Abstract IGE adjusted_Rochester FY22.xls
XLS spreadsheet 40 KB Posted
- Attached to
- FY22 Rochester Pier Repair
- Solicitation number
- W912P422B0006
About this file
This document contains an abstract for bids submitted in response to solicitation number W912P422B0006 for the Rochester Pier Repair Project issued by the Department of the Army Corps of Engineers Engineering District Buffalo. The project consists of furnishing all labor, materials, and equipment necessary to perform repair work on the pier. The NAICS code is 237990 with a size standard of $39.5 million. The government intends to award one firm fixed-price contract with a period of performance between the estimated dates of $1-5 million. Three bids were received in response ranging from $3.88-4.18 million. The work includes items such as mobilization, sheet piling, concrete work, armor stone installation, and pier lighting.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Rochester East Pier FY22 W912P422B0006.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bidder 1-3
| W912P4-22-B-0006 | response to this solicitation. | ||||||||
| Rochester | |||||||||
| Issuing Office | Tyrone Palaganase | ||||||||
| Department Of The Army | Contracting Officer | ||||||||
| US Army Engineer District, Buffalo | O F F E R S | ||||||||
| 1776 Niagara Street | |||||||||
| Buffalo, NY 14207-3199 | NO. 1 | NO. 2 | |||||||
| Project Title | GOVERNMENT ESTIMATE | OFFEROR | OFFEROR | ||||||
| GLDM | Dean Marine | ||||||||
| FY 22 Little Sodus | A. HIRED LABOR | Muskogon, MI | Mt. Clemens, MI | ||||||
| Fairport, NY | B. REASONABLE CONTRACT | BID SECURITY (type & amount) | BID SECURITY (type & amount) | ||||||
| XX | (without profit) | Bid bond - 20% of Bid | Bid bond - 20% of bid | ||||||
| NUMBER OF ADDENDA ISSUED: | C. REASONABLE CONTRACT | ADDENDA ACKNOWLEDGED | ADDENDA ACKNOWLEDGED | ||||||
| (including profit) | |||||||||
| Item | Est. | Unit | Estimated | Unit | Estimated | Unit | Estimated | ||
| No. | Description of Offered Item | Quantity | Unit | Price | Amount | Price | Amout | Price | Amout |
| Bidding Schedule | |||||||||
| Schedule A | |||||||||
| 1 | Mobilization and Demobilization | 1 | JA | $ 764,937.00 | $ 536,556.00 | $ 724,738.00 | |||
| 2 | Record (As-built) Draw | 1 | JA | $ 69,621.15 | $ 22,000.00 | $ 26,763.74 | |||
| 3 | Drive Line Clear Both sides | 1 | JA | $ 112,211.20 | $ 159,033.00 | $ 82,238.71 | |||
| 4 | Wave Absorb Re-build | 240 | LF | $ 403.85 | $ 96,924.00 | $ 587.00 | $ 140,880.00 | $ 505.47 | $ 121,312.80 |
| 5 | PZC-18 Sheet Pile | 22,164 | SF | $ 84.15 | $ 1,865,100.60 | $ 63.00 | $ 1,396,332.00 | $ 59.49 | $ 1,318,536.36 |
| 6 | Granular Fill Stone | 2,728 | TN | $ 59.15 | $ 161,361.20 | $ 69.00 | $ 188,232.00 | $ 101.98 | $ 278,201.44 |
| 7 | Concrete Cap | 543 | CY | $ 1,744.10 | $ 947,046.30 | $ 1,135.00 | $ 616,305.00 | $ 1,149.55 | $ 624,205.65 |
| 8 | Steel Ladders | 3 | EA | $ 9,142.15 | $ 27,426.45 | $ 5,039.00 | $ 15,117.00 | $ 5,608.18 | $ 16,824.54 |
| 9 | Concrete Removals | 1 | JA | $ 31,194.30 | $ 9,740.00 | $ 19,852.25 | |||
| Total Estimated Amount 1-9 | $ 4,075,822.20 | $ 3,084,195.00 | $ 3,212,673.69 | ||||||
| 10 | Record (As-built) Draw | 1 | JA | $ 53,083.15 | $ 5,500.00 | $ 13,381.87 | |||
| 11 | Drive Line Clear Both sides | 1 | JA | $ 36,614.55 | $ 50,891.00 | $ 27,412.91 | |||
| 12 | Wave Absorb Re-build | 60 | LF | $ 403.30 | $ 24,198.00 | $ 587.00 | $ 35,220.00 | $ 456.88 | $ 27,412.80 |
| 13 | PZC-18 Sheet Pile | 7,060 | SF | $ 101.45 | $ 716,237.00 | $ 60.00 | $ 423,600.00 | $ 67.71 | $ 478,032.60 |
| 14 | Granular Fill | 83 | TN | $ 61.00 | $ 5,063.00 | $ 69.00 | $ 5,727.00 | 236.57 | $ 19,635.31 |
| 15 | Concrete Cap | 174 | CY | $ 2,135.55 | $ 371,585.70 | $ 1,135.00 | $ 197,490.00 | $ 1,256.35 | $ 218,604.90 |
| 16 | Concrete Removals | 1 | JA | $ 32,482.95 | $ 7,940.00 | $ 33,234.12 | |||
| Total Estimated Amount 10-16 | $ 1,239,264.35 | $ 726,368.00 | $ 817,714.51 | ||||||
| 17 | Bulkhead | 1 | JA | $ 121,004.70 | $ 34,876.00 | $ 102,620.28 | |||
| 18 | Armor Stone | 25 | EA | $ 1,061.20 | $ 26,530.00 | $ 1,300.00 | $ 32,500.00 | $ 1,618.12 | $ 40,453.00 |
| 19 | Pier Lights | 6 | EA | $ 2,752.80 | $ 16,516.80 | $ 1,856.00 | $ 11,136.00 | $ 535.97 | $ 3,215.82 |
| Total Estimated Amount 1-19 | $ 5,479,138.05 | $ 3,889,075.00 | $ 4,176,677.30 |