Kentucky Lock Addition - Operational Contract - Anticipated Dates Update
Solicitation number
W912P523Z0024
Issued by

About this file

This sources sought notice provides information on an upcoming federal contract opportunity for the Kentucky Lock Operational Contract with the U.S. Army Corps of Engineers Nashville District. The scope of work involves approach walls, maintenance and operations buildings, middle walls and bridges, electrical and mechanical systems, and site development associated with a new 1,200 foot lock adjacent to the existing Kentucky Lock. The contract is estimated between $150-300 million using NAICS code 237990. The government is considering the use of Integrated Design and Construction and seeks feedback on this approach through responses to 22 questions related to past performance, design approach, schedule, cost, and project labor agreements among other topics. Responses are due by October 6, 2023 to Dellaria Martin and Cierra Vega of the Corps of Engineers Nashville District.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOURCES SOUGHT NOTICE

This announcement is for information and planning purposes only and is not to be construed as a commitment by the Government, implied or otherwise, to issue a solicitation or make a contract award. NO AWARD will be made from this Sources Sought Notice. This is NOT a request for proposal, quote, or invitation for bid. The sole purpose of this notice is to identify potential System for Award Management (SAM) Database registered businesses that are interested and capable of performing this work in order to determine an appropriate acquisition plan. USACE is not responsible for any costs incurred by interested parties in responding to this Sources Sought.

POINT OF CONTACT: Cierra Vega, Contract Specialist - cierra.r.vega@usace.army.mil Dellaria Martin, Contracting Officer – Dellaria.L.Martin@usace.army.mil

PROJECT INFORMATION

The U.S. Army Corps of Engineers, Nashville District, intends to design and construct the final standalone Lock Operational Contract as part of the overall Kentucky Lock Addition that will provide a new 1,200-foot-long operational lock adjacent to the existing 600-foot-long Kentucky Lock in Grand Rivers, KY, at Tennessee River Mile 22. The new 1,200-foot-long lock will improve navigational efficiency on the Tennessee River system, allowing for faster transit times and eliminating costly delays associated with the existing smaller lock. For the Lock Operational Contract, the Government is considering the use of a form of Early Contractor Involvement (ECI) called Integrated Design and Construction (IDaC).

NAICS CODE: 237990 Other Heavy and Civil Engineering Construction

SIZE STANDARD: $45M

CONTRACT ESTIMATED MAGNITUDE: $150M – $300M

mailto:cierra.r.vega@usace.army.mil mailto:Dellaria.L.Martin@usace.army.mil

OPERATIONAL CONTRACT SCOPE OF WORK

1) Approach Walls: Consists of the upstream floating approach walls (Qty. 1 @ approx. 1,200 ft.

long and Qty. 1 @ approx. 300 ft. long) and downstream fixed approach wall, approx. 1,200 ft.

long; upstream and downstream cofferdam demolition; upstream mooring cell demolition (Qty.

4); and approach area dredging.

2) Maintenance and Operations Buildings: Two buildings, one for operation of the locks (approx. 130 ft x 60 ft) and one for maintenance of the lock (approx. 60 ft x 30 ft). Buildings will be located approx. midway of new lock chamber on the land side.

3) Middle Wall and Pedestrian/Utility Bridges: Two bridges that will span from Kentucky Dam across the existing lock chamber and new lock chamber. Utility bridge will serve to carry all power and service utilities from TVA’s Powerhouse Island to the locks and as a public pedestrian/bicycle bridge. Access bridge will provide lock operations personnel and equipment access from Powerhouse Island to the middle lock wall.

4) Electrical/Mechanical: Consists of electrical/mechanical/hydraulic/structural steel components to operate the gates, valves, and systems associated with the new lock chamber.

5) East Bank Site Development: Grading, roads, drainage, utilities, and fencing associated with the new lock operations and maintenance buildings.

*Reference attachment “Sources Sought Attachment – Kentucky Lock Operational Scope” for more details

INTEGRATED DESIGN AND CONSTRUCTION (IDaC) OVERVIEW

Preconstruction Services can include, but not limited to:

-Consultation in construction methodology, current market conditions and identification of coordination issues.

-Construction cost estimates

-to validate designer prepared estimates at each review phase -for alternative designs and materials -for changed market conditions

-Cost control, when there is a significant difference or the construction estimate exceeds the target, the estimates will be examined to determine the cause for the differences and steps made to correct the Government or contractor estimates.

-Preconstruction services are awarded as firm fixed price contract

NOTE: The contractor shall not be responsible for any design services.

The responsibility of the design will remain wholly with the Designer of Record.

Fast tracking will not be utilized.

IDAC PROCESS SUMMARY

Prior to completion of the design, the Government issues open competition solicitation for bids that will include preconstruction services as the base of the contract and construction services as the option(s). Bids will consist of a firm fixed price for the preconstruction services, initial target price for construction, target profit, and a ceiling price. At conclusion of preconstruction services, and when the design is completed, the preconstruction services contractor provides a final firm fixed price bid for the construction option(s) to the Government. If final firm fixed price with profit price does not exceed the ceiling price and is accepted by the Government, the contractor executes the work under a standard firm fixed price contract arrangement with the Government. The amount of available profit to the contractor is based upon ‘cost-share’ percentages above/below the initial target price with profit mix/max limits, pre-determined by Government and provided in bid solicitation. If final firm fixed price with profit exceeds the ceiling price, the Government will not award the construction option to the preconstruction services contractor but will re-solicit the construction services as an open competition, firm fixed price contract. The preconstruction services contractor may or may not be eligible to compete if the construction option is re-competed, depending on factors determined by the Government.

OPERATIONAL CONTRACT DESIGN OVERVIEW

LOCK OPERATIONAL CONTRACT AND DOWNSTREAM LOCK MONOLITHS

GENERAL WORK AREA MAP (NOTE: ESTIMATED COMPLETION OF

DOWNSTREAM MONOLITHS IS MID-2027)

CAPABILITY STATEMENT SUBMITTAL

For the Lock Operational Contract, the Government is considering the use of a form of Early Contractor Involvement (ECI) called Integrated Design and Construction (IDaC). The Government is looking for both positive and negative feedback on the questions provided.

All interested, responsive and responsible System of Award Management (SAM) Database registered businesses are encouraged to participate in this Sources Sought by emailing the required information below to the point of contact. If your company is not SAM-registered, please do so at www.sam.gov.

Responses are to be sent via email to Dellaria Martin and Cierra Vega no later than 10:00 a.m. CST, 06 October 2023. A request to extend may be submitted to the email addresses listed above. The subject line of the email shall reference the Market Research number in the announcement. Electronic submittals will be retained for future reference; however, they are to be considered source sensitive and not subject to public disclosure.

Responses shall include the following information and shall not exceed a total of ten (10) pages:

1. Please provide business information in the following format:

a. Business Name

b. Points of Contact (Names/Phone Numbers/Email Addresses)

c. Address

d. Business Size and Category (Large/Small/8(A)/etc.) in relation to the NAICS code

e. CAGE and/or UEI Code

f. Indication of the intent to be a prime contractor or subcontractor

2. Bonding capability (construction bonding level per single contract/task order and aggregate construction bonding level, both expressed in dollars along with current available bonding capacity.

3. Firm’s interest in providing a proposal on the pending solicitation once issued.

4. Past Performance Information that documents the respondents experience performing projects similar to required work comparable for this project (e.g. management of construction in a marine environment). The referenced projects should be of similar scope and magnitude and should have been completed within the last ten years. Information should be provided in the form of Contract Performance Assessment Reporting System (CPARS), Past Performance Questionnaires (PPQs) or by providing the following information: Project title, location, general description of the construction to demonstrate similarity to the project listed above, the Offeror's role (i.e., prime contractor, subcontractor, etc.), dollar value of contract, duration, name of the company, agency or government entity for which the work was performed with contact information (reference name, phone number and e-mail address), identify/discuss the acquisition method (e.g sealed bid, best value), contract type (e.g. Firm Fixed Price, Fixed Price Incentive Successive Targets), and delivery method (e.g. Guaranteed Maximum Price, Design-Bid-Build, Design-Build, Early Contractor Involvement, http://www.sam.gov/

Construction Manager as Constructor, Integrated Design and Construction, etc.). In the discussion of acquisition method, identify the advantages/disadvantages (from the contractor’s and the owner’s perspective) of the contract type/acquisition approach used for the representative project. Responses should address the firm’s capability to execute construction of large inland navigation infrastructure within an active navigable waterway.

5. Based upon the scope of this project, identify if interested firms would form a joint venture to execute this work. Provide joint venture information, if applicable, including DUNS number and CAGE code.

6. Address the firm’s plan to include small business participation to the maximum extent practicable.

7. The Government is considering alternative procurement methods, specifically the use of Early Contractor Involvement (ECI) via Integrated Design and Construction (IDaC). Provide your opinions (advantages/disadvantages) on utilizing this type of procurement method.

8. What is the preference for the contractor, IDaC or traditional Design-Bid-Build (DBB)?

Note in either option the Government intends to incorporate Best Value Trade Off (BVTO) technical proposal evaluation/selection criteria.

9. If ECI-IDaC is used what is required, as far as level of detail, to be included in the solicitation package to ensure biddability?

10. Using ECI/IDaC, what level design submission (0%-100% Plans & Specs.) best supports a competitive bid which will confidently support a maximum ceiling price and a target price?

11. What would be the most advanced design level % before ECI or IDaC is no longer favorable?

12. What Pre-Construction Services should the Government consider to be necessary when developing a scope of services for ECI? Is there a rule of thumb or % that the Government should use when budgeting?

13. Given the scope of work of the Lock Operational Contract provided by the Government, what major concerns do you identify?

14. Given the provided design summary, if ECI or IDaC is used provide your opinions on how best to structure the design packages?

15. The Government is planning on a 2-year incremental funding stream (60%, 40%) with a tentative construction award September 2025, and a target lock operational date of FY 2029.

What is a reasonable rough order of magnitude construction duration given this funding stream?

16. Does the use of ECI/IDaC impact your answer in question #15 regarding the construction duration?

17. What do you see as the most efficient construction sequence to achieve the earliest lock operational date?

18. As applicable, provide your experience, if any, in performing preconstruction services on construction projects and if so, describe the type of services provided.

19. If applicable and possible, please provide some details on how the preconstruction services operated in practice. As an example, were there recurring established meetings? What design milestones were reviewed? How did the reviews operate? Was staff co-located with owner/government representatives?

20. Please describe what type of staff would be available to participate in the preconstruction services. What type of availability would they have to be integrated with the design team?

21. If applicable and possible, please provide what specific risks was the owner attempting to manage with the ECI-IDaC strategy that your company was involved with.

As this project is anticipated to exceed $35M, in accordance with the executive order on Project Labor Agreements please provide the following information:

22. The anticipated impacts to schedule and cost as a result of a Project Labor Agreement being mandatory.

23. If a Project Labor Agreement is mandated on this project, would your company submit an offer when the solicitation is issued?

24. Are there other ways, in your opinion, that the intent of a PLA could be met without explicitly requiring it?