This is Amendment 0002 to Solicitation W912P527QA001, issued by the U.S. Army Corps of Engineers (USACE), Nashville District, on November 5, 2026. The amendment extends the offer due date from November 5, 2026 at 3:00 PM Central Standard Time to November 12, 2026 at 3:00 PM Central Standard Time. The solicitation requires the supply and delivery of a DC and preferred AC System for the J. Percy Priest Dam and Powerhouse. Offerors must acknowledge receipt of this amendment prior to the extended deadline through one of three methods: completing and returning amendment items 8 and 15, acknowledging receipt on each copy of the offer submitted, or sending a separate letter or electronic communication referencing the solicitation and amendment numbers. Failure to acknowledge receipt by the deadline may result in offer rejection.

The amendment updates multiple attachments and adds two new attachments to the solicitation. Attachment 0001 (Price Schedule) is replaced with an amended version that now includes CLINs 0014 and 0015. Attachment 0002 (TSPECS JPP DC & AC Preferred AC System) has five sections replaced in their entirety by new Attachment 0005 (Amended TSPECS Sections). Attachment 0003 (System Replacement Specification Drawings) is replaced with revised drawings containing the correct solicitation number, while Attachment 0004 (System Referenced Drawings) remains unchanged. New Attachment 0006 (JPP Supply Layout) and Attachment 0007 (JPP Powerhouse Photos) are added. The amendment also includes responses to twelve inquiry items addressing manual transfer switch specifications, warning light and differential pressure switch quantities, enclosure material requirements, trade agreement certification requirements, delivery deadlines (June 10, 2027), invoicing and payment procedures, government witness requirements for factory tests with 15-30 days advance notice, site visit availability, drawing governance, CLIN pricing updates, fire extinguisher and signage item allocation, and prohibitions against technical deviations or equipment substitutions in offers. All other terms and conditions of the original solicitation remain unchanged.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Solicitation/Contract Form

The following changes have been made:

INFORMATION FROM TO

Response Due Date

05 Nov 2026 12 Nov 2026

Instructions, Conditions, & Notices to Offerors or Quoters

The following clauses were modified:

52.252-3 Alterations in Solicitation. Apr 1984 hereby reads as follows:

Alterations in Solicitation (Apr 1984)

Portions of this solicitation are altered as follows:

Amendment 0002: Supply and deliver the DC and preferred AC System to the J. Percy Priest Dam and Powerhouse.

PURPOSE: The purpose of this amendment is to:

1) Extend the offer due date to 12 November 2026 by 3:00 PM Central Standard Time.

End of Amendment 0002.

Amendment 0001: Supply and deliver the DC and preferred AC System to the J. Percy Priest Dam and Powerhouse.

PURPOSE: The purpose of this amendment is to:

1) Respond to solicitation inquiries. These inquiries are identified and addressed within this provision.

W912P527QA0010002

2) Add and revise attachments.

3) The offer due date is extended to 5 November 2026 by 3:00 PM Central Standard Time.

4) All other terms and conditions of the solicitation remain unchanged.

Attachments are updated as follows:

Attachment 0001, Price Schedule, is replaced with an amended price schedule.

Attachment 0002, TSPECS JPP DC & AC Preferred AC System RTA 13 Oct 2026, is not replaced.

The following sections of Attachment 0002 are replaced in entirety by Attachment 0005: Sections:

01 11 10.00 26, 01 22 00, 26 05 00.00 26, 26 28 00.00 26, and 26 32 36.00 26.

Attachment 0003, System Replacement Specification Drawings, is replaced with revised drawings.

Attachment 0004, System Referenced Drawings, has no changes.

Attachment 0005, Amended TSPECS Sections, is added for the purpose of replacing sections of Attachment 0002. The sections replaced are 01 11 10.00 26, 01 22 00, 26 05 00.00 26, 26 28

00.00 26, and 26 32 36.00 26.

Attachment 0006, JPP Supply Layout, is added.

Attachment 0007, JPP Powerhouse Photos, is added.

Inquiries:

Inquiry 1: Please clarify the required manual transfer switch. Section 01 22 00 specifies a UL 98-listed, 600A manual transfer switch, while Section 26 05 00.00 26, paragraph 2.19, specifies a UL 1008-listed, 800A minimum manual transfer switch. Which specification governs?

Response for Inquiry 1: Section 01 22 00, CLIN 0005 has been updated via Attachment 0005 to specify one UL 1008-listed, 800A Manual Transfer Switch.

Inquiry 2: Please confirm the required quantity of warning lights and whether the differential pressure switch is included. Section 01 11 10.00 26 specifies one differential pressure switch and three warning lights, while the CLIN 0009 payment description lists only two warning lights and omits the differential pressure switch from its item description.

Response for Inquiry 2: The differential pressure switch and all three (3) warning lights are included in the scope of work, reference Attachment 0005. These items shall be priced under CLIN 0009.

Inquiry 3: Please clarify the enclosure material requirements. Paragraph 2.3.1 specifies stainless-steel NEMA Type 12 enclosures, while paragraph 2.5 specifies a NEMA 3R enclosure for the automatic transfer switch. Is stainless steel required for all applicable enclosures, or is painted carbon steel acceptable for any of them?

Response for Inquiry 3: Stainless steel is required for the Automatic Transfer Switch (ATS) enclosure. Attachment 0005 updates paragraph 2.5 to require that the ATS be mounted inside a stainless steel enclosure rated NEMA 3R and UL 1008 listed. Indoor enclosures must conform to the stainless-steel NEMA Type 12 rating specified in paragraph 2.3.1. Standard carbon steel is not acceptable for these designated enclosures.

Inquiry 4: The solicitation includes Buy American/Balance of Payments and related domestic-source clauses. Please confirm whether any separate Trade Agreements Act (TAA) requirements or certifications apply to the offered equipment in addition to the listed clauses.

Response for Inquiry 4: No separate Trade Agreements Act (TAA) apply. The procurement is strictly subject to RFO DFARS 252.225-7001, Buy American and Balance of Payments Program, and RFO DFARS, 252-225-7000, Buy American Balance of Payments Program Certificate.

Offerors are required to provide certifications as applicable in accordance with RFO DFARS 252.225-7000.

Inquiry 5: Please confirm the required delivery deadline or delivery period. Section 01 00 00 specifies the delivery location, two weeks' advance notice, and delivery hours, but does not identify a specific required delivery date.

Response for Inquiry 5: Reference Solicitation Section F, Deliveries or Performance. The required delivery for all requirements is on or before 10 June 2027. A two-week notice is required prior to any deliveries.

Inquiry 6: Please confirm the invoicing requirements and payment timeline applicable to this contract. Section 01 22 00 establishes lump-sum payment by CLIN but does not specify the project-specific invoicing and payment timeline.

Response for Inquiry 6: Invoices will be processed in accordance RFO 52.212-4. Payment timelines will be in accordance with the Prompt Payment Act (31 U.S.C. 3903). An invoice must include the information required by 5 CFR part 1315.9(b). Invoices may be submitted by CLIN after delivery of all items required by the applicable CLIN.

Inquiry 7: Please confirm whether the Government intends to witness the specified factory tests in person or waive attendance, and clarify whether travel costs for Government representatives are the Government's responsibility or must be included in the contractor's price.

Response for Inquiry 7: The Government intends to witness factory tests in person. In accordance with Attachment 0005 Section 26 32 36.00 26, paragraph 3.1.1, and Section 26 28 00.00 26, paragraph 3.1, tests must be witnessed by the Contracting Officer's Representative (COR) unless waived in writing. The contractor must notify the COR 15 days in advance for inverters and 30 days in advance for panelboard tests. Travel costs for Government representatives are at the Government's expense and should not be included in the contractor's pricing.

Inquiry 8: Can a pre-award site visit be arranged to verify equipment dimensions, conduit entry points, and access pathways before pricing and manufacturing?

Response for Inquiry 8: No, there will not be a pre-award site visit. Please reference SECTION 01 11 10.00 26 1.1.1, General, and Attachment 0007 for spatial requirements information.

Inquiry 9: Please confirm which drawing set governs the solicitation. Attachment 0003 contains drawings marked "Final" with an older solicitation number in the title blocks, while Attachment 0004 contains reference drawings marked "90% Review." Are the Attachment 0003 drawings the current final drawings, and are the Attachment 0004 drawings for reference only?

Response for Inquiry 9: Attachment 0003 has been updated to list the correct solicitation number.

Attachment 0004 is provided for Reference.

Inquiry 10: Section 01 22 00 includes CLIN 0014 for final record drawings, but Attachment 0001 lists only CLINs 0001-0013. Should CLIN 0014 be priced separately, and will a revised price schedule be issued?

Response for Inquiry 10: Attachment 0001, Price Schedule, is updated and now includes CLINS 0014 and 0015.

Inquiry 11: Sections 10 44 16 and 10 14 00.20 specify two 15-pound CO2 fire extinguishers and interior signage, but Attachment 0001 does not identify separate CLINs for these items. Which CLIN should cover these items, or will the price schedule be amended?

Response for Inquiry 11: Attachment 0001, Price Schedule, is updated and now includes CLIN 0015 (Supply interior signage). Fire extinguishers specified in Section 10 44 16 must be priced as incidental to CLIN 0009 (Safety support equipment). Signage specified in Section 10 14 00.20 will be paid separately under CLIN 0015.

Inquiry 12: Please confirm whether proposed technical deviations or equipment substitutions may be included with the offer for evaluation and, if so, what documentation is required. Section 01 33 00 states that variations require Contracting Officer approval.

Response for Inquiry 12: Technical deviations or equipment substitutions shall not be included with the offer.

(End of Provision)

IDCode: J
Page: 1
Pages: 5
AmendNo: 0002
EffDate: 05 NOV 2026
ReqNo:
ProjNo:
IssCode: W912P5
AdmCode:
IssuedBy: W072 ENDIST NASHVILLE

KO CONTRACTING DIVISION, 801 BROADWAY RM A604

NASHVILLE, TN 37203-1070

UNITED STATES

RICHARD HESTER, EMAIL: RICHARD.B.HESTER@USACE.ARMY.MIL TELEPHONE: 615-736-7367

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W912P527QA001
SolDate: 19 OCT 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: This amendment extends the offer due date to 12 November 2026 at 3:00 PM CST. RFO Provision 52.252-3, Alterations in Solicitation, is updated to reflect the extension. All other terms and conditions remain the same.