W912P5-15-B-0004 Amendment 0001

View the file

Other files

File Type Posted
Q12-58_CVR.1.pdf PDF
SiteVisitRoster.pdf PDF
Q12-58 11.pdf PDF
W912P5-15-B-0004.pdf PDF
Cheatham_Spillway_Bulkheads_Full_Size_Folio_5-6-15.pdf PDF
15B0004_TSpecs_RTA.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTING DIVISION (JWP)

JAMES.W.PURCELL@USACE.ARMY.MIL

(615) 736-7674

(615) 736-7124

NASHVILLE TN 37202-1070

W38XDD51061191

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to incorporate prospective bidder Q&A, provide a site plan for the alternative storage area, and provide the site visit roster.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Jun-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P5-15-B-0004

X 9B. DATED (SEE ITEM 11)

28-May-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Jun-2015

CODE

US ARMY CORPS OF ENGINEERS-NASHVILLE

CELRN-CT, R00M A680,

110 NINTH AVE. SOUTH

NASHVILLE TN 37202-1070

W912P5 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W912P5

FACILITY CODECODE

EMAIL:TEL:

W912P5-15-B-0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by full text:

AMENDMENT 0001

Cheatham Lock and Dam Spillway Bulkhead Procurement

Prospective Bidder Questions

Q1: Will ultrasonic examination be a requirement for the ASTM A148 Roller and Grease Retainer castings?

A1: ASTM A148 provides the acceptance criteria for these castings. Ultrasonic examination of these components will not be a requirement for this contract.

Q2: Paragraph 2.2.3.2.4.1 “Ultrasonic Testing” (UT) requires that “The ultrasonic equipment shall be capable of making a permanent record of the test indications.” We would like clarification that they strictly mean permanent record of rejectable discontinuities and not of test indications? Ultrasonic indications are simply signals on an electronic display. Ultrasonic testing of welds is done with an “A” scan display and is not a static image of test results. UT is very dynamic as the inspector is moving a transducer manually and observing the ultrasonic pulse/echo signals on a screen. If the inspector does find a signal/indication that exceeds a specific criteria he can freeze that image on the screen and basically provide a photograph of the screen. Maybe the correct terminology would be “….capable of making a permanent record of rejectable discontinuities?

A2: The Government concurs that UT testing is very dynamic and is very much dependent on the technician performing the tests. While the discontinuities will be more evident and should definitely have permanent records, all welds tested should have a permanent record. If the technician finds no rejectable discontinuities in a weld, then a simple snapshot anywhere along the weld can be made with the proper notations indicating that there were no rejectable discontinuities within the weld.

Q3: In reference with roller bearing on drawing Q12-58/9, the SKF 23330 bearing is obsolete. SKF suggested replacement bearing is 22330 CCW33 bearing. The bearing width on the replacement bearing is narrower than the obsolete bearing.

A3: The substituted bearing (22330 CCW33) is acceptable. Contractor shall redesign the grease retainer on DWG Q12-58/9 to make up the desired width of the new bearing. Shop drawing of the new bearing, grease retainer and other modified items (by the contractor) shall be submitted on the shop drawings (Section 05 59 13, Par. 1.5.5) for approval.

Q4: Will delivery by truck be permitted in an alternative storage area?

A4: Yes, an alternative storage area on the lock side of the project has been identified for use during this contract (See drawing Q12-58/11). Truck delivery of the spillway bulkheads to the alternative storage area is permitted. Off –loading of the bulkheads remains the responsibility of the Contractor at either storage location.

Note: Revised cover sheet for drawings (Q12-58_CVR.1), site plan for spillway bulkhead storage areas (Q12- 58/11), and the site visit roster are attached separately.