FY19_SOW_MMD_Custodial_Services.pdf
PDF 310 KB Posted
- Attached to
- MOUNT MORRIS DAM CUSTODIAL SERVICES
- Solicitation number
- W912P4-19-T-0001
About this file
Statement of Work Mount Morris Dam, Mount Morris, NY Seasonal Custodial Services
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QUESTIONS_AND_ANSWERS.pdf | ||
| W912P4-19-T-0001.pdf | ||
| Price_Breakout_Schedule.xlsx | XLSX spreadsheet | |
| SITE_VISIT.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Army Corps of Engineers®
Buffalo District
Statement of Work Mount Morris Dam, Mount Morris, NY Seasonal Custodial Services Customer:
Manager, Mount Morris Dam and Recreation Area
Prepared By: S. Winslow U.S. Army Corps of Engineers Buffalo District 1776 Niagara Street Buffalo, NY 14207
November 2018
1 GENERAL DESCRIPTION OF WORK
The contractor shall perform the following work under this contract:
1.1 Base Bid Item(s)
1.1.1 Base Bid Item 1
Provide custodial services three (3) days a week for the Visitor Center from 01 May 2019 to 28 Oct 2019 for a total of seventy-eight (78) days.
1.1.2 Base Bid Item 2
Provide custodial services one (1) day a week for the MMD Conference Room, Administrative Office Area, and Employee Kitchen and bathroom from 03 May 2019 to 25 Oct 2019 for a total of twenty-six (26) days.
1.2 Optional Bid Item(s)
1.2.2 Optional Bid Item 1
Provide custodial services three (3) days a week for the Visitor Center from 01 May 2020 to 26 October 2020 for a total of seventy-seven (77) days.
1.2.3. Optional Bid Item 2
Provide custodial services one (1) day a week for the MMD Conference Room, Administrative Office Area, and Employee Kitchen and bathroom from 01 May 2020 to 23 Oct 2020 for a total of twenty-six (26) days.
1.2.4. Optional Bid Item 3
Provide custodial services three (3) days a week for the Visitor Center from 30 Apr 2021 to 27 Oct 2021 for a total of seventy-eight (78) days.
1.2.5. Optional Bid Item 4
Provide custodial services one (1) day a week for the MMD Conference Room, Administrative Office Area, and Employee Kitchen and bathroom from 30 Apr 2021 to 22 Oct 2021 for a total of twenty-six (26) days.
1.2.6. Optional Bid Item 5
Provide custodial services three (3) days a week for the Visitor Center from 29 Apr 2022 to 26 Oct 2022 for a total of seventy-eight (78) days.
1.2.7. Optional Bid Item 6
Provide l custodial services one (1) day a week for the MMD Conference Room, Administrative Office Area, and Employee Kitchen and bathroom from 29 Apr 2022 to 21 Oct 2022 for a total of twenty-six (26) days.
1.2.8. Optional Bid Item 7
Provide custodial services three (3) days a week for the Visitor Center from 01 May 2023 to 27 Oct 2023 for a total of seventy-nine (78) days.
1.2.9. Optional Bid Item 8
Provide custodial services one (1) day a week for the MMD Conference Room, Administrative Office Area, and Employee Kitchen and bathroom from 05 May 2023 to 27 Oct 2023 for a total of twenty-seven (26) days.
2 POINT OF CONTACT
For scheduling project site visits and/or questions regarding this Statement of Work:
U.S. Army Corps of Engineers, Buffalo District
Attn: Contracting Officer 1776 Niagara Street Buffalo, New York 14207
Phone: 716-879-4173 Facsimile: 716-879-4353
3 PRE-BID SITE VISIT
There will be one (1) scheduled pre-bid site visit for prospective bidders. The date and time of the visit will be posted on FBO. The location of the visit will be William B. Hoyt II Visitor Center, 6103 Visitor Center Road, Mount Morris Dam and Recreation Area, Mount Morris, New York 14510. Prospective bidders are urged to attend to gain information that will be necessary in the preparation of bid submittals. Due to maintenance, operation and security requirements, unscheduled visits will not be honored. Following a visit to the project site, a question and answer session will be held. During this session, prospective bidders are asked to direct all questions concerning the project to the Buffalo District Contracting Office (DCO).
4 PROJECT/CONTRACTUAL REFERENCES
EM 385-1-1, 3 Sep 2008, U.S. Army Safety and Health Requirements Manual
5 DETAILED DESCRIPTION OF WORK AND PROJECT INFORMATION
5.1 Detailed Description of Work – Base Bid Item(s)
5.1.1 Base Bid Item 1
Contractor shall provide custodial services with the following requirements:
Frequency: Cleaning shall be performed (3) days a week on Monday, Wednesday, and Friday between the hours of 08:30 to 10:00am, including any federal holidays. All work described in this statement of work shall be completed daily, no later than 10:00am when the Visitor Center opens to the public. In order to meet this requirement, the contractor shall employ more than one (1) worker. Failure to meet the required 10:00am deadline for completion of daily work requirements may be grounds for unsatisfactory contractor performance.
Period of Performance: Contractor shall commence work on 01 May 2019, and complete work on 28 October 2019 for a total number of seventy-eight (78) work days (federal holidays included). The bid item for this contract will be on a per-day quantity, with a bid quantity of seventy-eight (78) total work days. If work is not performed on any required workday, payment will not be made for days missed. Failure to meet these performance requirements will be considered basis for defaulting on the contract and may result in contract termination.
Areas to be Cleaned:
o Visitor Center Restrooms: 685 square feet of ceramic tile o Restroom Foyer: 50 square feet of ceramic tile o Atrium: 1735 square feet of ceramic tile o Exhibit and Activity Area: 1375 square feet of carpet o Media Room: 675 square feet of carpet
Duties and Responsibilities:
o Daily:
Empty waste containers, place new waste bags, and return to initial location. Items such as cardboard boxes shall be recycled and packing material too large or bulky for the waste baskets shall be placed in the large trash receptacles located adjacent to the maintenance building. Waste bags will be furnished by the government to the contractor.
Clean and disinfect surfaces of toilets, urinals, toilet seats, paper product dispensers and depositories, bathroom stall surfaces, railings, restroom entrance doors, infant changing stations, hand dryers, drinking fountains, sinks, and wall surfaces. Mirrors shall be cleaned with glass cleaner, leaving the surface free of streaks and other evidence of removable soil.
Fixtures and surfaces will be determined clean when all dirt, grime, streaks, and scale is removed. Chrome fixtures shall be polished. Brushes, sponges, cloths, or paper towels used to clean toilet fixtures shall not be used to clean any other areas.
Floors shall be swept free of dirt and debris, then wet-mopped with a disinfectant suitable for use on such floor surface, per product label. Floor surfaces will be determined clean when free of streaks and other evidence of removable soil.
Carpeted areas shall be inspected for gum, tar, and other substances stuck to the surface, and such substances shall be removed prior to vacuuming. Vacuum all carpeted areas. Areas such as corners not accessible by a push vacuum shall be cleaned with a vacuum hose with brush attachment. Carpets will be considered clean when free of all visible litter, soil, and embedded dirt.
Cloths used for cleaning or disinfecting surfaces must be disposable (ie: paper towels) or shall be laundered and/or replaced after each workday.
Mop heads, dust mops used for any cleaning, dusting, and/or mopping will be laundered or replaced monthly.
Perform a visual inspection of sink areas and report leaking fixtures, drainage problems, non-working light bulbs and damage to walls, floors, and fixtures to the government.
o Weekly:
Clean interior window glass, doors, door knobs, and counters, free of visible smudges, fingerprints, marks, streaks, etc. Cleaner suitable per product label for glass use shall be used on all windows and surfaces shall be free of streaks and any soil.
Clean/dust surfaces in each work area which include tables, benches, chairs, visitor exhibits, furniture, baseboard molding, window trim and sills, hand rails, and vents. Use cleaner suitable for use on such surface per product label.
o As Needed:
Refill all paper product dispensers and soap dispensers. Paper products and soap will be furnished by the government to the contractor.
Restrictions:
o Contractor shall not dispose of cleaning chemicals and supplies such as rags, towels, paper, etc. in the urinals or toilets, as the toilets are an environmentally friendly composting system and foreign chemicals and material is detrimental to the functionality of the system. Only approved cleaning products may be dumped into the utility sink located in the supply closet. Contractor’s employees must seek permission from Mount Morris Dam staff before dumping chemicals into the sink.
Healthy High Performance Cleaning (HPPC):
Contractor shall implement Healthy High Performance Cleaning methods. Include as a pre-bid submittal contractor cleaning procedures for employees for all specified surfaces in this Statement of Work. Include as a pre-work submittal all cleaning solvents to be used. Products shall not be used until approved by the government. Include all SDS sheets. The following shall be followed:
o Solvents: All cleaning solvents shall be environmentally preferable products. Allowable cleaning products shall be clearly labeled on the container with either a Green Seal or an EPA Design for the Environment label.
o Vacuum: The contractor supplied vacuum to be used shall meet the Carpet and Rug Institutes (C&RI) Green Label Program and be fitted with appropriate bags and HEPA filters.
5.1.2 Base Bid Item 2
Provide custodial services one (1) day a week for the MMD Conference Room, Administrative Office Area, and employee kitchen and bathroom (shop area) from 03 May 2019 to 25 Oct 2019 for a total of twenty-six (26) days.
Frequency: Cleaning shall be performed (1) day a week, on Fridays, between the hours of 08:30am to
12:00pm, including any federal holidays. All work described in this statement of work shall be completed daily no later than 12:00pm. In order to meet this requirement, the contractor shall employ more than one (1) worker. Failure to meet the required 12:00pm deadline for completion of daily work requirements may be grounds for unsatisfactory contractor performance.
Period of Performance: Contractor shall commence work on 03 May 2019 and complete work on 25 October 2019. The total number of work days excluding shall equal twenty-six (26), including federal holidays. The bid item for this contract will be on a per-day quantity, with a bid quantity of twenty-six (26) total work days.
If work is not performed on any required workday, payment will not be made for days missed. Contractor shall not fail to perform work on two (2) or more consecutive workdays or two (2) or more workdays in each calendar month. Failure to meet these performance requirements will be considered basis for defaulting on the contract and may result in contract termination.
Areas to be Cleaned:
o Mount Morris Dam Conference Room: 200 square feet of linoleum o Administrative Office Area: 605 square feet of carpet o Employee Kitchen/Bathroom: 210 square feet of ceramic tile
Duties and Responsibilities:
o weekly Clean/dust surfaces in conference room, administrative office area, employee kitchen and bathroom which includes tables, desks, cubicles, chairs, furniture, baseboard molding, window trim and sills, countertops, and vents. Use cleaner suitable for use on such surface per product label.
Clean interior window glass, doors, door knobs, and exterior of appliances (refrigerators, range and microwaves).
Clean and disinfect surfaces of toilets, toilet seats, vanity top, shower stall (interior and exterior), sinks, wall surfaces and doors.
Mirrors shall be cleaned with glass cleaner leaving the surface free of streaks and other evidence of removable soil. Fixtures shall be determined clean when all dirt, grime, streaks, and scale is removed. Chrome fixtures shall be polished. Brushes, sponges, cloths, or paper towels used to clean toilet fixtures shall not be used to clean any other areas.
Empty waste containers, place new waste bags, and return to initial location. Items such as cardboard boxes shall be recycled and packing material too large or bulky for the waste baskets shall be placed in the large trash receptacles located adjacent to the maintenance building. Waste bags will be furnished by the government to the contractor.
Carpeted areas shall be inspected for gum, tar, and other substances stuck to the surface. Remove any substances and vacuum all carpeted areas. Areas such as corners not accessible by a push vacuum shall be cleaned with a vacuum hose with brush attachment. Carpets shall be free of all visible litter, soil, and embedded dirt.
Floors shall be swept free of dirt and debris, then wet-mopped with a disinfectant suitable for use on such floor surface per product label. Floor surfaces shall be free of streaks and other evidence of removable soil.
Cloths used for cleaning or disinfecting surfaces will be disposable (ie: paper towels) or laundered and/or replaced after each workday. Mop heads and/or dust mops will be laundered or replaced monthly
5.2 Optional Bid Item(s)
5.2.1 Optional Bid Item 1
Provide custodial services for the Visitor Center as described in Base Bid Item 1, (3) days a week from 01 May 2020 to 26 Oct 2020 for a total of seventy-seven (77) days.
5.2.2 Optional Bid Item 2
Provide custodial services as described in Base Bid Item 2, one (1) day a week for the MMD Conference Room, Administrative Office Area, and Employee Kitchen and Bathroom from 01 May 2020 to 23 Oct 2020 for a total of twenty-six (26) days.
5.2.3 Optional Bid Item 3
Provide custodial services as described in Base Bid Item 1, three (3) days a week for the Visitor Center from 30 Apr 2021 to 27 Oct 2021 for a total of seventy-eight (78) days.
5.2.4 Optional Bid Item 4
Provide custodial services as described in Base Bid Item 2, one (1) day a week for the MMD Conference Room, Administrative Office Area, and Employee Kitchen and Bathroom from 30 Apr 2021 to 22 Oct 2021 for a total of twenty-six (26) days.
5.2.5 Optional Bid Item 5
Provide custodial services as described in Base Bid Item 1, three (3) days a week for the Visitor Center from 29 Apr 2022 to 26 Oct 2022 for a total of seventy-eight (78) days.
5.2.6 Optional Bid Item 6
Provide custodial services as described in Base Bid Item 2, one (1) day a week for the MMD Conference Room, Administrative Office Area, and Employee Kitchen and Bathroom from 29 Apr 2022 to 21 Oct 2022 for a total of twenty-six (26) days.
5.2.7 Optional Bid Item 7
Provide custodial services as described in Base Bid Item 1, three (3) days a week for the Visitor Center from 01 May 2023 to 27 Oct 2023 for a total of seventy-nine (78) days.
5.2.8 Optional Bid Item 8
Provide custodial services as described in Base Bid Item 2, one (1) day a week for the MMD Conference Room, Administrative Office Area, and Employee Kitchen and Bathroom from 05 May 2023 to 27 Oct 2023 for a total of twenty-seven (26) days.
6 PROJECT INFORMATION
6.1 Basis for Award
The government shall award the contract to the offeror who provides the lowest price technically acceptable offer.
The evaluated price shall include the base work plus all option(s). In order to be considered technically acceptable, the contractor shall:
Have a minimum of (5) years experience on projects of a similar nature. The contractor shall supply the names, locations, and client contact information for two (2) projects of similar size and scope that have been accomplished within the previous five (5) years as part of the bid submittals.
6.1.1 Multi-Year Optional Bid Items
Optional bid items are setup to allow the government to award up to an additional four (4) years of work beyond the base work for this contract. If the government chooses to award any of these optional work periods, the award date of the optional bid item(s) will be no sooner than thirty (30) days prior to the beginning of the performance period of the optional line item(s).
6.2 Pre-Work Submittals
All pre-work submittals, as stated in Section 16.2 of this SOW, shall be provided to the government within fourteen
(14) days following the award of the contract. The contractor shall allow seven (7) days for government review of submittals.
6.3 Material/Equipment Information
Contractor shall provide all labor, tools, equipment, supplies and materials needed to complete the work described herein, unless otherwise noted herein that any of these items will be provided by the government.
6.4 Material/Equipment Storage
Material storage will be accommodated for brooms, vacuums, mops, and towels only. The contractor shall not store any liquid cleaning solvents, products, or chemicals. All liquid cleaning products shall be removed from the premises after work is completed for said day.
7 QUALITY ASSURANCE (QA)
7.1 Overview
7.1.1 Government Project Manager (PM)
The government has appointed a Project Manager (PM) for this project. The PM shall ensure all questions of a technical nature concerning the contractual work are answered.
7.1.2 Government Quality Assurance (QA)
The government will appoint a Quality Assurance (QA) person to ensure all work is accomplished in accordance with contractual documents. The QA person for this contract will be identified after the contract is awarded. The QA person serves as the liaison between the contractor, PM, and the District Contracting Officer (DCO). The QA person does not have the authority to modify contractual agreements.
8 COMMUNICATION
During the execution of the contract, the PM shall receive weekly status reports from the contractor on issues such as milestones met and/or missed, and issues standing in the way of project completion. The DCO shall be the communication hub for the government QA Person, PM, and the contractor regarding clarification of contractual issues. Adhering to the established lines of communication will reduce or avoid generation of duplicate requests for information, which may inadvertently result in the government or contractor performing contractual changes without official approval by the DCO.
9 REPAIR/RESTORATION OF GOVERNMENT PROPERTY
The contractor, at no expense to the government, is required to protect all government facilities, grounds, and equipment, during contractual performance. All government structures, grounds, and equipment disturbed by contractor during the performance of work shall be returned to a pre-work condition prior to request of final payment.
Damages to government property that were caused by contractor and/or sub-contractor will be repaired at no expense to the government by the prime contractor.
10 WORK STOPPAGE, CONTRACT CANCELLATION PROTOCOLS
The Mount Morris Dam Manager, or government QA person, may issue temporary “Stop Work” notification if they find activities or job site conditions are in violation of Federal, Department of Defense, State or local health, safety and/or environmental standards, laws and regulations. The District Safety Officer (DSO), the DCO, and the PM shall be contacted immediately after a Stop Work notification order is issued or rescinded. Violation of health, safety or environmental regulations committed by the contractor shall not be grounds for compensation by the government to the contractor. Refer to contractual documents provided by the District Contracting Office regarding additional work stoppage and/or contract cancellation actions.
11 MATERIAL CHANGE ORDERS
Once equipment and materials are approved and accepted by the government, the contractor shall not substitute equipment or materials without providing a detailed explanation for the substitution. Changes in materials will require full justification and approval from the DCO. Modifications to contractual documents must be reviewed by the contractor, government QA person and PM, and approved by the government’s DCO. Requests for modifications must be in writing explaining the reasons for the modification, detailed description of the modification and what the benefits are and an estimated cost broken down by materials, labor and equipment.
12 COMPLETION
The contract will not be deemed fulfilled until all services are provided by the contractor under the terms of the contractual documents and found satisfactory to the DCO.
13 PAYMENT
The project will be paid for on a per workday basis, the per-day price for which includes all labor, materials, supplies, equipment, mobilization/demobilization, disposal, and other costs required to complete the work. Partial payment(s) on a monthly basis will be made; this will be discussed at the pre-construction meeting.
14 SAFETY
14.1 Publications
Contractor shall follow all applicable safety requirements detailed in the USACE Safety & Health Requirements Manual EM 385-1-1 (30 November 2014), available on-line at:
https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf The project shall not proceed until all safety submittals required under this contract have been reviewed and accepted by the government.
14.2 Questions
Questions regarding Safety and Health requirements for the project shall be addressed to the DCO with an informational copy provided to the PM. The contractor shall permit safety inspections by any government personnel of all work being performed.
14.3 Accident Reporting
All contractor accidents, involving injuries or property damage, occurring during the execution of this contract shall be reported to USACE within 4 hours of the contractor becoming aware of its occurrence. Notification will include contractor name; contract title; type of contract; name of activity, installation or location where accident occurred;
date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (to include type of construction equipment used, PPE used, etc.). The USACE initial contact must be made personally (telephone or email messages only are not acceptable) to one of the following:
USACE Point of Contacts:
Name Title Phone Email Stephen Winslow Morris Dam
Manager 585-658-4790 Stephen.E.Winslow@usace.army.mil
Joseph F.
Ricchiazzi
District Safety Officer
Office: (716) 879-4132 Cell: (716) 381-6978 joseph.f.ricchiazzi@usace.army.mil
Walter Kamad Contracting Officer
716-879-4134 Walter.Kamad@usace.army.mil
Gayle Geiger Purchasing Agent
716-879-4211 gayle.geiger@usace.army.mil
14.4 Activity Hazard Analysis (AHA’s)
Work cannot begin until after government acceptance of all Activity Hazard Analysis (AHA). The AHA’s must be developed specifically for this project and shall address the specific safety hazards associated with the work. During the site visit, contractors are encouraged to develop a preliminary hazard list based upon their observations and the information contained in this Scope of Work.
14.5 Man-Hours
USACE requires that contractors (prime and sub) report all man hours worked as well as all lost time for on-the-job accident and illness. This report shall be documented on the Buffalo District Man hour Exposure Report. See Attachment of this scope of work. The reporting time period begins following the award of the contract and continues until the life cycle of the project expires. All accidents shall be reported on USACE Eng Form 3394. Instruction for completing the form can be obtained from the government QA or District Safety Officer.
15 SECURITY
15.1 Start of Work
Contractor shall notify the Manager or identified QA person of their planned arrival at the project to start work at least seven (7) calendar days in advance. Contractor shall submit a weekly work schedule thereafter by no later than the Friday before the coming work week.
15.2 Arrival/Departure
Contractor is required to notify the Mount Morris Dam Manager of their arrival to and departure from the project site.
A similar notification is required if there shall be any deviation or cancellation of a scheduled work day during the life of the project.
15.3 Video/Camera Equipment
Contractor shall not transport or use video or camera equipment while working at Mount Morris Dam and Recreation Area unless permission to do so is requested through the Manager and approval is granted by the Buffalo District Security Officer.
15.4 Personally Identifiable Information (PII)
For all prime and subcontractor employees working at Mount Morris Dam, the following Personally Identifiable Information (PII) shall be provided for the USACE Buffalo District Security Officer to perform a limited background check: Complete name, social security number, date of birth, place of birth, and current address of residence. This information is mandatory before any workers will be allowed to enter the facility.
16 SUBMITTALS
16.1 Bid Submittals
The following submittals are required from the contractor under this Scope of Work to be submitted with the bid proposal:
Complete Bid Schedule with prices for all base and optional items. (See Attached) The product data and specification sheets for the following materials to be used by the contractor:
o Healthy High Performance Cleaning Processes Contractor experience as stated in Section 7.1 Other documentation as required by the DCO:
o Representations and certifications
16.2 Pre-Work Submittals
All submittals are required as per the timeline described in Section 7.2 of this SOW:
Project Submittals Activity Hazard Analysis (AHA’s) All materials/equipment data sheets provided under the contract, including but not limited to:
o Cleaning products with SDS sheets
END OF STATEMENT OF WORK
Attachment #1 – Bid Schedule
BID SCHEDULE BASE WITH 4 OPTION YEARS
MOUNT MORRIS DAM CUSTODIAL
BASE YEAR - FY 19
Item No.
Description Unit Quantity Unit Price Bid Total Item Cost
Provide Custodial Services for Visitor Center- 2019 day 78 $0.00
Provide Custodial Services for Conf Room, Admin Areas, Kitchen/Bathroom day 26 $0.00
Total - Base Year $0.00
OPTION YEAR 1 - FY 20
Item No.
Description Unit Quantity Unit Price Bid Total Item Cost
Provide Custodial Services for Visitor Center- 2019 day 77 $0.00
Provide Custodial Services for Conf Room, Admin Areas, Kitchen/Bathroom day 26 $0.00
*If bid item is chosen for award, the government will award in conjunction with the line item above.
Total - Option Year 1 $0.00
OPTION YEAR 2 - FY 21
No.
Description Unit Quantity Unit Price Bid Total Item Cost
1 Provide Custodial Services - day 78 $0.00
2 Provide Extended Custodial S i *
$0.00
OPTION YEAR 3 - FY 22
No.
Description Unit Quantity Unit Price Bid Total Item Cost
1 Provide Custodial Services - day 78 $0.00
2 Provide Extended Custodial S i *
Total - Option Year 3 $0.00
OPTION YEAR 4 - FY 23
No.
Description Unit Quantity Unit Price Bid Total Item Cost
1 Provide Custodial Services - day 78 $0.00
2 Provide Extended Custodial S i *
Total - Option Year 4 $0.00
Bid Summary
TOTAL BASE YEAR - FY 19 $0.00
TOTAL OPTION YEAR 1 - FY 20 $0.00
TOTAL OPTION YEAR 2 - FY 21 $0.00
TOTAL OPTION YEAR 3 - FY 22 $0.00
TOTAL OPTION YEAR 4 - FY 23 $0.00
Total Project Cost: $0.00
Attachment #2 – Directions to Mount Morris Dam
The Visitor Center at Mount Morris Dam and Recreation Area is located at 6103 Visitor Center Road in
Mount Morris, New York, 14510.
Visitor Center Road is located off Route 408 approximately 2 miles south of Mount Morris and 11 miles north of Nunda.
From the North:
(Interstate 90) take 390-South to exit 7 - Mount Morris/Letchworth, turn left/south off exit 7 onto 408-
South (about 3 miles). When 408S "Ts" at Main St. in the village of Mount Morris, turn left onto Main St., and then turn right at the next block onto Chapel St/408S. Follow Chapel St/408S for about 2 miles, and then turn right onto Visitor Center Rd. You will find Mount Morris Dam Visitor Center at the end (about
1.7 miles).
From the South:
(Route 17, I-86) take 390-North to exit 6 - Sonyea, turn left/north onto Route 36 and continue for about 7 miles into the village of Mount Morris. Turn left at the 1st traffic light onto Chapel St/408S. Follow Chapel St/408S for about 2 miles, and then turn right onto Visitor Center Rd. You will find the Mount Morris Dam Visitor Center at the end (about 1.7 miles).
Attachment #3 – Blank Activity Hazard Analysis