Amendment_1_-_FY19_Conneaut_Dredge_-_Plans_&_Specs_-_Certified_Final_-_RTA_-_W912P419B0008.pdf

PDF 26 KB Posted

Attached to
Conneaut Harbor Maintenance Dredging
Solicitation number
W912P419B0008
Issued by

About this file

Amendment 0001

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY19 CONNEAUT DREDGE AMENDMENT NO. 1

FY19CONNDREDGE W912P419B0008

Commence Actual Dredging Operations 70

Complete Base Bid Work 100

b. The Notice to Proceed will be issued on or about 06/07/19

1.2.1 Environmental Window

The Conneaut Harbor has dredging limitations based upon Environmental conditions. Dredging is permitted only between 1 July and 30 September

1.2.2 Schedule of Work

Submit a complete schedule of work covering the period of time from the Notice of Award through the specified duration of the contract, including all private and Government work, and the plant intended for each project, to the Contracting Officer within 10 calendar days of receipt of the Notice of Award.

1.2.3 Contract Accruals

Submit a monthly listing of accruals. Accruals are used to provide projections of the incremental costs not yet paid for, but earned. Submit the accrual submittal one week before the end of each month throughout the contract duration. Provide accrual information for each line item of the Bidding Schedule.

1.3 PROJECT/SITE CONDITIONS

1.3.1 Condition and Use of Project Site

The drawings indicate elevations and the reference drawings indicate the latest sounding information at the dredging site. Notify the Contracting Officer at least 5 calendar days prior to bringing any dredging/construction equipment or material to the work site. Accept responsibility for damages that may be suffered due to Contractor operations.

1.3.2 Physical Conditions

The physical conditions shown on the drawings are indicative of those that prevailed at the time of the site investigations and may be different than those at the time of dredging. Report significant variations that would require changes to the plans and/or specifications to the Contracting Officer immediately.

1.3.3 Waterways Navigation, Traffic and Notice to Mariners

There is a moderate amount of traffic in the harbor consisting of fishing boats, recreational boats, tugs, barges, and all classes of lake vessels varying in length to a maximum of 620 feet. Become acquainted with all information and regulations pertaining to navigation & vessel traffic within the waterways and must coordinate with the U.S. Coast Guard Offices indicated in paragraph entitled "Notifications" of the Section, to assure that a "NOTICE TO MARINERS" is issued prior to work activity at the project site. A copy of the requisite notice form is an attachment to this solicitation. Submit completed form to the address (shown on the form) no less than 2 weeks prior to the start of work activity at the project site.

SECTION 01 35 13 Page 1021 05/09/19 h5cosklm Highlight h5cosklm Highlight h5cosklm Highlight h5cosklm Highlight

File details come from the government source that posted it.