This document contains an amendment to a solicitation and related federal contract opportunity for painting armor at Fort Loudon Lock. The amendment extends the bid submission deadline from August 25th to August 30th. It also revises the bid schedule and work summary to correct inconsistencies.

The opportunity is a solicitation issued by the U.S. Army Corps of Engineers Nashville District. Services required include removing rust, paint, and debris from lock wall armor surfaces, then painting approximately 2,425 linear feet of corner armor and 53 check posts. An optional line item is included to paint around 100 linear feet of vertical mooring bit recesses. The period of performance is 217 calendar days from notice to proceed. A pre-bid site visit was held on August 4th. Bids are due electronically by August 30th in PDF format through the Army's Electronic File Sharing Service.

View the file

Other files

File Type Posted
FLL - Armor Painting - RTA - Specs.pdf PDF
FLL - Armor Painting - RTA - BID.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTING BRANCH (KHP)

KATHRYN.H.PASCUAL@USACE.ARMY.MIL

110 9TH AVENUE SOUTH ROOM A405

NASHVILLE TN 37203

W38XDD20392868

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Extend the bid submission deadline from 25 Aug 2022 to 30 Aug 2022.

2. Revise the bid schedule totals and summary of w ork to correct inconsistencies.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-Aug-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P522B0012

X 9B. DATED (SEE ITEM 11)

21-Jul-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-Aug-2022

CODE

US ARMY CORPS OF ENGINEERS-CELRN-RC-N

DIRECTORATE OF CONTRACTING

110 9TH AVENUE SOUTH, RM A680

NASHVILLE TN 37203

W912P5 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W912P5

FACILITY CODECODE

EMAIL:TEL:

W912P522B0012

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 25-Aug-2022 12:00 PM to 30-Aug-

2022 12:00 PM.

CLIN 1001 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

1001 1 Job OPTION Vertical Armor – Mooring Bit Recess

FFP

Vertical Armor – Mooring Bit Recess Armor * Approximate total required to paint mooring bit recess.

FOB: Destination

PSC CD: Z1PZ

NET AMT

SECTION 00 20 00 - INSTRUCTIONS FOR PROCUREMENT

The following have been modified:

BID SCHEDULE

Fort Loudin Lock Armor Painting

Bid Schedule

Item No. Description Est. Qty. Unit Est. Amount

BASE

0001 Mobilization & Demobilization 1 Job

0002 Horizontal Armor -Upstream Approach Wall

Corner Armor 800 LF

0003 Horizontal Armor - Chamber Wall Corner

Armor 850 LF

0004 Horizontal Armor - Downstream Approach Wall

W912P522B0012

Corner Armor 775 LF

0005 Check Post on Top of

Lock Wall 53 EA

TOTAL BASE ESTIMATED AMOUNT:

OPTION 1

Vertical Armor – Mooring

Bit Recess 100 LF

TOTAL ESTIMATED AMOUNT:

STATEMENT OF WORK

Fort Loudoun Lock Wall Armor Painting

Summary of Work

Contractor shall remove all loose rust, paint, dirt, dust, and other foreign material that would prevent proper coating.

Contractor shall be responsible for providing adequate protections and devises to prevent impacts to the environment and to protect the structure, which is on the historic register. Contractor shall be responsible for painting Upstream Approach Wall Corner Armor (~800 LF), Chamber Corner Armor (~850 LF), Downstream Approach Wall Corner Armor (~775 LF), and Check Posts (53 total). Optionally the Vertical Armor of the Mooring Bit Recesses (Option 1), shall be painted to the summer pool elevation (approx. 100 LF). All work shall be conducted in strict accordance to the project’s specifications and plans.

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following Acceptance/Inspection Schedule was added for CLIN 1001:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

Destination Government Destination Government

(End of Summary of Changes)