Abstract IGE adjusted_Rochester FY22.xls

XLS spreadsheet 40 KB Posted

Attached to
FY22 Rochester Pier Repair
Solicitation number
W912P422B0006
Issued by

About this file

This document contains an abstract for bids submitted in response to solicitation number W912P422B0006 for the Rochester Pier Repair Project issued by the Department of the Army Corps of Engineers Engineering District Buffalo. The project consists of furnishing all labor, materials, and equipment necessary to perform repair work on the pier. The NAICS code is 237990 with a size standard of $39.5 million. The government intends to award one firm fixed-price contract with a period of performance between the estimated dates of $1-5 million. Three bids were received in response ranging from $3.88-4.18 million. The work includes items such as mobilization, sheet piling, concrete work, armor stone installation, and pier lighting.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bidder 1-3

W912P4-22-B-0006response to this solicitation.
Rochester
Issuing OfficeTyrone Palaganase
Department Of The ArmyContracting Officer
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROR
GLDMDean Marine
FY 22 Little SodusA. HIRED LABORMuskogon, MIMt. Clemens, MI
Fairport, NYB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 764,937.00$ 536,556.00$ 724,738.00
2Record (As-built) Draw1JA$ 69,621.15$ 22,000.00$ 26,763.74
3Drive Line Clear Both sides1JA$ 112,211.20$ 159,033.00$ 82,238.71
4Wave Absorb Re-build240LF$ 403.85$ 96,924.00$ 587.00$ 140,880.00$ 505.47$ 121,312.80
5PZC-18 Sheet Pile22,164SF$ 84.15$ 1,865,100.60$ 63.00$ 1,396,332.00$ 59.49$ 1,318,536.36
6Granular Fill Stone2,728TN$ 59.15$ 161,361.20$ 69.00$ 188,232.00$ 101.98$ 278,201.44
7Concrete Cap543CY$ 1,744.10$ 947,046.30$ 1,135.00$ 616,305.00$ 1,149.55$ 624,205.65
8Steel Ladders3EA$ 9,142.15$ 27,426.45$ 5,039.00$ 15,117.00$ 5,608.18$ 16,824.54
9Concrete Removals1JA$ 31,194.30$ 9,740.00$ 19,852.25
Total Estimated Amount 1-9$ 4,075,822.20$ 3,084,195.00$ 3,212,673.69
10Record (As-built) Draw1JA$ 53,083.15$ 5,500.00$ 13,381.87
11Drive Line Clear Both sides1JA$ 36,614.55$ 50,891.00$ 27,412.91
12Wave Absorb Re-build60LF$ 403.30$ 24,198.00$ 587.00$ 35,220.00$ 456.88$ 27,412.80
13PZC-18 Sheet Pile7,060SF$ 101.45$ 716,237.00$ 60.00$ 423,600.00$ 67.71$ 478,032.60
14Granular Fill83TN$ 61.00$ 5,063.00$ 69.00$ 5,727.00236.57$ 19,635.31
15Concrete Cap174CY$ 2,135.55$ 371,585.70$ 1,135.00$ 197,490.00$ 1,256.35$ 218,604.90
16Concrete Removals1JA$ 32,482.95$ 7,940.00$ 33,234.12
Total Estimated Amount 10-16$ 1,239,264.35$ 726,368.00$ 817,714.51
17Bulkhead1JA$ 121,004.70$ 34,876.00$ 102,620.28
18Armor Stone25EA$ 1,061.20$ 26,530.00$ 1,300.00$ 32,500.00$ 1,618.12$ 40,453.00
19Pier Lights6EA$ 2,752.80$ 16,516.80$ 1,856.00$ 11,136.00$ 535.97$ 3,215.82
Total Estimated Amount 1-19$ 5,479,138.05$ 3,889,075.00$ 4,176,677.30