or, when applicable, a Government-recommended) site or quarry must be approved by the COR include, at a minimum, but are not necessarily limited to, compliance with the following environmental laws, regulations and

SECTION 01 10 00 Page 12 executive orders:

Federal Laws, Regulations, and Executive Orders Name Agency Section 404, U.S. Army Corps of Engineers, Clean Water Act Detroit District (IN/WI) (Permit) Chicago District (IL)

Section 10, River U.S. Army Corps of Engineers and Harbor Act of 1899 (Permit)

Emission U.S. Environmental Protection Limitations, Agency Clean Air Act

Section 9, U.S. Fish and Wildlife Service, Endangered Species Barrington Office (IL) Act of 1973 Bloomington Office (IN) Green Bay Office (WI)

Section 703, U.S. Fish and Wildlife Service Migratory Bird Treaty Act of 1918

Section 106, Illinois Historic Preservation National Historic Agency (IL) Preservation Act of 1966

Flood Plain U.S. Army Corps of Management, Engineers, Chicago District Executive Order 11988

Surface Mining Bureau of Mines Control and Reclamation Act of 1977

Resource U.S. Environmental Protection Conservation and Agency Recovery Act of 1976

Toxic Substance U.S. Environmental Protection Control Act Agency

Illinois State Statutes

SECTION 01 10 00 Page 13

Construction Illinois Department of Transportation, Within a Floodway Division of Water (Permit) Resources

Illinois Illinois Department of Endangered Species Conservation

Section 401, Illinois Environmental Protection Clean Water Act Agency, Division of Water (Permit) Pollution Control

Section 402, Illinois Environmental Protection Clean Water Act Agency, Division of Water (NPDES Permit) Pollution Control

State Agency Illinois Historic Historic Resources Preservation Agency Protection Act

Human Grave Illinois Historic Preservation Protection Act Preservation Agency

It is the Contractor's responsibility to ensure that all applicable Federal, state and local environmental statutory and regulatory requirements are satisfied, regardless of their presence on, or absence from, the above list.

(2) It is the responsibility of the Government to ensure that the requirements of the National Environmental Policy Act (NEPA) have been complied with. If the Contractor decides to use a site or quarry which has not previously undergone an environmental review under NEPA (either Government-recommended or Contractor-chosen), notify the Contracting Officer, who shall arrange for such an environmental review. This review and compliance process may include inter-agency coordination and the preparation and circulation for public review of environmental documentation. It is the responsibility of the Contractor to allow sufficient time in the construction schedule to accommodate this review and compliance process, and to provide the Contracting Officer with any and all information that the Contracting Officer deems necessary to facilitate the process. The review and compliance process requires a minimum time frame of 90 calendar days, but could take substantially longer, possibly up to one year or, in unusual circumstances, even longer than one year, to complete.

Any construction delays caused by the need to conduct an environmental review under NEPA shall be solely the responsibility

SECTION 01 10 00 Page 14 of the Contractor, at no additional cost to the Government.

(3) It is also the responsibility of the Government to perform Section 7 consultation under the Endangered Species Act, to coordinate with the United States Fish and Wildlife Service and appropriate state wildlife agencies under the Fish and Wildlife Coordination Act, and to perform a Farmland Conversion Impact Rating under the Farmland Protection Policy Act for all Government-Suggested or Contractor-Chosen sites. This must be accomplished concurrently with the NEPA environmental review process. It is the responsibility of the Contractor to allow sufficient time in the construction schedule to accommodate these consultation and coordination requirements as well as the NEPA review process, and to provide the Contracting Officer with any and all information that the Contracting Officer deems necessary to facilitate the completion of these consultation and coordination requirements.

(4) The Government cannot guarantee that any Government-Suggested or Contractor-chosen site is capable of complying with all applicable Federal, state and local environmental statutory and regulatory requirements and may reject any such site proposed for use by the Contractor for environmental reasons. If the Contracting Officer does not approve the use of a Government-recommended or Contractor-chosen borrow/disposal site or quarry because not all applicable Federal, state or local environmental statutory and regulatory requirements have been satisfied, or because the Government determines that such site or quarry could not be used for environmental reasons as a result of the environmental review under NEPA, it is the Contractor's responsibility to locate an alternate site or quarry and to perform all necessary reviews to obtain approval of the use of such alternative site or quarry. Any construction delays caused by the need to locate an alternate site or quarry, shall be solely the responsibility of the Contractor, at no additional cost to the Government.

(5) Nothing in this clause shall relieve the Contractor from the responsibility of obtaining all non-environmental permits and licenses which may be required under Federal, state or local statutes, regulations and ordinances.

1.20 TAX EXEMPTION

I LLI NOI S RETAI LER' S OCCUPATI ONAL TAX AND USE TAX EXEMPTI ON

SECTION 01 10 00 Page 15

Pursuant to the rulings of the Illinois Department of Revenue, materials which are to be physically incorporated into real estate owned by the Government are exempt from Illinois Retailers' Occupational Tax and Use Tax. However, sales of tools, fuel, lumber for forms and other end use or consumption items which are not physically incorporated into real estate are taxable sales. After contract award, the Contractor may request the Government Sales Tax Exemption Number, which must be used when purchasing tax exempt material. Nothing herein shall be construed to affect the provisions contained in Section 00700, Contract Clause entitled FEDERAL, STATE, AND LOCAL TAXES.

1.21 BARRICADES AND WARNING SIGNS

Provide and maintain barricades, danger and warning signs and suitable and efficient lights at all points of entry to the section or sections of roadway which are to be closed to public travel during construction operations under the contract. Furnish flagmen and watchmen to warn and direct traffic or to prevent travel on any portion of roadways during the periods in which operations under the contract are performed as may be required to ensure safety and prevent accidents. All facilities furnished by the Contractor under this paragraph must be as prescribed by local highway authorities and must be subject to approval by the Contracting Officer. Traffic control must be in accordance with the by the State and local authorities having jurisdiction. A copy of the plan must be submitted to the Contracting Officer for approval. Separate payment shall not be made for any costs incurred by the Contractor in compliance with the provisions of this paragraph but all costs therefore shall be considered as a subsidiary obligation of the Contractor and are included in the contract price for other contract items as applicable.

1.22 PRECONSTRUCTION CONFERENCE

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.

1.23 PROGRESS MEETINGS

A progress meeting will be held weekly. The meetings will occur on-site, in the Contractor's field trailer, as conditions allow. The day for conducting meetings will be mutually agreed to between the Contractor, the

SECTION 01 10 00 Page 16

Government and the Local Sponsors (DOE and CPD) within 10 calendar days after receipt of the notice to proceed. Unless the COR specifically indicates in writing otherwise, prepare meeting agendas and meeting minutes for each meeting.

Progress meeting will consist of a written agenda of topics and issues to be discussed during the meeting and followed up with draft meeting minutes prepared by the Contractor. The draft meeting minutes will be emailed out to all attendees one business day after the meeting for review and approval. The review and approval process will allow for mutual acceptance of the draft minutes as written, or editing to add, delete, and/or correct items that were covered in the weekly meeting. The edited draft meeting minutes will be published and handed out by the Contractor at each following week's progress meeting. If all attendees agree the minutes have been properly edited; then those minutes become the official final minutes of the previous week's progress meeting. All attendees will be required to sign an attendance sheet that will become an attachment to the official final meeting minutes.

The progress meeting agendas will at a minimum contain the following items (Italic wording represents example input per item):

1. Contract Schedule and S-curve status

a. Dollar driven schedule how much will the Contractor need in the next three months

b. Status of the contract and funds

2. Weather days for the last two weeks

3. Go over Punch/Discrepancy list Items

a. Not in contract compliance

b. Methods of correction

c. Where does it fit in the schedule?

d. Is it holding up a critical path item?

e. Is it a critical path item?

4. Status of stored materials

a. When to fund stored materials and when to subtract materials from the stored state

b. Where is the item on the scheduled?

5. Work performed since last progress meeting

a. Last week did we do what we said we were going to do?

b. Is there some slippage according to schedule?

6. Two week look ahead.

SECTION 01 10 00 Page 17

7. Submittal register open / closed items.

a. Status of needed submittals

b. Missing/overdue

8. Visit any open items from previous week's agenda.

9. Pay estimate

a. Questions

b. Concerns

c. Progress

10. Status of safety plan and accident prevention

11. Review of the QCS program

a. Questions

b. Problems

c. Observations

d. Review Reports (Contractor Action Items, Submittals in Review, Submittals due in 30 calendar days, etc)

12. Status and review of testing

a. Concrete

b. Soil

c. Asphalt

13. Requests for Information (RFIs) / RFC's

a. New

b. Unanswered

14.…