Disclaimer Plans as discussed today are draft and subject to change prior to solicitation.
Solicitation is currently planned for June 2017.
Solicitation documents will be posted on FEDBIZOPPS.
The website and solicitation number are:
Website: www.fbo.gov Solicitation number: W912P5-17-B-0001
Unfortunately, we cannot answer any questions at this time.
There will be a question and answer session during solicitation.
24 March 2017 USACE - Nashville District
J.W. Purcell, Contract Specialist Adam Walker, Project Manager Britt Henderson, Civil Engineer Chickamauga Lock Replacement Lock Chamber Contract Industry Review
File Name Information as of 17 March 2017; Subject to change prior to Solicitation
“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
.59 Agenda Welcome Corps/TVA Personnel Introductions Contracting Information Total Project Overview Lock Chamber Contract General Information Design Features Discussion
Corps/TVA Personnel Introductions Adam Walker – Project Manager Stacy Wiggins – Contracting Officer J.W. Purcell – Contract Specialist Britt Henderson – Civil Engineer, Technical Lead Mike Arles – Geologist Sarah Wiles – Geologist Jim Niznik – TVA Daniel Moore - TVA Tommy Long – Resident Engineer, ACO Rex Smith – COR Dewayne Ponds – Geologist Scott Caldwell – Civil Engineer Jill Kelly – QA Chris Ellis - QA
Contracting Information Procurement Information Full and Open Competition IFB for Heavy Construction Magnitude of $250M - $500M Anticipated Solicitation: June 2017 (60 days) Anticipated Award: September 2017
Questions and Comments
| Email: James.W.Purcell@usace.army.mil |
| Submit Comments by March 31, 2017 |
Chickamauga Lock Replacement Continued degradation of the existing lock necessitates a Replacement Lock - Potential to cutoff 318 navigable river miles.
New 110 ft x 600 ft lock will pass 9 barges per lockage as opposed to the existing 60 ft x 360 ft lock’s 1 barge per lockage.
4 spillway bays will be removed during construction of the new lock.
The planning done for the original lock envisioned the possibility of needing a larger lock and created the 4 bay space adjacent to the old lock instead of the 3 bay space on the rest of the dam.
AAR
Road & Bridges - $6M Completed Feb 2007 Cofferdam - $86M Awarded Sep 2006, Comp 2012 Lock Chamber Award anticipated: Sep ‘17
Lock & Associated Facilities $749M Road and Bridges 6M Total $755M
$211M Obl thru FY 16 = 28% completed Bridge Fabrication - $400K Completed June 2011 Gates & Valves - $17M Awarded Sep 2009, Comp 2012
Cofferdam Stabilization - $3.1M Awarded Sep 2015, Comp 2016
Lock Excavation - $33.2M Sep ’16 Award Base and 2 Options at $26M.
Approach Walls Award anticipated: ??Sep ’21
Approach Beams - $14M Awarded Apr 2010, Comp 2013
Decommissioning/Site Work Award anticipated: ??Sep ’20
Chickamauga Lock Replacement
Chickamauga Lock Fully funded certified estimate $755M (FY 17, Complete 2023) Gray – Completed Contract, Yellow – Ongoing Contract, Red – Future Contract Lock Excavation Contract awarded Sept 2016 to Heeter Geotechnical Construction out of Mount Morris, PA ; Full Base and 8 Options will be a 2 year duration. Currently exercising Base and Options 2 and 4 in FY16.
FY 17 – Plan to award the Lock Chamber Contract for the 110’x600’ lock.
Project Background The existing 60’ X 360’ lock chamber suffers from Alkali-Aggregate Reaction(AAR), commonly known as concrete growth: a reaction between the Alkali used in the cement and the Aggregate used in the concrete for construction of the lock. The concrete absorbs moisture and causes swelling of the concrete mass resulting in misalignment of components and instability of the structure. Aggressive maintenance and monitoring were implemented by LRN to counteract the effects of AAR, but this approach is cost-prohibitive as a long term solution.
The effects of AAR can be mitigated to an extent, but, the rate of growth is uncontrolled. At some point, TVA may close the lock if the Dam Safety Officer believes the AAR effects threaten dam safety.
The replacement lock will resolve the AAR problem and the standard size will provide more efficient lockages at Chickamauga.
Uncertainty surrounding completion of Chickamauga Lock could inhibit economic development upstream.
Loss of the lock function would result in probable transfer of cargo to highways and railways (which do not have available capacity), loss of transportation rate savings, and increased carbon emissions.
There are 318 navigable river miles upstream of the lock, including three locks and dams (Watts Bar, Ft. Loudon and Melton Hill), two TVA nuclear power plants, the DOE facility at Oak Ridge, numerous commercial stakeholders such as Olin-Lonza Chemical, and Knoxville, the third largest city in Tennessee. Many of these users transport cargo on the river that would be impractical or impossible to carry via rail or roadway.
Plans and specifications for the replacement lock are complete.
With consistent and sufficient funding, the replacement lock could be operational in 2022.
Construction activities at the project were temporarily suspended 2012-2015, until additional funding was received.
More than 28% complete from a time standpoint
Lock Chamber Contract - Design Features Miter Gates, Culvert Valves, and Bulkheads
Fabricated in Birmingham, AL, stored at TVA facility in Muscle Shoals, AL
Chickamauga Lock
Current Construction Contract – Lock Excavation 44 Inclined Rock Strand Anchors 51’ Long Secant Pile Ret. Wall Rock Excavation Contract Award Sep 2016 – total contract amount $33.2M Base and 2 of 8 Options exercised in FY16 (~$26M)
- 2 year Contract duration.
Current Contract, Lock Excavation, was awarded in Sept 2016.
-Total contract will have a 2 year duration, valued at $33.2M -FY16: awarded Base and 2 of 8 options, valued at $26M.
Remaining options ($7.2M) will be exercised in FY17, pending addition funding form FY17 Work Plan.
Scope includes: the secant pile wall to retain a bentonite layer located under monolith 13 of new land wall; installing 44 inclined rock stand anchors (must be complete before rock excavation begins), exploratory drilling for future monolith foundations, and 98,000 CY of rock excavation.
Lock Replacement Project – Initial Unwatering during lock excavation contract
Complete lock features located inside Cofferdam Contract Award - Sep 2017 Base with Options Contract Lock chamber contract
-Next planned contract, Lock Chamber, will be a Base with Options contract to begin concrete placements; anticipate awarding the base in FY17.
-Scope will include all items related to the new chamber that are located inside the cofferdam area, such as:
Concrete placement, new lock operations building, installing previously fabricated miter gates and culvert valves (which are stored at other TVA facilities), electrical systems, mechanical equipment, etc.
- Follow on contracts will be awarded to construct approach walls, decommission the existing lock, and complete site development activites.
Project Funding Project is funded 50% Inland Waterways Trust Fund (IWTF) and 50% Federal Appropriations. IWTF revenues generated from tax on marine diesel fuel.
4th highest priority construction project for IWTF funding.
Project received no funding in FY12-FY14, due to funding constraints of IWTF.
Changes occurred in 2014 that strengthened the IWTF.
WRDA 2014 – Increased diesel fuel fee from $0.20 to $0.29/gallon Olmsted Dam cost share changed from 50/50 to 85/15
Project Funding (continued) Like many inland navigation projects, Chickamauga is not currently eligible for the President’s Budget due to Benefit- Cost Ratio requirements.
Project has received funding through Corps of Engineer Work Plans or “Funding Pots”:
FY15 = $3.0M
FY16 = $29.9M (Capability = $29.9M)
Anticipated Lock Chamber solicitation in June 2017 is subject to receipt of additional funding in FY17.
Continuing Resolution until 28 April 2017.
Lock Replacement Project – February 2017 Information as of 17 March 2017; Subject to change prior to Solicitation Disposal Area Existing Lock Cofferdam
Lock Chamber Contract - Project Orientation
Upstream Downstream Land Wall River Wall
Lock Chamber contract
| Base | Concrete Batch Plant |
| Option 1 | Conveyor, Testing Facilities, QA Facilities |
| Option 2 | Remaining Excavation, Mud Mat, Drilled Shaft |
| Option 3 | Landwall Concrete from foundation to 5 ft above culvert (EL 631.5) |
| Option 4 | Upper Riverwall Concrete from foundation to 5 ft above culvert (EL 631.5) |
| Option 5 | Lower Riverwall Concrete from foundation to 5 ft above culvert (EL 631.5), Grouting |
| Option 6 | Landwall Concrete from EL 631.5 to EL 645 |
| Option 7 | Riverwall Concrete from EL 631.5 to EL 660 |
| Option 8 | Remainder of Concrete including Handrail, Instrumentation, Access Bridge Installation, Misc Work |
| Option 9 | Installation of Culvert Valves and Miter Gates including machinery and second pour concrete |
| Option 10 | Approach Wall Exploratory Drilling Program |
| Option 11 | Operations Building, Control Shelters, Electrical and small Mechanical Items |
| Option 12 | Bay 5 Shear Wall |
| Option 13 | Commissioning of the new lock |
Base and Options Anticipated Period of Performance: 4.5-6 years
Lock Chamber Contract - Options Concrete Sections
Monolith R5
Monolith L5
Option 3 Option 4 & 5 Option 7 Option 6 Option 8
Lock Replacement Project – Alternate view of site
General Information
Lock Chamber contract Construction Limits
Lock Chamber contract – Initial Construction Limits until Lock Excavation contract is complete
Contractor Areas Restricted Area
Excavation
Lock Replacement Project – stilling basin area
Tie-In with Existing Spillway
U-Frame Monolith - Concrete Sections
Example of U-Framed Monoliths Photo of Kentucky Lock Addition Project
Concrete Sections
Monolith R5
Monolith L5
Previously completed Segmental Cofferdam Wall
Example of Typical Monoliths Photo of Kentucky Lock Addition Project
Concrete Sections – Tie-in with Existing Segmental Cofferdam
Operations Building
Control Shelters Operations Building
Government Furnished Items @ Muscle Shoals
Fabricated in Birmingham, AL, stored at TVA facility in Muscle Shoals, AL
Lock Chamber Contract - Design Features Bay 5 Shear Wall
Bay 5
Bay 5 Shear Wall
Discussion This is a Special Notice and is for planning purposes only as defined by FAR 15.201. This is not a solicitation announcement, nor is it an Invitation for Bid (IFB), Request for Proposal (RFP), or Request for Quote (RFQ). No solicitation is currently published. Participation in this conference by any party does not obligate the Government in any contract award. The Government will not pay for the provision of any information, nor will it compensate any respondents for the development of such information. The Government is not responsible for any costs associated with: reviewing the Draft Documents, preparing and submitting comments, or any other efforts towards participation in this conference. Furthermore, the Government is not obligated to compensate respondents for any information received, even if the Draft Documents are revised as a result of a respondent's comment or question. Respondents should refrain from providing proprietary information in the course of the conference, since any information acquired by the Government in this forum will not be treated as proprietary. The information gathered will be used by the Government to make appropriate acquisition decisions. Replies to responses, comments, or suggestions will not be provided or published.
Please provide input on the how the Base and Options were separated.
Please provide input on idea of the “variable” period of performance.
Please provide input on the sufficiency of the laydown area.
Please provide any other recommendations for the improvement of the Plans and Specifications.
image11.jpg image12.jpeg image13.png image14.jpeg image15.jpeg image16.png image17.jpeg image18.jpeg image19.png image20.jpeg image21.jpeg image22.jpeg image23.jpeg image24.jpg image25.png image26.png image27.png image28.jpg image29.png image30.png image31.jpg image32.png image33.jpeg image34.png image35.png image36.png image37.jpg image38.jpg image39.png image40.png image41.png image42.png image43.jpg image44.jpeg image45.jpg image46.png image47.png image48.png image49.png image1.png image2.png image3.png image4.png image5.png image6.png image7.jpg image8.tiff image9.tiff image10.png