W912P518T0044 - Technical Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912P518T00440001.pdf | ||
| W912P518T0044_TPlans.pdf | ||
| W912P518T0044.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Nashville District
FT. LOUDOUN LOCK
TOW HAULAGE WINCH
Tennessee River Basin
Ft. Loudoun Lock
Lenoir City, Tennessee
Technical Specifications August 2018
Final
THIS PAGE INTENTIONALLY LEFT BLANK
FOR DUPLEX PRINTING
Tow Haulage Winch Ft. Loudoun Lock Lenoir City, Tennessee
PROJECT TABLE OF CONTENTS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 11 50 TOW HAULAGE WINCH UNIT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
SECTION 35 11 50
TOW HAULAGE WINCH UNIT
PART 1 GENERAL
1.1 SCOPE
1.2 SCHEDULING
1.3 SUBMITTALS
1.3.1 Summary
1.3.2 Submittal Delivery
1.3.3 Submittal List
1.3.4 Submittal Review
1.3.4.1 Approving Authority is COR
1.3.4.2 Review Notations
1.3.4.3 Disapproved or Rejected Submittals
1.3.4.4 Approved or Accepted Submittals
1.4 VARIATIONS
1.4.1 Considering Variations
1.4.2 Proposing Variations
1.4.3 Warranting that Variations are Compatible
1.4.4 Review Schedule Extension
1.5 PRODUCT SUBSTITUTIONS
1.5.1 Approved Substitutions
1.5.2 Disapproved or Rejected Substitutions
1.6 REFERENCES
1.7 ACCESS TO WORK
1.8 DELIVERY
1.8.1 General
1.8.2 Packaging
1.8.3 Point of Delivery
1.9 SITE SECURITY PROCEDURES
1.9.1 General
1.9.2 Background Investigation Requirements
1.9.3 Pre-Fabrication Meeting In Controlled Area
1.9.3.1 U.S. Citizens
1.9.3.2 Foreign Nationals (FNs)
1.10 WARRANTY
1.11 QUALIFICATIONS
1.12 APPLICABLE DRAWINGS
1.13 WITHHOLDING OF PAYMENT
1.14 STAMPS
1.15 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Specialty Metals
2.2 FABRICATION
2.2.1 Structural Fabrication
2.2.1.1 Dimensional Tolerances for Structural Work
2.2.1.2 Structural Steel Fabrication
2.2.2 Welding
SECTION 35 11 50 Page 1
2.2.2.1 Welding of Structural Steel
2.2.2.2 Welding of Steel Castings
2.2.2.3 Welding of Steel Studs
2.2.2.4 Qualification of Welders
2.2.3 Casting
2.2.4 Machine Work
2.2.4.1 Finished Surfaces
2.2.4.2 Unfinished Surfaces
2.2.4.3 Pin Holes
2.2.4.4 Bearings
2.2.5 Shop Assembly
2.3 BOLTS, NUTS AND ANCHOR BOLTS
2.3.1 Bolts and Studs
2.3.2 Anchor Bolts
2.4 SHAFTS, KEYS AND COUPLINGS
2.4.1 General
2.4.2 Keys
2.4.3 Flexible Couplings
2.4.4 Coupling Guards
2.5 WINCH UNIT
2.5.1 Design
2.5.1.1 General
2.5.1.2 Capacities and Speeds
2.5.2 Gear Unit
2.5.3 Rope Drum and Pressure Rollers
2.5.3.1 Rope Drum
2.5.3.2 Pressure Rollers
2.5.4 Limit Switch
2.5.4.1 Limit Switch Location and Drivetrain Design
2.5.5 Electric Motor
2.5.6 Encoder
2.5.7 Variable Frequency Drive (VFD)
2.6 WIRE ROPES
2.6.1 Pre-Stretching
2.6.2 Wire Strength and Ductility
2.6.3 Pre-forming
2.6.4 Stress Relief
2.6.5 Lubrication
2.7 CLEANING AND PAINTING
2.7.1 Cleaning
2.7.2 Painting and Coating
2.7.3 Parts or Surfaces Not Painted
PART 3 EXECUTION
3.1 PROTECTION OF FINISHED WORK
3.1.1 Machined Surfaces
3.1.2 Lubrication Before Assembly
3.1.3 Lubrication After Assembly
3.2 TESTS, INSPECTIONS, AND VERIFICATIONS
3.2.1 General
3.2.2 Function
3.2.3 Inspection
3.2.4 Procedures
3.2.5 Notice of Test Date
3.2.6 Factory Tests
3.2.7 Nondestructive Testing
3.2.8 Inspection of Structural Steel Welding
3.2.8.1 Visual Examination
SECTION 35 11 50 Page 2
3.2.8.2 Nondestructive Examination
3.2.8.3 Test Coupons
3.2.9 Retests
ATTACHMENTS:
Submittal Register
ENG Form 4025-R
-- End of Section Table of Contents --
SECTION 35 11 50 Page 3
SECTION 35 11 50
TOW HAULAGE WINCH UNIT
PART 1 GENERAL
1.1 SCOPE
The work covered by this section consists of furnishing and supplying all materials and equipment required to fabricate the tow haulage winch unit at Ft. Loudoun Lock Project as specified herein and on the contract drawings.
Grout pads, concrete pads, and anchor bolt installation are provided for information only. The tow haulage winch unit shall include inverter duty electric motor with encoder that is suitable for use with a closed loop vector control variable frequency drive (VFD), drum, gear unit, variable frequency drive (VFD), limit switch, integral winch unit base, wire ropes, anchor bolts, and other necessary accessories. All work shall be performed in strict accordance with this section of the specifications and the applicable drawings, and shall be subject to the terms and conditions of the contract. Contractor shall also deliver the equipment to Ft. Loudoun Lock Project. Installation shall be performed by the Government and/or under a separate and independent contract. The Contractor shall conduct a site visit to the project to verify field measurements prior to the production of shop drawings. The Contractor shall furnish one (1) identical spare of each of the following: electric motor, VFD, and limit switch.
1.2 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals. The Contractor shall supply and update a Project Schedule. The Contractor shall provide weekly project updates and shall include updated project schedules as needed. The project schedule shall not extend beyond the period of performance for the contract. See paragraph General under heading DELIVERY for contract period of performance.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer's Representative(COR) does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date
SECTION 35 11 50 Page 4 shown on the approved "Submittal Register."
1.3 SUBMITTALS
1.3.1 Summary
All submittals will go through the Contracting Officer's Representative(COR), as directed. The COR may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
The Contractor and the Designer of Record, if applicable, to check, approve, stamp, sign, and date all items prior to submittal submission indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals. Where applicsble, all submittals (and work performed) shall be subject to FAR 52.236-21 Alt 1, Specifications and Drawings for Construction.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.
Fabrication/work cannot proceed without approval of submittals requiring government approval. Allow 14 calendar days from the date of submission for government approval required submittals to be reviewed and returned.
Submittals will be evaluated based on only their compliance with requirements set forth in the contract documents. It is the Contractor's responsibility to ensure compliance before submission. The Government reserves the right to reject submittals not in compliance with contract documents. The Contractor will bear all of the cost from rejected submittals due to non-compliance.
Normally submittals for information only will not be returned. Approval by the COR is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This stipulation: does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the COR from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.3.2 Submittal Delivery
Use transmittal form ENG Form 4025-R for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. Properly complete this form by filling out all the heading blank spaces and identifying each item
SECTION 35 11 50 Page 5 submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item. Each submittal will have an updated submittal register attached.
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the COR. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the COR. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark all files to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
E-mail electronic submittal documents fewer than 10MB to an e-mail address as directed by the COR. E-mail only one (1) submittal per e-mail, unless otherwise directed by the COR. Provide electronic documents over 10MB on an optical disc, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:
https://safe.amrdec.army.mil/safe/.
1.3.3 Submittal List
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Unless otherwise noted, provide all submittals in PDF format. The following shall be submitted:
SD-01 Preconstruction Submittals
Project Schedule; G
Preliminary schedule shall be provided within 10 calendar days of contract award notice. Submit weekly project updates and updated project schedules as needed.
SD-02 Shop Drawings
Shop Drawings; G
One (1) set of shop drawings in PDF format and one (1) set in .dgn or .dwg format shall be submitted for approval prior to fabrication. Fabrication cannot commence until shop drawings have been approved. The contractor shall prepare assembly and shop drawings. It is the contractor's responsibility to design a tow haulage winch unit that fits inside the existing pit without any interference with the existing structural beams or existing concrete structural. Shop drawings that do not meet this requirement shall be disapproved. Design shall allow the assembly to be lifted in and out of pit as a complete unit. Drawings shall include catalog cut, templates, fabrication and assembly details, and type, grade, and class of materials, anchor bolt locations, pressure roller details as appropriate. Elements of fabricated
SECTION 35 11 50 Page 6 items inadvertently omitted on contract drawings shall be detailed by the fabricator and indicated on the shop drawings. Submittal shall include complete machine design computations performed by a professional engineer for all equipment specified herein and shown on the accompanying contract drawings. Drafting shall be executed by computer assistance in ".dgn" or ".dwg" format. Electronic drawings shall have "true" scale. Drawings shall be made in a manner to give clear, permanent reproductions. Drawings shall be identified by serial number and descriptive titles indicating their application to the contract and they shall be signed and stamped by a responsible representative of the Contractor. A responsible representative is defined as a professional engineer with non-expired license whom represents the Contractor.
Shop drawings shall also list the lubricant, frequency (monthly, quarterly, annually), and location of items that need lubrication.
Calculations as required in paragraph "WINCH UNIT" shall be provided with shop drawings.
SD-03 Product Data
Motor characteristics curves; G
Motor characteristics curves (test or calculated) indicating the speed, current, and kilowatt input, plotted against torque or percent of load as abscissas. Characteristic curves of duplicate equipment shall be acceptable. Submit with shop drawings.
Limit Switch; G
Limit switch specifications and characteristics. Limit switch location and drivetrain design proposal. Submit with shop drawings.
Variable Frequency Drive; G
Variable Frequency Drive (VFD) specifications, catalog cuts, and characteristics. Submit with shop drawings.
Encoder; G
Encoder specifications and catalog cuts. Submit with shop drawings.
Anchor Bolts; G
Anchor bolt specifications and catalog cuts. Submit with shop drawings.
Wire Ropes; G
Wire rope specifications and catalog cuts. Proof of mill and and manufacture shall be submitted.
Gear Unit; G
Submit product data of gear unit and motor adapter with shop drawings.
SECTION 35 11 50 Page 7
Dowels; G
Submit product data of dowels with shop drawings.
SD-06 Test Reports
Nondestructive Testing; G
Record of Nondestructive Testing shall be required.
Factory Test Procedures; G
SD-07 Certificates
Welder Certification; G
The welders shall be certified.
SD-08 Manufacturer's Instructions
SD-10 Operation and Maintenance Data
Operating and Maintenance Instructions; G
Prior to delivery of equipment, the Contractor shall furnish three (3) sets of operating and maintenance instruction manuals for the operating equipment furnished hereunder. Maintenance, adjusting, and detailed operating instructions are required for the gear unit, bearings, limit switch, encoder, VFD and inverter duty motor.
SD-11 Closeout Submittals
As-Built Drawings; G
Upon completion of the work under this contract, the Contractor shall furnish a complete set of As-Built drawings and a DVD containing the drawings and computations approved as final. For drawings on the submitted DVD, one (1) set will be in PDF format and one (1) set will be in .dgn or .dwg format. Submittal shall also include complete machine design computations performed by a professional engineer for all equipment specified herein and shown on the accompanying contract drawings. Drafting shall be executed by computer assistance in ".dgn" or ".dwg" format. Electronic drawings shall have "true" scale. Drawings shall be made in a manner to give clear, permanent reproductions. Drawings shall be identified by serial number and descriptive titles indicating their application to the contract and they shall be signed and stamped by a responsible representative of the Contractor. A responsible representative is defined as a professional engineer with non-expired license whom represents the Contractor.
1.3.4 Submittal Review
1.3.4.1 Approving Authority is COR
When approving authority is COR, the Government will:
a. Note date on which submittal was received.
SECTION 35 11 50 Page 8
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph Review Notations and with markings appropriate for action indicated.
1.3.4.2 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
1.3.4.3 Disapproved or Rejected Submittals
Make corrections required by the COR. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the Federal Acquisition Regulation (FAR) clause entitled CHANGES, is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work.
Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.3.4.4 Approved or Accepted Submittals
The COR's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that design, general method of construction, materials, detailing and other information appear to meet the Solicitation and Accepted Proposal.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the
SECTION 35 11 50 Page 9
Contractor Quality Control (CQC) requirements of this contract is responsible for design, dimensions, all design extensions, such as the design of adequate connections and details, etc., and the satisfactory construction of all work.
After submittals have been approved or accepted by the COR, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.4 VARIATIONS
Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 Alt 1, Specifications and Drawings for Construction, and will be considered where advantageous to the Government.
1.4.1 Considering Variations
Discussion with COR prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.4.2 Proposing Variations
When proposing a variation, deliver written request to the COR, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.
The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
1.4.3 Warranting that Variations are Compatible
When delivering a variation for approval, the Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.4.4 Review Schedule Extension
In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.
SECTION 35 11 50 Page 10
1.5 PRODUCT SUBSTITUTIONS
A product substitution is a minor variation that changes a specific product, but does not change the overall design. Therefore, all information, requirements, stipulations, disclaimers, and guidance in VARIATIONS section applies to PRODUCT SUBSTITUTIONS as well.
Contractor is allowed to substitute called-out name-brand products for products of equal or greater specifications. Any additional cost will be covered by the Contractor. Contractor shall not purchase or install any substitutions prior to government approval. All proposed substitutions require government approval regardless of whether or not the submittal originally required government approval. All proposed substitutions shall be marked as a Variation as described in VARIATIONS. The Government reserves the right to rescind inadvertent approval of submittals found to not be properly marked as a Variation at no additional cost to the Government regardless of purchase or installation status.
1.5.1 Approved Substitutions
Substitutions are judged based on compliance to contract documents. It is the Contractor's responsibility to ensure all compatibility and performance prior to submission. The Government reserves the right to rescind inadvertent approval of submittals found to not be properly marked as a Variation at no additional cost to the Government regardless of purchase or installation status.
1.5.2 Disapproved or Rejected Substitutions
The Government is not responsible for any cost associated with the rejection of any substitutions.
1.6 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;
Errata 6 2016; Errata 7-9 2017) Building Code Requirements for Structural Concrete (ACI 318-14) and Commentary (ACI 318R-14)
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016) Structural Welding Code - Steel
ASME INTERNATIONAL (ASME)
ASME B17.1 (1967; R 2017) Keys and Keyseats
ASME B4.1 (1967; R 2009) Preferred Limits and Fits for Cylindrical Parts
ASME B46.1 (2009) Surface Texture, Surface Roughness, Waviness and Lay
SECTION 35 11 50 Page 11
ASTM INTERNATIONAL (ASTM)
ASTM A1023/A1023M (2015) Standard Specification for Stranded Carbon Steel Wire Ropes for General Purposes
ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A325 (2014) Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength
ASTM A574 (2017) Standard Specification for Alloy Steel Socket-Head Cap Screws
ASTM A668/A668M (2017) Standard Specification for Steel Forgings, Carbon and Alloy, for General Industrial Use
ASTM A153/A153M (2016) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A193/A193M (2016) Standard Specification for Alloy-Steel and Stainless Steel Bolting Materials for High-Temperature Service and Other Special Purpose Applications
ASTM A36/A36M (2014) Standard Specification for Carbon Structural Steel
ASTM A572/A572M (2015) Standard Specification for High-Strength Low-Alloy Columbium-Vanadium Structural Steel
ASTM B177/B177M (2011; R 2017) Standard Guide for Engineering Chromium Electroplating
ASTM E165/E165M (2012) Standard Practice for Liquid Penetrant Examination for General Industry
ASTM E709 (2015) Standard Guide for Magnetic Particle Examination
ASTM F3125/F3125M (2015a) Standard Specification for High Strength Structural Bolts, Steel and Alloy Steel, Heat Treated, 120 ksi (830 MPa) and 150 ksi (1040 MPa) Minimum Tensile Strength, Inch and Metric Dimensions
SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC SP 2 (1982; E 2000; E 2004) Hand Tool Cleaning
SSPC SP 3 (1982; E 2004) Power Tool Cleaning
SECTION 35 11 50 Page 12
SSPC SP 7/NACE No.4 (2007) Brush-Off Blast Cleaning
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
FS RR-W-410 (Rev H) Wire Rope and Strand
1.7 ACCESS TO WORK
The Contracting Officer's Representative(COR) and other agents of the Government shall at all time have access to all places of manufacture where equipment or materials are being made or prepared for use under this contract, and shall have full access for unrestricted inspections of such equipment or materials.
1.8 DELIVERY
1.8.1 General
Shop drawings shall be submitted by 60 calendar days after award notice for approval. Winch unit shall be delivered by 240 calendar days after the approval of shop drawings. The period of performance of the contract shall reflect this, 300 calendar days from award notice.
As-Built drawings and operating and maintenance instructions shall be submitted within 7 calendar days after the delivery of winch unit.
1.8.2 Packaging
The Contractor shall prepare all materials and articles for shipment in such manner as to facilitate handling and to protect them from damage in transit, and shall be responsible for, and make good, any and all damage due to improper preparation or loading for shipment. All damage shall be repaired or replaced by the Contractor with no additional cost to the Government. Boxes and crates shall be marked and have a packing list enclosed showing the parts contained therein. The software for the variable frequency drive (VFD) is very sensitive. Therefore, care should be taken to prevent the VFD and VFD software from being damaged during shipment. All transportation, delivery and storage costs shall be included in the offer price.
1.8.3 Point of Delivery
Contractor shall contact the lockmaster, Matthew Emmons ((865) 986-2762;
Matthew.D.Emmons@usace.army.mil), one week prior to the delivery date to verify the address. Delivery will be made from Monday to Thursday, 0800 to 1600 local time. Delivery may not be scheduled for federally observed holidays.
Ft. Loudoun Lock
6699 US-321 S
Lenoir City, TN 37772
1.9 SITE SECURITY PROCEDURES
1.9.1 General
The entire Ft. Loudoun Lock Project area is not open to the public.
Depending upon the level of security threat, some Project areas may or may not be open to the Contractor and Contractor employees. Guidance and forms
SECTION 35 11 50 Page 13 for project site security requirements are available on the Nashville District Public Website:
http://www.lrn.usace.army.mil/BusinessWithUs/ContractSecurityRequirements.aspx
1.9.2 Background Investigation Requirements
Since this is a delivery and/or supply only, there are no investigation requirements. However, the Contractor(s) will be escorted at all times inside any restricted area.
1.9.3 Pre-Fabrication Meeting In Controlled Area
After award and priod to submission of shop drawings, the Contractor shall conduct a pre-fabrication site vist/meeting to verify field dimensions.
Dimensions that are different from the Contract Drawings and/or Reference Drawings shall be noted on the shop drawings.
Contractors and/or potential contractors wishing to attend the pre-fabrication meeting held at or in LRN restricted/controlled areas (such as a Power Plant or Navigation Lock) shall submit a Nashville District (LRN) Security Access Form to the Nashville District Point of Contact (LRN POC) five (5) working days prior to the site visit or meeting. If submitting the document in less than five working days, the Offeror may not receive approval for participation. The LRN POC will notify the Contractor if the request is approval or denied. Any pre-fabrication meeting which will cover anything other than public domain information shall be limited to US Citizens, except under unique circumstances. The Security Access Form and guidance is available at:
http://www.lrn.usace.army.mil/BusinessWithUs/Contracting/Contract Security Requirements.
Any pre-fabrication meeting which will cover anything other than public domain information shall be limited to US Citizens, except under unique circumstances.
1.9.3.1 U.S. Citizens
The Offeror/Bidder and/or Contractor shall submit a Nashville District (LRN) Security Access Form to the Nashville District Point of Contact (LRN POC) five (5) working days prior to the site visit or any meeting held at or in LRN restricted/controlled areas (such as a Power Plant or Navigation Lock). If submitting the document in less than five working days, the Offeror/Bidder may not receive approval for participation. The LRN POC will notify the individual(s) if the request is approved or denied.
The "U.S. Citizen Pre-Bid or Site Visit" Form with guidance is available at:
http://www.lrn.usace.army.mil/BusinessWithUs/ContractSecurityRequirements.aspx
1.9.3.2 Foreign Nationals (FNs)
FNs wishing to attend a pre-bid meeting or site visit shall submit a completed LRN FN Security Form and legible color copies of two of the following documents: Passport (unexpired or expired), Certificate of U.S.
Citizenship (INS Form N-560 04 N-561), Certificate of Naturalization (INS Form N-550 or N-570), unexpired foreign Passport with I-551 stamp or attached INS Form I-94 indicating unexpired employment authorization, an Alien Registration Receipt Card with photo (INS Form I-151 or I-551), unexpired Temporary Resident Card (INS Form I-688), unexpired Employment
SECTION 35 11 50 Page 14
Authorization Card (INS Form I-688A), unexpired Reentry Permit (INS Form I-327), unexpired Refugee Travel Document (INS- Form I-571), or unexpired Employment Authorization Documentation issued by the INS which contains a photograph (INS Form I-688B) to the LRN POC to be forwarded to LRN-SM for approval. These documents must be submitted two (2) weeks prior to the meeting or site visit. Exceptions will be considered on a case by case basis but will be limited.
The "Foreign National Security Access Form" and "Foreign National Pre-Bid Meeting Request Form" with guidance are available at:
http://www.lrn.usace.army.mil/BusinessWithUs/ContractSecurityRequirements.aspx
1.10 WARRANTY
All equipment and material furnished shall be warrantied for 12 months after delivery.
1.11 QUALIFICATIONS
Contractors shall have at least two years successful experience in fabricating winch units of similar size. A list of the prior winch unit fabrication by the offeror, together with the names and addresses of the buildings, the names of the owners or manager thereof, and any other pertinent information may be required to be submitted promptly upon request by the Government. The offer may be rejected if the offeror has established on former jobs a record for unsatisfactory winch fabrication, has repeatedly failed to complete contracts awarded to him/her within the contract time, or otherwise fails to meet the experience requirements of this clause.
1.12 APPLICABLE DRAWINGS
The following drawings are provided as reference and contract drawings. All dimensions shall be verified by the contractor:
Contract Drawings:
64W330-1: Chamber Tow Haulage - Machinery Recess and Plan 64W330-2: Chamber Tow Haulage - Assembly and Details 61W301: Chamber Tow Haulage - Concrete Slab Reinforcement
Reference drawings:
DWG 02-L602.3-20^27.1: Towing Equipment - Recesses DWG 02-L602.3-20^28.1: Towing Equipment - Sections & Track Details DWG 02-L602.3-20^29.2: Towing Equipment - Track Details DWG 02-L602.3-33^1.1: Towing Equipment - Assembly DWG 02-L602.3-33^2.1: Towing Equipment - Details DWG 02-L602.3-33^3.2: Towing Equipment - Details DWG 02-L602.3-33^4.2: Towing Equipment - Details
1.13 WITHHOLDING OF PAYMENT
No payment for materials incorporated in the work will be made if all required Designer of Record or required Government approvals have not been obtained. No payment will be made for any materials incorporated into the work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted
SECTION 35 11 50 Page 15
Proposal.
1.14 STAMPS
Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements is to include:
a. Firm Name
b. Checkbox corresponding to "Approved"
c. Checkbox corresponding to "Approved with corrections as noted on submittal data and/or attached sheets"
d. Signature of approving official (Electronic or Scanned are Acceptable for electronic delivery).
e. Title of approving official
f. Date Signed
For design-build construction, both the Contractor Quality Control System Manager and the Designer of Record are to stamp and sign to certify that the submittal meets contract requirements.
1.15 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13 and Department of Labor regulations, U.S. Army Corps of Engineers(USACE)contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract.
While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
a. U.S. Department of Labor Veterans employment: www.vets.gov/
b. Federal veteran employment information:
www.fedshirevets.gov/index.aspx
c. Veterans’ Employment and Training Service (VETS):
http://www.dol.gov/vets/
d. Veterans Opportunity to Work (VOW) Program:
http://benefits.va.gov/vow/
e. Hiring Our Heroes initiative:
www.uschamberfoundation.org/hiring-our-heroes
f. Guide to Hiring Veterans:
https://obamawhitehouse.archives.gov/sites/default/files/docs/white_house_busine
SECTION 35 11 50 Page 16
PART 2 PRODUCTS
2.1 MATERIALS
Where the characteristics of any material are not explicitly specified, approved material meeting the requirements of the appropriate specifications of the American Society for Testing Materials or other recognized standard shall be employed. Incidental fittings, fixtures, accessories, and supplies shall be of approved manufacture and of standard first-grade quality.
2.1.1 Specialty Metals
Any material(s) used in this contract that can be classified as a "Specialty Metal", as defined by FAR 252.225-7008, Restriction on Acquisition of Specialty Metals, shall conform to FAR 252.225-7008. In addition to the material and classification (and all the other Shop Drawings requirements) being noted on the shop drawings, specialty metals, if used, will be explicity noted as a specialty metal on all shop drawings.
Proof of origin, mill, and/or manufacture, as applicable, of specialty metals, if used, shall be submitted with the shop drawings.
2.2 FABRICATION
2.2.1 Structural Fabrication
Structural steel shall be in accordance with ASTM A36/A36M or ASTM A572/A572M, GR 50. Material shall be straight before being laid off or worked. Perform straightening, if necessary, by methods that will not impair the metal. Sharp kinks or bends will be cause for rejection of the material. Material with welds will not be accepted except where welding is definitely specified, indicated or otherwise approved. Make bends using approved dies, press brakes or bending rolls. Where heating is required, take precautions to avoid overheating the metal and allow it to cool in a manner that will not impair the original properties of the metal. Proposed flame cutting of material, other than structural steel, will be subject to approval and shall be indicated on detail drawings. Shearing shall be accurate and all portions of the work neatly finished. Corners shall be square and true unless otherwise shown. Re-entrant cuts shall be filleted to a minimum radius of 3/4 inch unless otherwise approved. Provide finished members free of twists, bends and open joints. Bolts, nuts and screws shall be tight.
2.2.1.1 Dimensional Tolerances for Structural Work
Measure dimensions using an approved calibrated steel tape of approximately the same temperature as the material being measured. The overall dimensions of an assembled structural unit shall be within the tolerances indicated on the drawings or as specified in the particular section of these specifications for the item of work. Where tolerances are not specified in other sections of these specifications or shown, an allowable variation of 1/32 inch is permissible in the overall length of component members with both ends milled; component members without milled ends shall not deviate from the dimensions shown by more than 1/16 inch for members 30 feet or less.
2.2.1.2 Structural Steel Fabrication
Structural steel may be cut by mechanically guided or hand-guided torches, SECTION 35 11 50 Page 17 provided an accurate profile with a surface that is smooth and free from cracks and notches is obtained. Prepare surfaces and edges in accordance with AWS D1.1/D1.1M, Subsection 3.2. Where structural steel is not to be welded, chipping or grinding will not be required except as necessary to remove slag and sharp edges of mechanically guided or hand-guided cuts not exposed to view. Chip, grind or machine to sound metal hand-guided cuts which are to be exposed or visible.
2.2.2 Welding
2.2.2.1 Welding of Structural Steel
a. Welding Procedures for Structural Steel - Prequalify welding procedures for structural steel as described in AWS D1.1/D1.1M, or qualify by tests as prescribed in AWS D1.1/D1.1M. Properly documented evidence of compliance with all requirements of these specifications for previous qualification tests shall establish a welding procedure as prequalified. For welding procedures qualified by tests, the test welding and specimen testing will be witnessed and the test report document signed by the COR. Approval of any welding procedure will not relieve the Contractor of the responsibility for producing a finished structure meeting all requirements of these specifications.
b. Welding Process - Perform welding of structural steel by an electric arc welding process using a method which excludes the atmosphere from the molten metal and conforms to the applicable provisions of AWS D1.1/D1.1M. Minimize residual stresses, distortion and shrinkage from welding.
c. Welding Technique
(1) Filler Metal - The electrode, electrode-flux combination and grade of weld metal shall conform to the appropriate AWS specification for the base metal and welding process being used or be as shown where a specific choice of AWS specification allowable is required. Use a controlled temperature storage oven at the job site as prescribed by AWS D1.1/D1.1M, to maintain low moisture of low hydrogen electrodes.
(2) Preheat and Interpass Temperature - Perform preheating as required by AWS D1.1/D1.1M, or as otherwise specified except that the temperature of the base metal shall be at least 70 degrees F.
(3) Stress-Relief Heat Treatment - Where stress relief heat treatment is specified or shown, perform in accordance with the requirements of AWS D1.1/D1.1M, unless otherwise authorized or directed.
d. Workmanship - Perform welding workmanship in accordance with AWS D1.1/D1.1M, and other applicable requirements of these specifications.
(1) Preparation of Base Metal - Prior to welding inspect surfaces to be welded to ensure compliance with AWS D1.1/D1.1M.
(2) Temporary Welds - Make temporary welds, required for fabrication and erection, under the controlled conditions prescribed for permanent work. Conduct preheating for temporary welds as required by AWS D1.1/D1.1M for permanent welds except that the minimum temperature shall be 120 degrees F in any case.
SECTION 35 11 50 Page 18
(3) Tack Welds - Subject tack welds that are to be incorporated into the permanent work to the same quality requirements as the permanent welds; clean and thoroughly fuse them with permanent welds.
2.2.2.2 Welding of Steel Castings
Remove unsound material from the surfaces of steel castings, to be incorporated into welded connections, by chipping, machining, air-arc gouging or grinding. Do not weld major connections designed for transfer of stresses if the temperature of the casting is lower than 100 degrees F.
Castings containing over 0.35 percent carbon or over 0.75 percent manganese shall be preheated to a temperature not to exceed 450 degrees F and conduct welding while the castings are maintained at a temperature above 350 degrees F. Welding will not be permitted on castings containing carbon in excess of 0.45 percent except on written authorization. Castings requiring welding repairs after the first annealing and castings involving welding fabrication shall be stress-relieved annealed prior to receiving final machining unless otherwise permitted.
2.2.2.3 Welding of Steel Studs
Conform to the requirements of AWS D1.1/D1.1M, except as otherwise specified for the procedures for welding steel studs to structural steel, including mechanical, workmanship, technique, stud application qualification, production quality control and fabrication and verification inspection procedures.
2.2.2.4 Qualification of Welders
Certify that the qualification of welders and welding operators and tack welders who will perform structural steel welding have been qualified for the particular type of work to be done in accordance with the requirements of AWS D1.1/D1.1M, Section 4 prior to commencing fabrication. List the qualified welders by name and specify the code and procedures under which qualified and the date of qualification within the certification. Prior qualification will be accepted if welders have performed satisfactory work under the code for which qualified within the preceding three months.
Welders are required to repeat the qualifying tests when their work indicates a reasonable doubt as to proficiency. Those passing the re-qualification tests will be re-certified. Those not passing will be disqualified until passing. Contractor incurs all expenses in connection with qualification and re-qualification. Submit welder certification for approval.
2.2.3 Casting
Each casting and castings weighing more than 500 pounds shall bear cast or stamped heat numbers. Dimensions of castings shown on approved detail drawings are finished dimensions. Castings that are warped or otherwise distorted or that are oversize to an extent that will interfere with proper fit with other parts of the winch unit or structure will be rejected. The structure of metal in castings shall be homogeneous and free from excessive nonmetallic inclusions. Excessive segregation of impurities or alloys at critical points in castings will be cause for rejection. Do not make repairs to castings prior to approval. Surface imperfections will be considered minor when the depth of the cavity prepared for welding is the lesser of 20 percent of the actual wall thickness or 1 inch. Defects other
SECTION 35 11 50 Page 19 than minor surface imperfections may be welded only when specifically authorized in accordance with the following requirements:
a. The defects have been entirely removed and are judged not to affect the strength, use or machineability of the castings when properly welded and stress relieved.
b. The proposed welding procedure, stress relief and method of examination of the repair work have been submitted and approved.
2.2.4 Machine Work
Tolerances, allowances and gauges for metal fits between plain, non-threaded, cylindrical parts shall conform to ASME B4.1 for the class of fit shown or required unless otherwise shown on approved detail drawings.
Where fits are not shown they will be suitable as approved. Tolerances for machine-finished surfaces designated by non-decimal dimensions shall be within 1/64 inch. Sufficient machining stock will be allowed on placing pads to ensure true surfaces of solid material. Provide finished contact or bearing surfaces true and exact to secure full contact. Polish journal surfaces and finish all surfaces with sufficient smoothness and accuracy to ensure proper operation when assembled. Parts entering any machine shall be accurately machined and all like parts be interchangeable except that parts assembled together for drilling or reaming of holes or machining will not be required to be interchangeable with like parts. Accurately locate all drilled bolt holes.
2.2.4.1 Finished Surfaces
Provide surface finishes, indicated or specified, in accordance with ASME B46.1. Values of required roughness heights are arithmetical average deviations expressed in microinches. These values are maximum. Lesser degrees will be satisfactory unless otherwise indicated. Compliance with surface requirements shall be determined by sense of feel and visual inspection of the work compared to Roughness Comparison Specimens in accordance with the provisions of ASME B46.1. Values of roughness width and waviness height shall be consistent with the general type of finish specified by roughness height. Where the finish is not indicated or specified use that which is most suitable for the particular surface, provide the class of fit required and be indicated on the detail drawings by a symbol which conforms to ASME B46.1 when machine finishing is provided. Flaws such as scratches, ridges, holes, peaks, cracks or checks which will make the part unsuitable for the intended use will be cause for rejection.
2.2.4.2 Unfinished Surfaces
Lay out all work to secure proper matching of adjoining unfinished surfaces unless otherwise directed. Where there is a large discrepancy between adjoining unfinished surfaces, chip and grind smooth or machine to secure proper alignment. Unfinished surfaces shall be true to the lines and dimensions shown and be chipped or ground free of all projections and rough spots. Fill in depressions or holes not affecting the strength or usefulness of the parts in an approved manner.
2.2.4.3 Pin Holes
Pin Holes shall be bored true to gages, smooth and straight, and at right angles to the axis of the member. The boring shall be done after the member
SECTION 35 11 50 Page 20 is securely fastened in position.
2.2.4.4 Bearings
Bearings may be lined with babbit or bronze unless otherwise specified or shown. Where the bearing pressure is in excess of 200 psi, bearings shall be lined with bronze. For general purpose bronze bushings, the allowable bearing pressure should be below 1,500 psi with a maximum concentrated bearing pressure of not more than 5,000 psi (this refers to a bushing with an eccentric load). Anti-friction bearings of approved types and of sizes not less than those recommended by the bearing manufacturer for the duty intended will be permitted subject to approval. Properly align all bearings provided with a suitable means of lubrication. Install anti-friction bearings as required to provide for retention of the lubricant and to exclude dirt and grit.
2.2.5 Shop Assembly
Assemble each machinery and structural unit furnished in the shop to determine the correctness of the fabrication and matching of the component parts unless otherwise specified. Do not exceed those tolerances shown.
Closely check each unit assembled to ensure that all necessary clearances have been provided and that binding does not occur in any moving part.
Assembly in the shop shall be in the same position as final installation in the field unless otherwise specified. Perform assembly and disassembly work in the presence of the COR unless waived in writing.
Immediately remedy errors or defects disclosed by the Contractor without cost to the Government. Before disassembly for shipment each piece of a machinery or structural unit shall be match-marked to facilitate erection in the field. Indicate the location of match-marks by circling with a ring of white paint after the shop coat of paint has been applied or as otherwise directed.
2.3 BOLTS, NUTS AND ANCHOR BOLTS
All bolts, anchor bolts, nuts, and washers shall be galvanized or Zinc coated in accordance with ASTM A153/A153M.
2.3.1 Bolts and Studs
Except as otherwise specified or shown, all bolts and studs shall conform to the minimum requirements of ASTM F3125/F3125M for semifinished, washer-faced, heavy hexagon heads and shall have cut threads, coarse-thread series, class 2A fit for bolts, 2B fit for nuts. Bolts and studs shall be furnished with nuts and washers as required. Socket head bolts in accordance with ASTM A574 shall be used if interference exists when hexagon head bolts are used.
a. Bolt holes shall be accurately located, smooth, perpendicular to the member, and cylindrical.
b. Holes for regular bolts shall be drilled or subdrilled…