This document is an Abstract of Offers for Construction for the West Valley Spillway Repair project. The solicitation (W912P425BA010) was issued by the Department of the Army, US Army Engineer District in Buffalo, NY on 31-Jan-25, with bids opened on 03-Mar-25. The project involves repair work at the West Valley site in New York, with two offers received: a government estimate and an offer from Laubacher Enterprises, Inc. from Niagara Falls, NY.
The bidding schedule includes 15 line items covering various construction activities such as mobilization/demobilization, construction access, clearing, demolition, erosion control, structural excavation and fill, drainage, concrete work, stone armoring, and site restoration. The total estimated project cost ranges from $4,756,988.66 (government estimate) to $4,898,000.00 (Laubacher Enterprises bid). Each line item has detailed unit quantities and pricing, with both the government estimate and the contractor's bid provided for comparative analysis. The bid security for both offers is a bid bond at 20% of the total bid amount.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
XX
Item Est. Unit Estimated Unit Estimated Unit Estimated No. Description of Offered Item Quantity Unit Price Amount Price Amout Price Amout
Bidding Schedule
Mobilization &
Demobilization 1 JOB $403,156.59 $403,156.59 $473,482.35 $473,482.35
Construction Acces
1 JOB $154,124.17 $154,124.17 $111,500.00 $111,500.00
3 Clearing & Grubbing 3 ACRE $11,790.77 $35,372.31 $1,750.00 $5,250.00
Demolition and
Deconstruction 1 JOB $23,495.82 $23,495.82 $8,750.00 $8,750.00
5 Work Zone Traffic Control 1 JOB $11,443.95 $11,443.95 $11,000.00 $11,000.00
Erosion and Sediment
Control 1 JOB $150,496.33 $150,496.33 $180,000.00 $180,000.00
7 Structural Excavation 11,270 BCY $15.64 $176,262.80 $37.15 $418,680.50
8A Structural Fill 3,975 BCY $68.23 $271,214.25 $88.25 $350,793.75
8B Embankment Fill 2,675 BCY $112.65 $301,338.75 $55.40 $148,195.00
9 Drainage Stone 1,350 CY $259.31 $350,068.50 $77.70 $104,895.00
8" Perforated PVC Drain
Pipe 980 LF $53.68 $52,606.40 $163.50 $160,230.00
11 Structural Concrete 1,935 CY $1,207.44 $2,336,396.40 $1,242.00 $2,403,270.00
Solicitation Number 31-Jan-25 03-Mar-25 Date Issued: Date Opened
ABSTRACT OF OFFERS - CONSTRUCTION I CERTIFY that I have opened, read, and recorded on this abstract all offers received in
W912P425BA010 response to this solicitation.
Issuing Office Department Of The Army
US Army Engineer District, Buffalo O F F E R S 478 Main Street
OFFEROR OFFEROR
Buffalo, NY 14202 NO. 1 NO. 2
Niagara Falls, NY
Laubacker Enterprises, Inc.
Project Title GOVERNMENT ESTIMATE
BID SECURITY (type & amount) BID SECURITY (type & amount)
West Valley Spillway Repair A. HIRED LABOR
ADDENDA ACKNOWLEDGED ADDENDA ACKNOWLEDGED
(without profit) Bid bond - 20% of Bid Bid bond - 20% of bid West Valley, New York B. REASONABLE CONTRACT
(including profit)
NUMBER OF ADDENDA ISSUED: C. REASONABLE CONTRACT
Stone Armoring (Shoreline
Protection) 2,763 TONS $69.44 $191,862.72 $61.80 $170,753.40
13 Rip Rap 600 TONS $77.57 $46,542.00 $225.00 $135,000.00
14 Site Restoration 1 JOB $224,878.84 $224,878.84 $200,000.00 $200,000.00
15 As- Built Development 1 JOB $27,728.83 $27,728.83 $16,200.00 $16,200.00
Total $4,756,988.66 $4,898,000.00
| 2025-03-03T13:32:26-0500 | |
| ERNEST.JEFFREY.G.1016090294 |