Abstract of Bids Schedule A W912P420B0006 1.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- LaSalle Park Shoreline Protection Project
- Solicitation number
- W912P420B0006
About this file
This document contains an abstract of bids for a federal construction contract opportunity. The US Army Corps of Engineers Buffalo District solicited proposals for the LaSalle Park Shoreline Protection Project in Buffalo, New York, to construct approximately 1,355 feet of shoreline protection along Lake Erie and the Niagara River. The project involves items such as mobilization, record drawings, path and concrete removals, pipe piles, concrete work, structural fill, geotextiles, bracing, turf establishment, handrails, tree planting, and excavation. Three bids were received from Cold Spring Construction, Union Concrete and Construction Corp., and Hohl Industrial Services, ranging from $4.4 million to $6.3 million for the base contract and $6.1 million to $8.9 million overall when including options. The solicitation was issued as an invitation for bid requiring firm fixed pricing with bonding and System for Award Management registration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract of Bids Schedule B W912P420B0006 1.xlsx | XLSX spreadsheet | |
| Amendment 0005_12May2020.pdf | ||
| Amendment 0004_23Apr2020.pdf | ||
| Amendment 0003_16Apr2020.pdf | ||
| Amendment 0002_07Apr2020.pdf | ||
| Amendment 0001_02Apr2020.pdf | ||
| Solicitation Package LaSalle Final_02Apr2020.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table 1
| ABSTRACT OF BIDS - Construction | 1. SOLICITATION NUMBER | |||
| W912P420B0006 | 2. DATE ISSUED | |||
| 4/02/20 | 3. DATE OPENED | |||
| 05/20/2020 | PAGE | |||
| 1 | OF PAGES |
| 4. ISSUING OFFICE | |||
| US Army Corp of Engineers Contracting Branch, Detroit District | I CERTIFY that I have opened, read, and recorded on this abstract all timely offers received in response to the solicitation. | NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE) |
Walter Kamad, Contracting Officer
SIGNATURE DATE SIGNED
21-May-2020
| 5. PROJECT TITLE | |||
| FY20 LaSalle Shoreline, Schedule A | 8. GOVERNMENT ESTIMATE | 9. OFFERS |
NO. 1 NO. 2
| A. Hired Labor | A. OFFEROR: | |||
| Cold Spring Construction | A. OFFEROR: | |||
| Union Concrete and Construction Corp. | A. OFFEROR: |
Hohl Industrial Services
| X | B. Reasonable Contract (Without Profit) | B. BID SECURITY (TYPE AND AMOUNT) | |||
| 20% | B. BID SECURITY (TYPE AND AMOUNT) | ||||
| 20% | B. BID SECURITY (TYPE AND AMOUNT) |
20%
| 6. Number of Amendments Issued | |||||
| 1 | C.Reasonable Contract (With Profit) | C. AMENDMENTS ACKNOWLEDGED | |||
| Yes | C. AMENDMENTS ACKNOWLEDGED | ||||
| Yes | C. AMENDMENTS ACKNOWLEDGED |
Yes
| 7A. ITEM NO | 7B. DESCRIPTION OF OFFERED ITEM | 7C. EST. QUANTIT | |||||||||||||||||
| Y | D. UNIT | E. UNIT PRICE | F. ESTIMATED AMOUNT | D. UNIT PRICE | E. ESTIMATED AMOUNT | D. UNIT PRICE | E. ESTIMATED AMOUNT | D. UNIT PRICE | E. ESTIMATED AMOUNT | ||||||||||
| 0001 | Mobilization/Demobilization | 1 | JA | $425,209.85 | $ 425,209.85 | $ 300,000.00 | $ 300,000.00 | $1,800,000.00 | $1,800,000.00 | $501,451.00 | $501,451.00 | ||||||||
| 0002 | Record As-built Drawings (Reach 1) | 1 | JA | $66,955.80 | $ 66,955.80 | $ 5,000.00 | $ 5,000.00 | $20,000.00 | $20,000.00 | $72,800.00 | $72,800.00 | ||||||||
| 0003 | Existing Path Removal (Reach 1) | 552 | LF | $63.05 | $ 34,803.60 | $ 25.00 | $ 13,800.00 | $7.00 | $3,864.00 | $37.00 | $20,424.00 | ||||||||
| 0004 | Pipe Piles | 99 | EA | $122,114.90 | $ 1,199,375.10 | $ 11,000.00 | $ 1,089,000.00 | $5,000.00 | $495,000.00 | $16,390.00 | $1,622,610.00 | ||||||||
| 0005 | Concrete Pile Fill | 620 | CY | $606.65 | $376,123.00 | $220.00 | $136,400.00 | $145.00 | $89,900.00 | $579.00 | $358,980.00 | ||||||||
| 0006 | Concrete Deck, Beams and Retaining Wall | 1420 | CY | $849.15 | $1,205,793.00 | $775.00 | $1,100,500.00 | $2,130,000.00 | $2,130,000.00 | $1,634.00 | $2,320,280.00 | ||||||||
| 0007 | Existing Concrete Removals | 1 | JA | $164,895.95 | $164,895.95 | $40,000.00 | $40,000.00 | $140,000.00 | $140,000.00 | $64,620.00 | $64,620.00 | ||||||||
| 0008 | Structural Fill | 860 | CY | $122.11 | $105,014.60 | $70.00 | $60,200.00 | $110.00 | $94,600.00 | $121.00 | $104,060.00 | ||||||||
| 0009 | Geotextile | 1950 | SY | $5.04 | $9,828.00 | $3.00 | $5,850.00 | $6.00 | $11,700.00 | $8.00 | $15,600.00 | ||||||||
| 0010 | Bracing for Excavation (Reach 1) | 1 | JA | $230,045.75 | $230,045.75 | $335,000.00 | $335,000.00 | $150,000.00 | $150,000.00 | $303,870.00 | $303,870.00 | ||||||||
| 0011 | Turf Establishment | 1 | JA | $16,903.80 | $16,903.80 | $30,000.00 | $30,000.00 | $55,000.00 | $55,000.00 | $50,830.00 | $50,830.00 | ||||||||
| 0012 | Hand Rails and Mesh | 1360 | LF | $412.75 | $561,340.00 | $185.00 | $251,600.00 | $200.00 | $272,000.00 | $335.00 | $455,600.00 | ||||||||
| 0013 | Bollards and Cleats Removal and Storage | 10 | EA | $470.15 | $4,701.50 | $200.00 | $2,000.00 | $700.00 | $7,000.00 | $797.00 | $7,970.00 | ||||||||
| 0014 | New Asphalt Path | 1 | JA | $14,974.70 | $14,974.70 | $15,000.00 | $15,000.00 | $1,600.00 | $1,600.00 | $12,062.00 | $12,062.00 | ||||||||
| 0015 | Tree Planting | 32 | EA | $386.40 | $12,364.80 | $1,250.00 | $40,000.00 | $1,550.00 | $49,600.00 | $1,207.00 | $38,624.00 | ||||||||
| 0016 | Excavation for Pipe Piles | ||||||||||||||||||
| Placement | 1 | JA | $252,501.25 | $ 252,501.25 | $1,000,000.00 | $ 1,000,000.00 | $1,000,000.00 | $1,000,000.00 | $286,900.00 | $286,900.00 | |||||||||
| TOTAL AMOUNT OF BASE BID | $ 4,680,830.70 | $ 4,424,350.00 | $6,320,264.00 | $6,236,681.00 | |||||||||||||||
| 0017 | Option 1 | ||||||||||||||||||
| Record As-built Drawings (Reach 2) | 1 | JA | $86,361.85 | $86,361.85 | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 | $72,800.00 | $72,800.00 | |||||||||
| 0018 | Existing Path Removal (Reach 2 | 780 | LF | $60.85 | $47,463.00 | $8.00 | $6,240.00 | $7.00 | $5,460.00 | $33.00 | $25,740.00 | ||||||||
| 0019 | Tree Removal | 1 | JA | $21,836.30 | $21,836.30 | $15,000.00 | $15,000.00 | $5,000.00 | $5,000.00 | $14,780.00 | $14,780.00 | ||||||||
| 0020 | Park Benches, and Picnic Tables Removal and Re-installation | 1 | JA | $13,146.15 | $13,146.15 | $8,000.00 | $8,000.00 | $4,300.00 | $4,300.00 | $13,207.00 | $13,207.00 | ||||||||
| 0021 | Existing Concrete Removals | 1 | JA | $164,545.50 | $164,545.50 | $45,000.00 | $45,000.00 | $55,000.00 | $55,000.00 | $48,222.00 | $48,222.00 | ||||||||
| 0022 | Concrete Surface Repairs | 45 | CY | $1,313.15 | $59,091.75 | $665.00 | $29,925.00 | $1,200.00 | $54,000.00 | $13,521.00 | $608,445.00 | ||||||||
| 0023 | Structural Fill | 160 | CY | $92.25 | $14,760.00 | $84.00 | $13,440.00 | $100.00 | $16,000.00 | $134.00 | $21,440.00 | ||||||||
| 0024 | Grout | 250 | CY | $1,091.45 | $272,862.50 | $425.00 | $106,250.00 | $13.00 | $32,500.00 | $561.00 | $140,250.00 | ||||||||
| 0025 | PZ-22 Steel Sheet Pile | 9840 | LF | $96.20 | $946,608.00 | $105.00 | $1,033,200.00 | $100.00 | $984,000.00 | $100.00 | $984,000.00 | ||||||||
| 0026 | New Concrete Path | 860 | LF | $341.40 | $293,604.00 | $225.00 | $193,500.00 | $18.00 | $154,800.00 | $366.00 | $314,760.00 | ||||||||
| 0027 | Turf Establishment | 1 | JA | $27,454.45 | $27,454.45 | $30,000.00 | $30,000.00 | $52,000.00 | $52,000.00 | $30,590.00 | $30,590.00 | ||||||||
| 0028 | Bollards and Cleats Removal and Storage | 8 | EA | $579.40 | $4,635.20 | $200.00 | $1,600.00 | $700.00 | $5,600.00 | $912.00 | $7,296.00 | ||||||||
| 0029 | Tree Planting | 45 | EA | $352.05 | $15,842.25 | $1,300.00 | $58,500.00 | $1,550.00 | $69,750.00 | $1,283.00 | $57,735.00 | ||||||||
| TOTAL AMOUNT OF OPTION 1 | $ 1,968,210.95 | $ 1,545,655.00 | $1,448,410.00 | $2,339,265.00 | |||||||||||||||
| 0030 | Option 2 Optional Concrete Path | 1349 | LF | $810.00 | $1,092,690.00 | $100.00 | $134,900.00 | $275.00 | $370,975.00 | $216.00 | $291,384.00 | ||||||||
| 0031 | 31 Tree Removal | 1 | JA | $15,597.35 | $15,597.35 | $7,000.00 | $7,000.00 | $2,100.00 | $2,100.00 | $14,286.00 | $14,286.00 | ||||||||
| TOTAL AMOUNT OF OPTION 2 | $ 1,108,287.35 | $ 141,900.00 | $373,075.00 | $305,670.00 | |||||||||||||||
| TOTAL AMOUNT OF BASE AND ALL OPTIONS | $ 7,757,329.00 | $ 6,111,905.00 | $8,141,749.00 | $8,881,616.00 |