THIS FILE CONTAINS AMENDMENT NO. 0002 INCLUDING THE ATTACHMENT SHOWING THE PARKING AREA (TO BE USED FOR PREBID MEETING).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMEND0006_15B0005.pdf | ||
| AMENDMENT_0003_W912P615B0005_FB_PWR_BACKUP_FAC_1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81G6651320899
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
REFERENCE: INVITATION FOR BIDS NUMBER W912P6-15- B-0005, “FB1 BACKUP POWER AND CONTROL GEAR”
The US Army Corps of Engineers is issuing the amendment to this solicitation for the follow ing reasons:
A. INVITATION FOR BIDS: The BID DUE DATE for the referenced Solicitation (Invitation for Bid, No. W912P6-15-B-0005) is NOT EXTENDED by this Amendment; therefore, proposals are due by 2:00 p.m. CDT on 10 AUG 2015. Detailed information regarding the submission of proposals is located at Section 00100 of the Solicitation document.
THIS AMENDMENT CONTINUES ON THE NEXT PAGE
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 31-Jul-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P6-15-B-0005
X 9B. DATED (SEE ITEM 11)
09-Jul-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
31-Jul-2015
CODE
U. S. ARMY ENGINEER DISTRICT, CHICAGO
231 SOUTH LASALLE STREET SUITE 1500
CHICAGO IL 60604-1437
W912P6 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P6-15-B-0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
FB1 BP&CG
B. The USACE erred in the following responses provided for in Amendment 0001.
1) Paragraph D: There will be no climbing of ladders or roof access as part of this site visit. Therefore, the "and appropriate gloves for climbing ladder" should be deleted from the end of (3) in paragraph D. Also (4) should be deleted from paragraph D.
2) Paragraph F: The USACE inadvertently omitted the quantity for CLIN 0013 response to Question 2 in paragraph F is hereby amended to read as follows: A revised Bid Schedule will be provided with a quantity listed in a subsequent amendment..
3) In response to Question 6 in paragraph F, the entire response is hereby amended to read as follows:
Response 6: The adjacent Barrier 1 project is beginning the foundation slab. Earthwork within the building footprint is complete. Clearing and earthwork north of Building 1 is scheduled to be accomplished in the next 2 months. The project is currently under construction; therefore as-builts aren't available. The solicitation plans and specifications can be viewed as a reference and are located at www.fbo.gov under solicitation number W912P6- 14-B-0011.
B. Available parking for the Pre-bid meeting is designated in Attachment 1 enclosed herein.
C. USACE RESPONSES TO CONTRACTOR’S QUESTIONS:
Question 1: A request to extend the bid date and time was received.
Response 1: The bid receipt date and time has not been extended.
Question 2: Sheet A-100 (47 of 52) indicates a “Wire Mesh Partition with doors where shown” is too be installed in the north section of the new proposed building. Doors “101E” and “101D” are indicated to be installed within the new partition.
Sheet A-600 provides a door schedule indicting both 101E and 101D are to have a height of 7’-0”. Nowhere within the plan documents or specifications does it indicate the proposed height of the Wire Mesh Partition. Please provide the required partition height for the entire length of the partition.
Response 2: A1: The height and signage requirements for the wire mesh partition is 8'-0" as called out on sheet E-102.
Question 3: Sheet C-102 (25 of 42) indicates to install new Type A fence along the east perimeter of the project limits.
Sheet C-500 indicates pre-cast concrete barrier per IDOT Std 704001-04 at 12’-0” length is too be utilized. Most current IDOT standard is 704001-07 at 12’-6” in length. Please provide confirmation that the most current IDOT Standard is too be utilized for installation of the Type A fence.
Response 3: As shown on sheet C-050, the existing Type A fence should be reused onsite. If additional barriers are required, the most current IDOT standard shall be utilized.
Response 4: Can you please provide any information in regards to the name of the contractor who is currently completing the control work at this location?
Question 4: Clearing, grubbing, and grading of the location is included in a currently ongoing Corps contract, W912P6-14-C-0022, with E.P. Doyle & Son, LLC. The work is not completed and as-builts are currently unavailable. The solicitation plans and specifications for this contract can viewed as reference and are located at www.fbo.gov under solicitation number W912P6-14-B-
0011.
D: Responses to additional contractor’s questions submitted will be addressed in subsequent amendments.
(End of Summary of Changes)