W81G6672378885
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
REFERENCE: W912P6-18-B-0011 ABRAHAM LINCOLN NATIONAL CEMETERY 5600 NICHE COLUMBARIUM AND 1350 IN-GROUND CREMAINS PROJECT
- The Bid Opening Date has extend by w ay of this Amendment. ALL BIDS ARE DUE ON October 25, 2018, “PRIOR” TO 2:00PM (Chicago, Local Time). The Bid Opening place remains the same.
- This Amendment provides the correct revised specif ication sections and revised plan sheets that w ere not provided under Amendment
0001.
- Point of Contact for this Amendment is Anita R. Simpkins at (312) 846-5370 or at anita.r.simpkins@usace.army.mil.
- Description of revisions follow on the next pages.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Oct-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P618B0011
X 9B. DATED (SEE ITEM 11)
19-Sep-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Oct-2018
CODE
U.S. ARMY ENGINEER DISTRICT, CHICAGO
231 SOUTH LASALLE STREET SUITE 1500
CHICAGO IL 60604-1437
W912P6 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P618B0011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
A. AMENDED Solicitation Sections: None
B. AMENDED SPECIFICATION SECTIONS: Bidders shall remove all revised specification sections provided under Amendment 0001 and replace with the specification sections provided as part of this Amendment.
SECTION NUMBER TITLE
01 35 26 GOVERNMENT SAFETY REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 22 00 PRICE AND PAYMENT PROCEDURES
01 00 00 GENERAL REQUIREMENTS
00 31 32.13 SUBSURFACE DRILLING AND SAMPLING INFORMATION
APPENDIX A 00 31 32.13 APPENDIX A - PREVIOUS SOIL BORINGS ADJACENT SITES
APPENDIX B 00 31 32.13 APPENDIX B - SOIL BORING RESULTS TTL 2018
04 43 00 NATURAL STONE VENEER
04 40 10 CUT STONE ASSEMBLIES
10 14 00 EXTERIOR SIGNAGE
New revised Specification Sections being provided as part or Amendment 0002 are as follows:
SECTION NUMBER PARAGRAPH AND DESCRIPTION OF CHANGE
00 14 00 2.11 Bronze Plates, 2.12 Granite Section Markers, 2.13 Gravesite Layout Markers
00 31 32.13 APPENDIX A 00 31 32.13 APPENDIX A - PREVIOUS SOIL BORINGS ADJACENT SITES
00 31 32.13 APPENDIX B 00 31 32.13 APPENDIX B - SOIL BORING RESULTS TTL 2018
01 52 02 SENTENCE added to paragraph 3.2.1 Administrative Field Offices
B. AMENDED PLAN SHEETS: Bidders shall remove all revised plan sheets provided under Amendment
0001 and replace with the plan sheets provided as part of this Amendment. (CS-106, CG-304, CG-104, LI-
101, LI102, LI103, LI-104, LP102, and CU-102)
New revised Plan Sheets being provided as part or Amendment 0002 are as follows:
SHEET REF. NO. TITLE AND DESCRIPTION
CP502 Detail F1 Section Marker updated.
CP101 Legend updated with features not relevant to sheet.
CP102 Note three place holder deleted.
D. USACE’S RESPONSES TO CONTRACTOR’S INQUIRES FOLLOW:
Question #1 - Please provide or give further direction where the referenced Appendix A is found. This document is referenced throughout the bid documents, but the Appendix is not included.
USACE REPONSE FOR QUESTION #1 – Specification Section 00 31 32.13 Appendix A - Previous Soil Borings Adjacent Sites and 00 31 32.13 Appendix B - Soil Boring Results TTL 2018 is included in AMD 0002.
Question #2 - Please provide as-builts or structural calcs for the bridge leading to the haul road.
USACE RESPONSE FOR QUESTION #2 – As-builts of the bridge are provided in attached amendment.
Question #3 - Sheet SS001, note 1 states to match the adjacent columbarium in color, finish and texture. Detail C6/SS301 clearly shows this to be a match for Columbarium #7, but not #6 which is directly adjacent to our new one. Please advise what columbarium we are to match.
USACE REPONSE FOR QUESTION #3 - See specification Section 04 43 00 paragraph 2.1, it shall match Columbarium 7.
Question #4 - The original specifications for this project do not reference the Columbarium, Wall or Row Designators. The columbarium markers are referenced in the amendment as to be in Section 04 43 00, but aren’t. Our material provider will need these specifications in order to properly price what is anticipated by the NCA and USACE. Can you help me out with this?
USACE RESPONSE FOR QUESTION #4 – See Section 10 14 00, 2.11 for additional requirements on the designators.
Question #5 - The portions of the drain pipe that are parallel to the columbarium at the bottom of the filter rock runs.
USACE REPONSE FOR QUESTION #5 - See Plan Sheet CU-601 for portions of the drain pipe that are parallel to the columbarium at the bottom of the filter rock runs.
Question #6 - The 1.5' long portions at the bottom of the stone drainage pit for the flower watering stations.
USACE REPONSE FOR QUESTION #6 – See Plan Sheet LS501 - Detail D1 for 1.5' long portions at the bottom of the stone drainage pit for the flower watering stations.
Question #7 - None of the pipe is imbedded in the concrete, it is at the bottom of a rock drain on top of the columbarium spread footings.
USACE REPONSE FOR QUESTION #7 – See Plans Sheets CU-501 -Detail B6 & F6, SS301, SS302, SS501 - Detail A2
Question #8 - Please provide spec section for the gravesite grid monument.
USACE REPONSE FOR QUESTION #8 – This information is included in the amended SECTION 10 14 00, 2.13 GRAVESITE LAYOUT MARKERS that is part of Amendment 0002.
Question #9 - Due to the potential cost impact and technical changes that could arise from answers to RFI’s, we respectfully request an extension to the proposal due date. It is stated as of now, that the deadline for RFIs is Wednesday, October 17th, per Amendment 1. In the best case scenario, if the government’s responses could be answered and returned to the contractors in one (1) day, by the end of Thursday October 18th, contractors would only have one (1) remaining business day to review the answers, make technical changes and coordinate with subcontractors based on answered RFIs, before the
Bid Opening on Monday October 22nd. Therefore, we request a bid extension of one (1) week from the receipt of RFIs so that contractors have enough time to review and make any necessary changes.
Arrangements for the bid delivery have to be made in advance and we would appreciate as much notice as possible of a change to the bid date, if the date can be extended.
USACE REPONSE FOR QUESTION #9 – The bid due date has been extended by way of Amendment 0002.
The Bid Opening date has been extended to October 25, 2018, ALL BIDS MUST BE RECEIVED “PRIOR” TO 2:00PM (Chicago, Local Time). The Bid Opening place remains the same.
Question #10 - Will a functional load test be required for the columbarium?
USACE REPONSE FOR QUESTION #10 – Specification Section 03 48 24 PRECAST CONCRETE COLUMBARIUM UNITS paragraph 1.2.7 Functional Load Tests addresses this question. It states that the tests will be done "If required by the COR, ...". This is a Quality Assurance test that the COR of the construction contract might require if the COR feels for some reason the units being delivered to the site don't meet the specifications.
Question #11 - To what extent is the laydown area required to be restored? Please provide detail.
USACE REPONSE FOR QUESTION #11 – All areas disturbed by construction activities shall be restored, per note 2 on Plan Sheet GC102.
Question #12 - What is the lead time for the government furnished, contractor installed Niche Covers?
USACE REPONSE FOR QUESTION #12 – COR will coordinate with the National Cemetery Administration in procurement of the niche covers. Lead time obtained after the contract has been awarded.
Question #13 – A subcontractor mentioned that there is a single headstone approximately located near the northern side of the work area.
USACE REPONSE FOR QUESTION #13 – We revisited the survey data, work limits over laid on an aerial image, and photographs from the site. We could not readily locate a headstone inside the work limits.
It’s assumed that a Section Marker in the vicinity of the work limits, maybe referenced by the contractor.
If this is still a concern, please provide additional information (pictures or location) and we will address more fully.
Question #14 - Is that headstone inside the work limits of the project?
USACE REPONSE FOR QUESTION #14 – See USACE response to Question #13 above.
Question #15 - Is the headstone indication of a single grave?
USACE REPONSE FOR QUESTION #15 - See USACE response to Question #13 above.
Question #16 - Will the contractor have to work around the headstone/grave?
USACE REPONSE FOR QUESTION #16 - See USACE response to Question #13 above.
Question #17 - It was mentioned in Questions and Answer #5 from Amendment 1 that the Index of drawings provided in section “252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)” has been updated in Amendment 1, however, the section was not updated and provided in the Amendment.
Please provide an updated list of drawings for section 252.236-7001.
USACE REPONSE FOR QUESTION #17 – The sheet index was updated in 252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS, no additional sheets were added in Amdnement 0001.
Question #18 - The list of Drawings from this section “252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)” does not match the index of drawings provided in the original RFP Drawings.
This conflicting information leads us to assume that we might be missing drawings. Can you please provide us with an accurate “252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)” section from the RFP so that we can compare this list to the drawings that were provided in the original RFP.
USACE REPONSE FOR QUESTION #18 - See USACE response to Question #17 above.
Question #19 - In Amendment 1 there is supposed to be the boring reports but I do not see them, I believe they were not added to the amendment and other drawings were duplicated at the end of the amendment.
USACE REPONSE FOR QUESTION #19 – See USACE response to Question #1 above.
*Question #20 - Is all the PVC slotted or just the 4” on page CU 102? Does all the drain pipe need to be embedded in 4” of concrete or just the 4” PVC?
USACE RESPONSE FOR QUESTION #20 – Only pipe that is the slot perforated pipe is the following:
1.) See Sheet CU-601 for portions of the drain pipe that are parallel to the columbarium at the bottom of the filter rock runs.
2.) See Sheet LS501 - Detail D1 for 1.5' long portions at the bottom of the stone drainage pit for the flower watering stations.
3.) See Sheets CU-501 -Detail B6 & F6, SS301, SS302, SS501 - Detail A2,the pipe is not imbedded in the concrete, it is at the bottom of a rock drain on top of the columbarium spread footings.
Question #21 - No Specifications found for the item below: Elastomeric Waterproofing Membrane Per Detail C5 / SS302
USACE REPONSE FOR QUESTION #21 – See specification section 04 40 10 CUT STONE ASSEMBLIES, 2.5.2.
Question #22 - Is the storm sewer live and what size is it where manhole #2 is connecting CU102. Is M21&M21A on the chart 12” RCP(CU-601)?
USACE REPONSE FOR QUESTION #22 – 18" storm sewer is active. Labels were added\updated to amended Plan Sheets CU102, CU502 and CU601.
Question #23 - The original specifications for this project do not reference the Columbarium, Wall or Row Designators. The columbarium markers are referenced in the amendment as to be in Section 04 43 00, but aren’t. Our material provider will need these specifications in order to properly price what is anticipated by the NCA and USACE. Can you help me out with this?
USACE REPONSE FOR QUESTION #23 - See Plan Sheet SS-203 and Section EXTERIOR SIGNAGE 10 14 00, Section on Bronze Plaque included in AMD 002.
Question #24 - Will 8” CMU, fully reinforced and grouted be an acceptable alternative to the concrete piers shown at each end of the niches? This allows a better fit for the veneer and limestone caps. It is our understanding that the previous Columbaria at this site used the CMU method of construction for the piers. Reference: Sheets SS301 and SS302.
USACE REPONSE FOR QUESTION #24 – No.
Question #25 - In the Revised section 01 35 26 Government Safety Requirements AMD0001 09-30-18 in 1.7 Accident Prevention Plan under 1.7.1b. Names and Qualifications on page 15 it states that “As a minimum, designate and submit qualifications of competent persons for each of the following major areas:
excavation; scaffolding; fall protection; hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents; and personal protective equipment and clothing to include selection, use and maintenance.” Do all of the listed “major areas” in the section above apply to this project?
USACE REPONSE FOR QUESTION #25 – The contractor shall refer to the list to determine which personnel must have qualification documentation submitted, based on the work plan and pertinent sections of the Accident Prevention Plan and/or Activity Hazard Analyses. In cases where no need exists for a competent person that is listed in the specifications, the contractor should disregard that respective requirement.
Question #26 - Please include the Boring results as mentioned in the RFI response and noted as part of Appendix A and Appendix B.
USACE REPONSE FOR QUESTION #26 - See USACE response to Question #1 above.
Question #27 - Can CMU be used instead of Cast-in-place Concrete as has been previously done on existing columbarium at that site?
USACE REPONSE FOR QUESTION #27 - No
Question #28 - Please extend the bid date to allow for better subcontractor coverage.
USACE REPONSE FOR QUESTION #28 - See USACE response to Question #9 above.
ALNC COLUMBARIUM AND IN-GROUND CREMAINS PROJECT W912P618B0011
TABLE OF CONTENTS
AMD0002 – 09/18/18
PROJECT TABLE OF CONTENTS
DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS
00 10 00
SOLICITATION
00 21 00
INSTRUCTIONS
00 21 13
INSTRUCTIONS TO BIDDERS
00 45 00
REPRESENTATIONS AND CERTIFICATIONS
00 70 00
CONDITIONS OF THE CONTRACT
00 73 00
SUPPLEMENTARY CONDITIONS
DIVISION 00 GENERAL REQUIREMENTS
00 31 32.13 SUBSURFACE DRILLING AND SAMPLING INFORMATION
DIVISION 01 GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 13 20 PROJECT SCHEDULE
01 22 00 PRICE AND PAYMENT PROCEDURES
01 33 00 SUBMITTAL PROCEDURES
01 35 26.00 03 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 REFERENCE PUBLICATION
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE RMS CM
01 52 02 TEMPORARY CONSTRUCTION FACILITIES
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 02 EXISTING CONDITIONS
02 41 10 DEMOLITION AND SITE CLEARING
DIVISION 03 CONCRETE
03 30 50 SITE WORK CONCRETE
03 30 53 CAST-IN-PLACE CONCRETE
03 48 24 PRECAST CONCRETE COLUMBARIUM UNITS
DIVISION 04 MASONRY
04 40 10 CUT STONE ASSEMBLIES
04 43 00 NATURAL STONE VENEER
04 73 00 COLUMBARIUM NICHE COVERS
DIVISION 07 THERMAL AND MOISTURE PROTECTION
07 92 00 JOINT SEALANTS
DIVISION 10
10 14 00 EXTERIOR SIGNAGE
DIVISION 26 ELECTRICAL
26 05 11 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS
26 05 19 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
DIVISION 31 EARTHWORK
SECTION 01 00 00 Page 7
AMD0002 - 09/30/18
c. The Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Cemetery. Interruption time approved by the Cemetery may occur at other than Contractor's normal working hours at no additional cost to the Government.
d. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR, which may require the work to be performed off hours which shall be done at no additional cost to the Government.
e. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
1.5.4 Abandoned Lines
All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed. Lines shall be capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
1.5.5 Traffic Control
To minimize interference of construction activities with flow of Cemetery traffic, comply with the following:
a. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times.
b. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article USE OF ROADWAYS.
1.5.6 Coordination of Construction
The Abraham Lincoln National Cemetery will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the site. Contractor is responsible to ensure that no contract work interferes with any funeral, ceremony, procession, or visitation to be delayed, altered, or otherwise impacted in such a way that the dignity or security of the event is compromised.
The burial activities at a National Cemetery shall take precedence over construction activities. Cooperation and coordination with the Cemetery Director, through the COR, in arranging construction schedule to cause the least possible interference with Cemetery activities in actual burial areas, SECTION 01 00 00 Page 8
AMD0002 - 09/30/18
is required. Construction noise during the interment services shall not disturb the service. Coordination of work may require that equipment that is heard from the service location be shut-off, or moved out of the area prior to the service, as acceptable to the Cemetery Director through the COR. Trucks and workmen shall not pass through the service area during this period.
a. Work Hours: The Contractor must restrict all construction activities, including start-up and warming of equipment, to the following schedule, unless otherwise approved by the Contracting Officer: Monday through Friday between 7:30 a.m. and 5:00 p.m. or daylight hours, whichever is less. Saturday work may be permitted with 2 days advance notice and the prior approval of the Contracting Officer. No work will be permitted on Sundays or federal holidays.
Access to the job site will be allowed 30 minutes prior to starting time.
b. Construction Vehicle Speed: Limit onsite construction vehicle speeds to the posted speed limits, unless otherwise approved.
c. All work involving use of tools or equipment which would disrupt or interfere with any interment service or ceremony conducted in the immediate vicinity of the work sites shall cease until the service has been competed.
d. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
e. Discontinue work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, and clean up all areas of operation adjacent to functioning areas of the Cemetery, including existing burial sections and any other areas identified by the COR before these dates.
f. Clean-up activities shall include the removal of all equipment from beyond the fenced construction area, tools, materials and debris, and leaving the areas in a clean, neat condition.
1.6 ALTERATIONS
1.6.1 Survey
Before any work is started, make a thorough survey with the COR of the site in which alterations are to occur and areas which are anticipated routes of access. The Contractor shall video the condition of the construction limits and hauling routes prior to any construction or moving of equipment. This shall be done in the presence of the Contracting Officer (give 48 hours notice). The Contractor shall provide two copies of the video to the Government. At the completion of the contract, the Contractor shall restore all work areas to their pre-construction condition and to the approval of the Contracting Officer. Video shall include:
a. Existing conditions.
SECTION 01 00 00 Page 13
AMD0002 - 09/30/18
reduced pressure backflow preventer at each connection to the existing potable water system. Water usage from the existing distribution system, where available, shall be provided at no cost to the Contractor. Pressure, flow rate and volume of water shall be provided at conditions that will not disrupt the operations of the existing system, provide any facilities required to make the water source characteristics suitable for Contractor's intended use(s) without adversely impacting the existing system.
b. Maintain connections, pipe, fittings and fixtures and conserve water use so none is wasted. The Contractor “may” obtain water by connecting to the functional Cemetery water distribution system subject to conditions as stated below. Failure to stop leakage or other wastes, or causing unacceptable adverse impacts on the existing system, will be cause for immediate revocation (at COR's discretion) of use of water from the Cemetery's system and will require or result in the Contractor connection(s) being immediately shut-off.
1.13 GOVERNMENT-FURNISHED PROPERTY
As soon as the project construction schedule has been developed, the Contractor shall notify the COR of the date they anticipate the need for the Government furnished niche covers to be delivered onsite. The Government shall deliver to the Contractor the Government-furnished property shown on the Schedule below.
DESCRIPTION QUANTITY
Niche Covers 5,600
Estimated value of government furnished equipment: $280,000 ($50 each). The contractor shall replace niche covers that were damaged through his handling of the niche covers at the full replacement cost.
Equipment furnished by the Government to be installed by the Contractor will be furnished to the Contractor at the Cemetery.
Storage space for equipment will be provided by the Government and the Contractor shall be prepared to unload and store such equipment therein upon its receipt at the Cemetery.
Notify COR in writing, 60 calendar days in advance, of date on which Contractor will be prepared to receive equipment furnished by Government.
Arrangements will then be made by the Government for delivery of equipment.
a. Immediately upon delivery of equipment, the Contractor shall arrange for a joint inspection thereof with a representative of the Government. At such time the Contractor shall acknowledge receipt of equipment described, make notations, and immediately furnish the Government representative with a written statement as to its condition or shortages.
b. The Contractor thereafter is responsible for such equipment until such time as acceptance of contract work is made by the Government.
Completely assemble and install the Government furnished equipment in place ready for proper operation in accordance with specifications and drawings.
SECTION 01 00 00 Page 14
AMD0002 - 09/30/18
1.14 CONSTRUCTION DIGITAL IMAGES
1.14.1 General
Prior to commencement of operations by the Contractor at the site, a detailed survey will be made of all existing structures, including adjacent roads that may be affected by the Contractor's operations. The survey will be conducted in coordination with local interests, Contractor, Corps of Engineers Representative, and private parties concerned and will be sufficient in scope to provide advance agreement among all concerned as to the condition of the existing structures. Participate in pre-construction surveys of existing structures as deemed necessary to permit determination and accurate assessment of any subsequent damage to existing structures that may be incurred during the period of the contract. Photographs and videos must be submitted to shown conditions existing prior to start of construction. Submit all videos at 720P minimum resolution in mpeg format.
During the construction period through completion, furnish the COR with digital images on a disc and include one color print of each image. Digital views shall be taken of exterior and aerial photographs as selected and directed by COR.
1.14.1.1 Unmanned Aerial Systems (UAS)
Unmanned Aerial Systems (UAS) Photography is authorized using systems with encrypted command and video links.
Operators must meet FAA requirements for operation of UAS.
The attached list of systems are pre-approved for contractor use for this contract.
Contractor must submit a technical data sheet to the USACE Aviation and Remote Systems Program (HQAviation@USACE.army.mil) for approval prior to operations. The approval indicates that the system is allowed to be flown on the project site, and does not provide mission approval or risk acceptance.
1.14.1.2 Formats
Each view shall be taken with a professional grade camera with minimum size of six megapixels (MP) and the images will be a minimum of 2272 pixels by 1704 pixels for the eight inch by 10 inch prints and 2592 pixels by 1944 pixels for the 16 inch by 20 inch prints, as per these specifications:
Take digital photos of the daily work in progress, including close-ups. The photographs shall be of the actual work as it progresses. The images shall be of both close-up in nature as well as panoramic in nature to get the feel for the entire work in progress. In addition, work of product installations that are going to be covered up shall be taken.
Images of the site will be taken at monthly intervals. However, the COR may also direct the taking of special digital images at any time prior to completion and acceptance of contract.
Images shall be taken by a commercial photographer and must show distinctly, at as large a scale as possible, all parts of work embraced in the picture.
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
08/18
PART 1 GENERAL
1.1 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this Contract for which Contract job amountor unit price payments will be made are listed in the BID SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular bid item must be included in the listed bid item most closely associated with the work involved. The price and payment made for each bid item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; delivery, storage, and handling of materials; performing all Contractor quality control, environmental protection, meeting safety requirements, tests and reports, potholing, obtaining permits, costs incurred for all disposal fees and permit fees; and all work required for which separate payment is not otherwise provided. Refer to the Contract Clause: CONTRACT PRICES - BIDDING
SCHEDULES.
1.1.1 Mobilization (Bid Item 0001)
1.1.1.1 Payment
All costs connected with the mobilization of all of the Contractor's drilling and blasting plant and equipment will be paid for at the contract lump sum price for this item.
Payment will be made at the applicable lump sum price for mobilization of all the Contractor's plant and equipment to complete the work. Payment constitutes full compensation for all plant, labor, equipment, and incidentals associated with mobilization. Costs associated with daily mobilization will not be included in this cost. Daily mobilization will be included in the unit prices of materials being provided.
1.1.1.2 Unit of Measure
Unit of measure: JOB
1.1.2 Demobilization (Bid Item 0002)
1.1.2.1 Payment
All costs connected with the demobilization of all of the Contractor's drilling and blasting plant and equipment will be paid for at the contract lump sum price for this item.
Payment will be made at the applicable lump sum price for demobilization of all the Contractor's plant and equipment to complete the work. Payment constitutes full compensation for all plant, labor, equipment, and incidentals associated with demobilization. Costs associated with daily demobilization will not be included in this cost. Daily demobilization will be included in the unit prices of materials being removed.
1.1.2.2 Unit of Measure
Unit of measure: JOB
1.1.3 Site Clearing (Bid Item 0003)
1.1.3.1 Payment
Payment for site work will be made at the contract job price for "Site Clearing", which price and payment shall constitute full compensation for providing all plant, labor, material and equipment to perform all operations for the project site, access\haul roads, staging and storage area, and spoil pile area including, but not limited to, clearing and grubbing, tree and shrub removal and trimming, earth/topsoil stripping and stockpiling, and tree protection.
1.1.3.2 Unit of Measure
Unit of Measure: JOB
1.1.4 Site Earthwork (Bid Item 0004)
1.1.4.1 Payment
Payment for excavation will be made at the applicable contract lump sum, JOB price for all "Site Earthwork" required to bring the site to the grades and elevations shown on the drawings. These prices and payments shall constitute full compensation for furnishing all plant, labor, equipment and material and performing all operations necessary for all work as specified and as shown on the drawings, including, but not limited to rough excavation to cut site to specified grade, hauling excavated material to spoil pile location, construction of a spoils pile, and erosion and sedimentation controls. Site earthwork is to occur after the site has been stripped and\or cleared and grubbed. It does not included additional excavation required for the placement of features or structures designated on the drawings. Earthwork associated the placement of features is considered incidental to that feature.
1.1.4.2 Unit of Measure
Unit of Measure: JOB
1.1.5 Storm Drainage Utilities (Bid Item 0008)
1.1.5.1 Payment
Payment for all work associated with the drainage system will be made at the contract job price for "Storm Drainage Utilities", which price and payment shall constitute full compensation for providing all plant, labor, material and equipment and for performing all operations necessary to complete the work as specified and as shown on the drawings, including relocation of existing storm drainage system, manhole construction, necessary earthwork, hauling excavated material to spoil pile location as shown on the drawings, placement of stone materials, culverts, and placement of the storm drainage network and supporting components.
SECTION 01 35 26 Page 1
SECTION 01 35 26.00 03
GOVERNMENTAL SAFETY REQUIREMENTS
11/15
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
ASSE/SAFE A10.34 (2001; R 2012) Protection of the Public on or Adjacent to Construction Sites
ASSE/SAFE A10.44 (2014) Control of Energy Sources
(Lockout/Tagout) for Construction and Demolition Operations
ASSE/SAFE Z244.1 (2003; R 2014) Control of Hazardous Energy
Lockout/Tagout and Alternative Methods
ASSE/SAFE Z359.0 (2012) Definitions and Nomenclature Used for Fall Protection and Fall Arrest
ASSE/SAFE Z359.1 (2007) Safety Requirements for Personal
Fall Arrest Systems, Subsystems and Components
ASSE/SAFE Z359.11 (2014) Safety Requirements for Full Body
Harnesses
ASSE/SAFE Z359.12 (2009) Connecting Components for Personal
Fall Arrest Systems
ASSE/SAFE Z359.13 (2013) Personal Energy Absorbers and Energy
Absorbing Lanyards
ASSE/SAFE Z359.14 (2014) Safety Requirements for Self-
Retracting Devices for Personal Fall Arrest and Rescue Systems
ASSE/SAFE Z359.15 (2014) Safety Requirements for Single
Anchor Lifelines and Fall Arresters for Personal Fall Arrest Systems
ASSE/SAFE Z359.2 (2007) Minimum Requirements for a
Comprehensive Managed Fall Protection Program
SECTION 01 35 26 Page 2
ASSE/SAFE Z359.3 (2007) Safety Requirements for Positioning and Travel Restraint Systems
ASSE/SAFE Z359.4 (2013) Safety Requirements for Assisted-
Rescue and Self-Rescue Systems, Subsystems and Components
ASSE/SAFE Z359.6 (2009) Specifications and Design
Requirements for Active Fall Protection Systems
ASSE/SAFE Z359.7 (2011) Qualification and Verification
Testing of Fall Protection Products
ASSE/SAFE Z490.1 (2009) Criteria for Accepted Practices in
Safety, Health, and Environmental Training
ASME INTERNATIONAL (ASME)
ASME B30.20 (2013; INT Oct 2010 - May 2012) Below-the-
Hook Lifting Devices
ASME B30.22 (2010) Articulating Boom Cranes
ASME B30.26 (2015; INT Jun 2010 - Jun 2014) Rigging
Hardware
ASME B30.3 (2012) Tower Cranes
ASME B30.5 (2014) Mobile and Locomotive Cranes
ASME B30.8 (2010) Floating Cranes and Floating
Derricks
ASME B30.9 (2014; INT Feb 2011 - Nov 2013) Slings
ASTM INTERNATIONAL (ASTM)
ASTM F855 (2015) Standard Specifications for
Temporary Protective Grounds to Be Used on De-energized Electric Power Lines and Equipment
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 1048 (2003) Guide for Protective Grounding of
Power Lines
SECTION 01 35 26 Page 3
AMD0002 - 09/30/18
IEEE C2 (2012; Errata 2012; INT 1-4 2012; INT 5-7 2013; INT 8-10 2014; INT 11 2015) National Electrical Safety Code
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION (NASA)
NASA NPR 8621.1 (2006b; Change 7) NASA Procedural
Requirements for Mishap and Close Call Reporting, Investigating, and Recordkeeping
NASA NPR 8715.3 (2008c; Change 9) NASA General Safety
Program Requirements
NASA-STD 8719.12 (2011; Change 2) Safety Standard for
Explosives, Propellants, and Pyrotechnics
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA Z535.2 (2011) Environmental and Facility Safety
Signs
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2013) Standard for Portable Fire
Extinguishers
NFPA 241 (2013; Errata 2015) Standard for
Safeguarding Construction, Alteration, and Demolition Operations
NFPA 306 (2014) Standard for Control of Gas Hazards on Vessels
NFPA 51B (2014) Standard for Fire Prevention During
Welding, Cutting, and Other Hot Work
NFPA 70 (2014; AMD 1 2013; Errata 1 2013; AMD 2
2013; Errata 2 2013; AMD 3 2014; Errata 3-4 2014; AMD 4-6 2014) National Electrical Code
NFPA 70E (2015; ERTA 1 2015) Standard for Electrical
Safety in the Workplace
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements
Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
10 CFR 20 Standards for Protection Against Radiation
29 CFR 1910 Occupational Safety and Health Standards
SECTION 01 35 26 Page 4
29 CFR 1910.146 Permit-required Confined Spaces
29 CFR 1910.147 Control of Hazardous Energy (Lock Out/Tag
Out)
29 CFR 1910.333 Selection and Use of Work Practices
29 CFR 1915 Confined and Enclosed Spaces and Other
Dangerous Atmospheres in Shipyard Employment
29 CFR 1915.89 Control of Hazardous Energy (Lockout/Tags-
Plus)
29 CFR 1919 Gear Certification
29 CFR 1926 Safety and Health Regulations for
Construction
29 CFR 1926.1400 Cranes and Derricks in Construction
29 CFR 1926.16 Rules of Construction
29 CFR 1926.450 Scaffolds
29 CFR 1926.500 Fall Protection
49 CFR 173 Shippers - General Requirements for
Shipments and Packagings
CPL 2.100 (1995) Application of the Permit-Required
Confined Spaces (PRCS) Standards, 29 CFR 1910.146
1.2 DEFINITIONS
1.2.1 Competent Person (CP)
The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.
1.2.2 Competent Person, Confined Space
The Competent Person, Confined Space (CP), is a person meeting the competent person requirements as defined EM 385-1-1 Appendix Q, with thorough knowledge of OSHA’s Confined Space Standard, 29 CFR 1910.146, and designated in writing to be responsible for the immediate
SECTION 01 35 26 Page 5
AMD0002 - 09/30/18
supervision, implementation and monitoring of the confined space program, who through training, knowledge and experience in confined space entry is capable of identifying, evaluating and addressing existing and potential confined space hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.3 Competent Person, Cranes and Rigging
The CP, Cranes and Rigging, as defined in EM 385-1-1 Appendix Q, is a person meeting the competent person, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the Crane and Rigging Program, who through training, knowledge and experience in crane and rigging is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.4 Competent Person, Excavation/Trenching
A CP, Excavation/Trenching, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and 29 CFR 1926, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the excavation/trenching program, who through training, knowledge and experience in excavation/trenching is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.5 Competent Person, Fall Protection
The CP, Fall Protection, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and in accordance with ASSE/SAFE Z359.0, who has been designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment, is capable of identifying, evaluating and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.6 Competent Person, Scaffolding
The CP, Scaffolding is a person meeting the competent person requirements in EM 385-1-1 Appendix Q, and designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the scaffolding program. The CP for Scaffolding has enough training, knowledge and experience in scaffolding to correctly identify, evaluate and address existing and potential hazards and also has the authority to take prompt corrective measures with regard to these hazards. CP qualifications must be documented and include experience on the specific scaffolding systems/types being used, assessment of the base material that the scaffold will be erected upon, load calculations for materials and personnel, and erection and dismantling. The CP for scaffolding must have a documented, minimum of
SECTION 01 35 26 Page 6
AMD0002 - 09/30/18
8-hours of scaffold training to include training on the specific type of scaffold being used (e.g., mast-climbing, adjustable, tubular frame), in accordance with EM 385-1-1 Section 22.B.02.
1.2.7 Competent Person (CP) Trainer
A competent person trainer as defined in EM 385-1-1 Appendix Q, who is qualified in the material presented, and who possesses a working knowledge of applicable technical regulations, standards, equipment and systems related to the subject matter on which they are training Competent Persons. A competent person trainer must be familiar with the typical hazards and the equipment used in the industry they are instructing. The training provided by the competent person trainer must be appropriate to that specific industry. The competent person trainer must evaluate the knowledge and skills of the competent persons as part of the training process.
1.2.8 High Risk Activities
High Risk Activities are activities that involve work at heights, crane and rigging, excavations and trenching, scaffolding, electrical work, and confined space entry.
1.2.9 High Visibility Accident
A High Visibility Accident is any mishap which may generate publicity or high visibility.
1.2.10 Load Handling Equipment (LHE)
LHE is a term used to describe cranes, hoists and all other hoisting equipment (hoisting equipment means equipment, including crane, derricks, hoists and power operated equipment used with rigging to raise, lower or horizontally move a load).
1.2.11 Medical Treatment
Medical Treatment is treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.
1.2.12 Near Miss
A Near Miss is a mishap resulting in no personal injury and zero property damage, but given a shift in time or position, damage or injury may have occurred (e.g., a worker falls off a scaffold and is not injured; a crane swings around to move the load and narrowly misses a parked vehicle).
1.2.13 Operating Envelope
The Operating Envelope is the area surrounding any crane or load handling equipment. Inside this "envelope" is the crane, the operator, SECTION 01 35 26 Page 7
AMD0002 - 09/30/18
riggers and crane walkers, other personnel involved in the operation, rigging gear between the hook, the load, the crane's supporting structure (i.e., ground or rail), the load's rigging path, the lift and rigging procedure.
1.2.14 Qualified Person (QP)
The QP is a person designated in writing, who, by possession of a recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.
1.2.15 Qualified Person, Fall Protection (QP for FP)
A QP for FP is a person meeting the requirements of EM 385-1-1 Appendix Q, and ASSE/SAFE Z359.0, with a recognized degree or professional certificate and with extensive knowledge, training and experience in the fall protection and rescue field who is capable of designing, analyzing, and evaluating and specifying fall protection and rescue systems.
1.2.16 Recordable Injuries or Illnesses
Recordable injuries or illnesses are any work-related injury or illness that results in:
a. Death, regardless of the time between the injury and death, or the length of the illness;
b. Days away from work (any time lost after day of injury/illness onset);
c. Restricted work;
d. Transfer to another job;
e. Medical treatment beyond first aid;
f. Loss of consciousness; or
g. A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (a) through (f) above.
1.2.17 USACE Property and Equipment
Interpret "USACE" property and equipment specified in USACE EM 385-1-1 as Government property and equipment.
1.2.18 Load Handling Equipment (LHE) Accident or Load Handling Equipment Mishap
A LHE accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, SECTION 01 35 26 Page 8
AMD0002 - 09/30/18
including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment;
two-blocking; overload; or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents, even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, or roll over). Document any mishap that meets the criteria described in the Contractor Significant Incident Report (CSIR).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Accident Prevention Plan (APP); G, CN
Activity Hazard Analysis (AHA); G, CN
Crane Operators/Riggers; G, GSO
Standard Lift Plan; G CN
LHE Inspection Reports; G, CN
Confined Space Entry Plan
SD-06 Test Reports
Notifications and Reports
Submit reports as their incidence occurs, in accordance with the requirements of the paragraph, "Notifications and Reports".
Accident Reports; G, GSO
Monthly Exposure Reports
SD-07 Certificates
Hot Work Permit
Certificate Of Compliance
1.4 MONTHLY EXPOSURE REPORTS
SECTION 01 35 26 Page 9
AMD0002 - 09/30/18
Provide a Monthly Exposure Report and attach to the monthly billing request. This report is a compilation of employee-hours worked each month for all site workers, both Prime and subcontractor. Failure to submit the report may result in retention of up to 10 percent of the voucher.
1.5 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this contract, comply with the most recent edition of USACE EM 385-1-1, and the following federal, state, and local laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
1.6 SITE QUALIFICATIONS, DUTIES, AND MEETINGS
1.6.1 Personnel Qualifications
1.6.1.1 Site Safety and Health Officer (SSHO)
Provide an SSHO that meets the requirements of EM 385-1-1 Section 1.
The SSHO must ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Alternate SSHO must be at the work site at all times to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO and Alternate SSHO must have the required training, experience, and qualifications in accordance with EM 385-1-1 Section 01.A.17, and all associated sub-paragraphs.
If the SSHO is off-site for a period longer than 24 hours, an equally-qualified alternate SSHO must be provided and must fulfill the same roles and responsibilities as the primary SSHO. When the SSHO is temporarily (up to 24 hours) off-site, a Designated Representative (DR), as identified in the AHA may be used in lieu of an Alternate SSHO, and must be on the project site at all times when work is being performed.
Note that the DR is a collateral duty safety position, with safety duties in addition to their full time occupation.
1.6.1.2 Contractor…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.