W912P418T0011
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
REPLACE GARAGE DOOR ON BLDG #3
FFP
Replace rolling steel door on building #3 at US Army Corps of Engineers (Buffalo District), 1776 Niagara Street, Buffalo, NY 14207-3199. The Contractor will provide all plant, labor, equipment, materials, freight and supervision to remove existing rolling steel door, guide assembly, hood and all associated parts. Supply and install new custom size(11’ 11-3/4” X 14’ 1”) right hand drive, 20 gauge galvanized interior mount rolling steel door with 3” flat slats, new guide assembly, hood, weather seals and gray final coat. Contractor to field verify all measurements. See Statement of Work.
FOB: Destination
NET AMT
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
OCT 2010
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
APR 2014
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
OCT 2016
52.204-13 System for Award Management Maintenance OCT 2016 52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.211-18 Variation in Estimated Quantity APR 1984 52.215-13 Subcontractor Certified Cost or Pricing Data--Modifications OCT 2010 52.215-15 Pension Adjustments and Asset Reversions OCT 2010 52.215-19 Notification of Ownership Changes OCT 1997 52.219-6 Notice Of Total Small Business Set-Aside NOV 2011 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards- Overtime
Compensation
MAY 2014
52.222-6 Construction Wage Rate Requirements MAY 2014 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records MAY 2014 52.222-9 Apprentices and Trainees JUL 2005 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-35 Equal Opportunity for Veterans OCT 2015 52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-37 Employment Reports on Veterans FEB 2016 52.222-50 Combating Trafficking in Persons MAR 2015 52.222-54 Employment Eligibility Verification OCT 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
SEP 2013
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-10 Waste Reduction Program MAY 2011 52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
AUG 2011
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-17 Interest MAY 2014 52.232-23 Assignment Of Claims MAY 2014
52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.232-40 Providing Accelerated Payments to Small Business Subcontractors
DEC 2013
52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-4 Physical Data APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.244-6 Subcontracts for Commercial Items NOV 2017 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7012 Safeguarding Covered Defense Information and Cyber
Incident Reporting
OCT 2016
252.209-7004 Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism
OCT 2015
252.223-7004 Drug Free Work Force SEP 1988 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
JUN 2012
252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 days. * The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. As used in this clause--
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4) such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) \1\ Item 1 Foreign construction material.... ........... ___ ........ ....... ………. ___ ................ ........ ___ Domestic construction material... ........ ___ ............... .............. ___ .................. ...... ___ Item 2 Foreign construction material.... ......... ___ ............. ........ ……. ___ ............... ......... ___ Domestic construction material... ....... ___ .................. ............. ___ ................. ....... ___ Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browsefar http://farsite.hill.af.mil/
Section 00 70 00 - Conditions of the Contract
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A Government
General Decision Number: NY180056 06/08/2018 NY56
Superseded General Decision Number: NY20170056
State: New York
Construction Type: Building
County: Erie County in New York.
BUILDING CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.
Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/05/2018 1 01/12/2018 2 03/09/2018 3 05/18/2018 4 06/01/2018 5 06/08/2018
BOIL0007-001 01/01/2017
Rates Fringes
BOILERMAKER......................$ 33.00 28.15
BRNY0045-004 07/01/2017
Rates Fringes
BRICKLAYER.......................$ 31.10 24.55
CEMENT MASON.....................$ 31.10 24.55
MARBLE SETTER....................$ 31.45 23.70
TERRAZZO FINISHER................$ 29.13 14.87
TILE FINISHER....................$ 29.13 14.87
Tilesetter & Terrazzo Worker.....$ 31.45 23.70
CARP0276-014 07/01/2017
6/11/2018https://www.wdol.gov/wdol/scafiles/davisbacon/NY56.dvb?v=5
Rates Fringes
CARPENTER........................$ 32.00 27.13
ELEC0041-003 05/28/2018
Rates Fringes
CABLE SPLICER....................$ 36.73 3%+22.29
ELECTRICIAN......................$ 35.24 27.95
ELEC0041-004 05/29/2017
Rates Fringes
Communications System CABLER......................$ 10.50 11.41+a INSTALLER...................$ 17.65 17.12+a MASTER TECHNICIAN...........$ 26.95 17.40+a SOUND WIREMAN...............$ 24.50 17.33+a
Work covers low voltage construction, installation, maintenance, and removal of teledata facilities (voice, data and video) including outside plant, telephone and data inside wire, interconnect, terminal equipment, central offices, PABX fiber optic cable and equipment, railroad communications, micro waves, V-Sat, bypass, CATV, WAN (wide area networks); LAN (local area networks) and ISDN (integrated systems digital network). Also, installation of sound systems, nurses call systems, intercom systems, staff registry/locating/signaling systems, antenna systems and associated devices; installation of security systems and apparatus, and cabling from VDT's to computers. This work does not apply to new construction, or to the installation of raceway systems and boxes for the above work.
ELEC1249-003 05/07/2018
Rates Fringes
ELECTRICIAN (LINE
CONSTRUCTION: LIGHTING AND
TRAFFIC SIGNAL Including any and all Fiber Optic Cable necessary for Traffic Signal Systems, Traffic Monitoring systems and Road Weather information systems) Flagman.....................$ 26.28 6.75%+23.40+a Groundman (Truck Driver)....$ 35.04 6.75%+23.40+a Groundman Truck Driver (tractor trailer unit)......$ 37.23 6.75%+23.40+a Lineman & Technician........$ 43.80 6.75%+23.40+a Mechanic....................$ 35.04 6.75%+23.40+a
FOOTNOTE:
a. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, plus President's Day, Good Friday, Decoration Day, Election Day for the President of the United States and Election Day for the Governor of the State of New York, provided the employee works the day before or the day after the holiday.
ELEC1249-004 05/07/2018
Rates Fringes
ELECTRICIAN (Line Construction) Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :
Flagman....................$ 30.36 6.75%+23.40+a Groundman digging machine operator...................$ 45.54 6.75%+23.40+a Groundman truck driver (tractor trailer unit).....$ 43.01 6.75%+23.40+a Groundman Truck driver.....$ 40.48 6.75%+23.40+a Lineman and Technician.....$ 50.60 6.75%+23.40+a Mechanic...................$ 40.48 6.75%+23.40+a Substation:
Cable Splicer..............$ 55.66 6.75%+23.40+a Flagman....................$ 30.36 6.75%+23.40+a Ground man truck driver....$ 40.48 6.75%+23.40+a Groundman digging machine operator...................$ 45.54 6.75%+23.40+a Groundman truck driver (tractor trailer unit).....$ 43.01 6.75%+23.40+a Lineman & Technician.......$ 50.60 6.75%+23.40+a Mechanic...................$ 40.48 6.75%+23.40+a Switching structures;
railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation Cable Splicer..............$ 57.11 6.75%+23.40+a Flagman....................$ 31.15 6.75%+23.40 Groundman Digging Machine Operator...................$ 46.73 6.75%+23.40+a Groundman Truck Driver (tractor-trailer unit).....$ 44.13 6.75%+23.40+a Groundman Truck Driver.....$ 44.13 6.75%+23.40+a Lineman & Technician.......$ 51.92 6.75%+23.40+a Mechanic...................$ 41.54 6.75%+23.40+a
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial Day, Good Friday, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New York State, provided the employee works two days before or two days after the holiday.
ELEC1249-008 01/01/2018
Rates Fringes
ELECTRICIAN (Line Construction)
TELEPHONE, CATV
FIBEROPTICS CABLE AND
EQUIPMENT
Cable splicer..............$ 31.83 3%+4.73 Groundman..................$ 16.01 3%+4.73 Installer Repairman- Teledata Lineman/Technician- Equipment Operator.........$ 30.21 3%+4.73 Tree Trimmer................$ 23.95 3%+9.98+a
a. New Year's Day, President's Day, Good Friday, Decoration Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving, Christmas Day.
ELEV0014-001 01/01/2018
Rates Fringes
ELEVATOR MECHANIC................$ 48.26 32.645+a+b
FOOTNOTE:
a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.
b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.
ENGI0017-001 07/01/2015
BUILDING CONSTRUCTION
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 33.68 27.90+a GROUP 2.....................$ 28.88 27.90+a GROUP 3.....................$ 34.13 27.90+a GROUP 4.....................$ 34.38 27.90+a GROUP 5.....................$ 34.88 27.90+a GROUP 6.....................$ 34.45 27.90+a
NOTE: HAZARDOUS WASTE PREMIUM $2.50
TUNNEL WORK $1.00
FOOTNOTES: a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, provided the employee has worked the day before and the day after the holiday.
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Air hoist, all boom type equipment (100 ft. or less), all pan and carry-alls, archer hoist, asphalt roller asphalt spreader or paver, automatic fine grade machine (CMI and similar type), archer hoist, backhoe and pull hoe (tractor mounted and rubber mounted), back filling machine, belt place (CMI and similar), bending machine (pipe), bituminous spreader and mixer, black top plant (automated), black top plant (non-automated), blast or rotary drill (truck or track mounted), blower for burning brush, boiler (when used for power), boom trucks, boring machine, bulldozer, cableway cage hoist, caisson auger, central mix plant (and all concrete batching plants), cherry picker (over 5 tons), cherry picker (under 5 tons), chipping machine and chip spreader, concrete curb and gutter machines, concrete curing machine, concrete mixer (over 1/2
cu. yd.) concrete pavement spreaders and finishers, concrete paver, concrete pump, concrete saw (self-propelled), conveyor, core drill, crane, crusher, derrick operator, dragline, dredge, drill rig (tractor mounted), dual drum paver, electric pump used in conjunction with well point systems, elevating grader self-propelled or towed), elevator excavator (all purpose, hydraulcally operated) farm tractor with accessories, fine grade machine, forklift, front end loader, generator (10 outlets or more), gradall, grader, grout or gunite machine, head tower, hoist-one drum, hoisting engine, hydraulic boom, hydraulic hammer, (self propelled), hydraulic pipe jack machine (or similar type machine), hydraulic system pumps, hydro crane, hydro hammer (or similar type), industrial tractor, jersey spreader, kolman plant loader (and similar type loaders), locomotive, lubrication truck, maintenance engineer, maintenance lubrication unit or truck, mine hoist, mixr for stabilized base (self-propelled), monorail, motorized hydraulic pin puller, motorized hydraulic seeder mucking machine, mulching machine, multiple drum hoist (more than 1 drum in use), overhead crane, peine crane (or similar type), pile driver, plant engineer, pneumatic mixer, post hole digger, power boom, pump crete, push or snatch cat, quarry master or equivalent road widener, rock bit sharpener (all types), roller (all), rolling machin (pipe), rotomill, scoopmobile, shovel, side boom, skimmer, slip form paver (CMI and similar type, first and second operator), snorkel, strato-tower, stump chipping machine, tire truck and repair, towed roller, tractor drawn belt type grader/loader, tractor shovel, tractor with towed accessories, tractors (when using winch power), tractors, trencher, truck crane, tunnel shovel, tube finisher (CMI and similar type), vibratory compactor, vibro tamp, well drilling machine, well point, winch, winch truck with "A" frame.
GROUP 2: Aggregate bin, CMI and similar type concrete spreads, cement bin, chipping machine and chip spreader, compressors (4 or less), compressors: (any size, but subject to other provisions for compressors, dust collectors, generators, mechanical heaters, pumps, welding machines (four of any type or combination), concrete mixer (1/2 cu. yd. and under), fireman, form tamper, fuel truck, heating boiler (used for temprory heat), jeep trencher, power heaterman, power plant in excess of 10 K.W., pump (4" or over), revinius widener, stem cleaner, stump chipping machine, welding machine (1 machine over 300 amps or 2 or 3 machines regardless of amps).
GROUP 3: Crane with boom over 100 feet
GROUP 4: Crane with boom over 200 feet
GROUP 5: Crane with boom over 300 feet
GROUP 6: Master meachanic
IRON0006-015 05/01/2017
ERIE (Township of Grand Island)
Rates Fringes
IRONWORKER
Ironworker..................$ 30.05 26.15 Sheeter.....................$ 30.05 26.15
LABO0210-001 07/01/2016
BUILDING
Rates Fringes
Laborers:
GROUP 1....................$ 26.38 23.65
GROUP 2....................$ 26.55 23.65
GROUP 3....................$ 26.66 23.65
GROUP 4....................$ 27.13 23.65
GROUP 5....................$ 27.88 23.65
GROUP 6....................$ 28.38 23.65
LABORER BUILDING CLASSIFICATIONS
GROUP 1: Basic, boat safety man, flagman, tool room man, nurseryman demolition worker; top man; wrecker; IBC barriers except on structurers; guard rail. Asphalt shovelers, foundation laborers over 8' in depth, hod carriers, plaster tender, plaster scaffold builder, pneumatic gas, electric operator, including all forms of busters, jackhammers, chipping guns and steel burners.
GROUP 2: Mortar mixer, asphalt smoothers, pneumatic gas electric tool operator including all forms of busters, jackhammers, and chipping guns over 8' in depth.
GROUP 3: Worker on any swing scaffold, blaster, plumbing laborer, wagon driller, bottom (caisson or cofferdam), laser setter, asphalt rakers, asphalt screed man.
GROUP 4: Stone cutter, curb setter and flag layer.
GROUP 5: Asbestos removal, deleader.
GROUP 6: Hazardous waste worker.
PAIN0004-007 05/01/2017
Rates Fringes
GLAZIER..........................$ 26.50 20.57
PAIN0004-018 05/01/2017
(AREA NORTH OF WHITEHAVEN ROAD, GRAND ISLAND, NEW YORK)
Rates Fringes
Painters:
Lead Abatement..............$ 25.95 23.69 Painters....................$ 25.95 23.69 Spraying, Paperhangers, Sand Blasting, Swinging scaffold....................$ 25.95 23.69 Tapers......................$ 26.45 23.69
PAIN0004-024 05/01/2017
ENTIRE COUNTY, (Excluding area North of Whitehaven Road, Grand Island, New York)
Rates Fringes
Painters:
Brush & Roll................$ 25.95 23.69 Spray, Sandblasting, Swing Scaffold or any Hanged Rigging platform, Epoxy.....$ 25.95 23.69 Taping/Drywall..............$ 26.45 23.69
PLAS0009-001 04/01/2018
Rates Fringes
PLASTERER........................$ 29.65 19.74
PLAS0111-001 07/01/2017
Rates Fringes
CEMENT FINISHER..................$ 30.00 29.62
PLUM0022-008 05/01/2017
ERIE- All Townships in the County
Rates Fringes
PIPEFITTER
ZONE 1......................$ 34.85 24.30
ROOF0074-001 06/01/2017
ERIE COUNTY
Rates Fringes
Roofers:
Composition.................$ 28.00 21.42 Slate & Tile................$ 28.15 21.42
* SHEE0071-001 05/28/2018
ERIE COUNTY:
Rates Fringes
Sheet metal worker...............$ 34.38 24.39
TEAM0449-004 07/01/2017
ERIE COUNTY
Rates Fringes
Truck drivers: (Includes Single Axle Dump and Off-Highway Dump Trucks).........$ 32.16 8.45+a+b
Work on a hazardous waste site then additional $2.00 per hour.
Euclids add $0.25 to Journeyman Rate
FOOTNOTE: a. Health and Welfare $438.61 per week
b. Paid Holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day provided the employee has worked the working day before and after the holiday
TEAM0449-007 06/01/2017
ERIE COUNTY
Rates Fringes
Truck drivers: (Dump Truck Only, Excludes Single Axle Dump and Off-Highway Dump Trucks)..........................$ 20.25 3.46+a
FOOTNOTE: a. Paid Holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day provided the employee has worked the working day before and after the holiday
SUNY1999-001 06/18/1999
Rates Fringes
SPRINKLER FITTER.................$ 15.94 3.88
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
STATEMENT OF WORK 29 DEC 2017
REPLACE ROLLING STEEL DOOR ON BUILDING #3
US ARMY CORPS OF ENGINEERS (BUFFALO DISTRICT)
1776 NIAGARA STREET
BUFFALO NY 14207-3199
The Contractor will provide all plant, labor, equipment, materials, freight and supervision to remove existing rolling steel door, guide assembly, hood and all associated parts.
Supply and install new custom size(11’ 11-3/4” X 14’ 1”) right hand drive, 20 gauge galvanized interior mount rolling steel door with 3” flat slats, new guide assembly, hood, weather seals and gray final coat. Contractor to field verify all measurements.
INTERFERENCE WITH BUSINESS:
A. Normal duty hours for work shall be from 7:00 a.m. to 3:00 p.m., Monday through Friday. Requests for additional work shall require written approval from the Contracting Officer 7 days in advance of the proposed work period.
B. The contractor shall furnish sufficient personnel to perform the work specified. The employees shall conduct themselves in a proper and productive manner at all times and shall not loiter. The employees shall be required by the contractor to maintain themselves and their clothing in a neat and clean manner. The contractor shall not employ those persons whose presence would violate Standards Of Conduct, DOD 5500.7-R (DOD Joint Ethics). The contractor shall not knowingly allow any employee who is under the influence of alcohol, drugs, or other incapacitating agents to perform work under this contract.
QUALITY ASSURANCE:
A. The contractor shall provide for the safe, careful and efficient operations of all tools and equipment. All tools and equipment shall be in good operating condition and be calibrated, when required.
B. All employees shall possess required licenses/certificates as required by federal, state, and local authorities.
PROCUREMENT:
Contractor shall be responsible for controlling procurement sources and those of his subcontractors to ensure that each purchase meets quality requirements.
GOVERNMENT FURNISHED PROPERTY AND SERVICES:
The Government will not provide any facilities, materials, equipment, supplies to the contractor.
CONTRACTOR FURNISHED ITEMS:
A. The contractor shall supply all equipment, tools, maintenance products, etc.
necessary to perform the tasks, as specified.
B. All equipment must be in good working condition.
C. All equipment, tools, maintenance products, etc. used by the contractor shall be in compliance with OSHA, EPA and other DOD Directives.
SPECIFIC TASKS:
A. Safely disconnect existing rolling steel door from existing motor assembly.
B. Remove existing rolling steel door on building #3 with all associated hardware, guide assembly and hood.
C. Supply and install new guide assembly.
D. Supply and install custom size right hand drive, 20 gauge galvanized interior mount rolling steel door with hood, 3” flat slats, weather seals and gray final coat.
E. Reconnect new door to existing motor assembly.
F. Test for proper operation and adjust as necessary.
G. There are no provisions for modifications or additions to the existing enclosure.
WARRANTIES. The manufacturer of the door shall issue a manufacturer’s warranty as follows:
a. One (1) year warranty covering workmanship and all materials provided covering repair and/or replacement of the components as necessary to correct defects in materials or workmanship.
b. Additionally, the Contractor shall issue a warranty for a minimum of two (2) years for workmanship and quality over all work performed under this contract.
c. All materials, supplies, components or articles required for the work shall be standard products of reputable manufacturers and entirely suitable for the purpose intended. They shall be new and unused, unless otherwise specified, and will be subject to the approval of the Contracting Officer or his designated official (COR).
COMPLETION OF WORK. All physical work required by this contract shall be completed within thirty (30) days after Notice To Proceed is given by the Contracting
Officer. Copies of the warranty provided to the Government.
NOTES, GENERAL:
1. The door shall be installed including related components, without impairing the structural integrity or damaging the existing building (Bldg 3) and structure. The proposed installation shall be in a professional workmanlike manner.
2. The Contractor shall assume all risks in connection with performance and delivery of the work and shall be liable for and hold the Government harmless from any and all damages to persons and properties.
3. All measurements must be field verified by contractor.
SAFETY REQUIREMENTS:
The Contractor shall follow all Safety Requirements detailed in the Unified Facilities
Guide Specifications (USACE UFGS 01-35-26, August 2009) and applicable Safety &
Health Requirements Manual per EM 385-1-1.
EM 385-1-1 is available on-line at: http://www.usace.army.mil/CESO/Pages/EM 385-1-
1, 2008NEW!.aspx
The project cannot proceed until all safety submittals required under this contract have been reviewed and approved by the Buffalo District Safety Office.
Preconstruction Submittals Abbreviated Accident Prevention Plan (APP)
Abbreviated APP Checklist (Attached)
Activity Hazard Analysis (AHA)
Proof of qualifications for Competent Persons/Site Safety and Health Officer(s)
(SSHO); to include copy of the 30 hour OSHA construction safety class completion certificate, resume of experience, documentation of 24 hour/year formal safety training.
http://www.usace.army.mil/CESO/Pages/EM%20385-1-1 http://www.usace.army.mil/CESO/Pages/EM%20385-1-1
Submit reports as required Accident reports via Eng Form 3394 Accident Investigation Report
Monthly Man-Hour Exposure Reports by the 5th day of each month
All contractor accidents, involving injuries or property damage, occurring during the execution of this contract shall be reported to USACE within 4 hours of the contractor becoming aware of its occurrence. Notification will include contractor name; contract title; type of contract; name of activity; installation or location where accident occurred;
date and time of accident; names of personnel injured; extent of property damage, if any;
extent of injury, if known, and brief description of accident (to include type of construction equipment used, PPE used, etc.). The USACE initial contact must be made personally (Telephone or email messages only are not acceptable).
Work shall not begin until the Abbreviated APP has been submitted to, and accepted by, the USACE Buffalo District Safety Office (DSO). In the Abbreviated APP, the
Contractor shall avoid providing material of a general nature not specifically related to this project or site. Previous versions of existing off-the-shelf APP are not acceptable.
The Abbreviated APP shall be prepared following the format found in USACE publication U.S. Army Corps of Engineers (USACE) Safety and Health Requirements
Manual ER 385-1-1, Appendix A. The following documents shall be considered in the preparation of the Abbreviated APP:
USACE EM 385-1-1 (15 Sep 08) Safety and Health Requirements Manual
USGS-01 35 26 (August 2009) Governmental Safety Requirements
USDOL OSHA 29 CFR 1926 Safety and Health Regulations for Construction
USDOL OSHA 29 CFE 1910 General Industry Safety and Health Standards
GENERAL SAFETY REQUIREMENTS:
A. Contractor shall take safety and health measures in performing work under this contract. Contractor is subject to applicable federal, state, and local laws, regulations, ordinances, codes, and orders relating to safety and health.
B. During the performance of work, the contractor shall comply with procedures prescribed for control and safety of persons visiting the site. Contractor is responsible for his personnel and for familiarizing each of his subcontractors with safety requirements. Contractor shall advise the Contracting Officer of any special safety restriction he has established so that Government personnel can be notified of these restrictions. The contractor shall permit safety inspections of all work being performed.
C. All waste materials generated by contractor operations shall be promptly removed from site. No on-site disposal will be allowed. Waste material generated by the contractor during the life cycle of the project shall be legally disposed of in public or private disposal facilities off-site at no additional cost to the government.
D. The contractor shall not use photo/video equipment during the execution of this project unless prior permission to do so has been obtained from the government.
A safety briefing will be conducted by the contractor prior to the start of work. The focus of the briefing will be on accident reporting procedures, emergency response, working around hazardous energy sources, personal protective equipment and any other subjects deemed appropriate by the contractor.
POINT OF CONTACT
For scheduling site visits and questions on Scope Of Work and/or contract: U.S. Army
Corps of Engineers, Buffalo District Contracting Officer, Mrs. Dorothy J. Jones, 1776
Niagara Street, Buffalo, New York 14207.
Phone: 716.879.4253 FAX: 716.879.4353
SUBMITTALS
Submittals (One) shall be submitted to: U.S. Army Corps of Engineers, Buffalo District
Office, Mrs. Dorothy J. Jones, 1776 Niagara Street, Buffalo, New York 14207.
Phone: 716.879.4253 FAX: 716.879.4353
List of Submittals:
Proposed complete work schedule identifying significant tasks and dates, submittal schedule and on-site work schedule. Work Plan to include hours of work, work sequence, Quality Control, and daily housekeeping.
Product data sheets, including warrantee information and listing of industry standards that the products meet.
All safety requirements per EM 385-1-1.
Emergency contact list.