Amendment_2.pdf
PDF 335 KB Posted
- Attached to
- East & West Arrowhead Breakwater Rehabilitation
- Solicitation number
- W912P4-14-B-0003
About this file
Please see attachment with amendment 2.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| EAST_AND_WEST_ARROWHEAD_BRKWTR_REPAIR-CLEV_HRBR_CPLT.pdf | ||
| Amendment_4_23Apr14.pdf | ||
| Amendment_3_22Apr14.pdf | ||
| Amendment_1_15Apr14.pdf | ||
| Teleconference_Information_26Mar14.docx | DOCX document | |
| Solicitation_11Mar14.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EAST AND WEST ARROWHEAD BREAKWATER REPAIR - CLEVELAND HARBOR
CLEVELAND, OHIO
STONE RUBBLEMOUND
CONSTRUCTION SOLICITATION/CONTRACT FORM (1442) AND BIDDING SCHEDULE
SECTION 00010
SCHEDULE A
Bid on Bidding Schedule will be based upon repairing a portion of the East and West Arrowhead Breakwater in Cleveland, Ohio. Bid shall include all required types/sizes of stone indicated on the contract drawings.
Duration for Base Bid is 180 calendar days – See section 01 35 13, Paragraph 1.2.1 Commencement (Schedule A) .
ITEM
No.
ESTIMATED
DESCRIPTION QUANTITY
UNIT
PRICE
AMOUNT
Mobilization & Demobilization
LS
Record (As-Built) Drawings
East Arrowhead Breakwater Repair of approximately 880 feet of breakwater (As shown on the contract drawings) a Bedding Stone 1,708 TN $_______ $ b Underlayer Stone 3,434 TN $_______ $ c Armor Stone 25,472 TN $_______ $
Total Estimated Amount (Items 1 ~ 3) $
“OPTION 1”
4 West Arrowhead Breakwater Repair of approximately 150 feet of breakwater a Bedding Stone 128 TN $ $ b
Underlayer Stone
TN
c
Armor Stone
3,158
Total Estimated Amount of Option 1 $ ___
(CONT.)
PRICE
“OPTION 2”
5 East Arrowhead Breakwater Repair of approximately 175 feet of breakwater a Bedding Stone 320 TN $ $
4,606
Total Estimated Amount of Option 2 $ ___
“OPTION 3”
6 East Arrowhead Breakwater a Bedding Stone 195 TN $ $
3,442
Total Estimated Amount of Option 3 $ _
Total Estimated Amount of All Line Items (Items 1 ~ 6) $
NOTE 1: BIDDERS ARE REQUIRED TO PROPOSE TO "SCHEDULE A" AND "SCHEDULE B". THE
GOVERNMENT RESERVES THE RIGHT TO MAKE AWARD TO THE LOWEST BIDDER (BASE +
OPTIONS) ON "SCHEDULE A" OR "SCHEDULE B". THE CONTRACTING OFFICER WILL
DETERMINE AN OFFER UNRESPONSIVE FOR FAILURE TO BID ON BOTH SCHEDULES.
NOTE 2: FOR BID EVALUATION PURPOSES, THE TOTAL BID WILL BE BASED UPON THE BASE
BID AMOUNT SHOWN ABOVE (ITEMS 1 THROUGH 3) AND THE TOTAL OF THE OPTIONS (ITEMS
4,5, & 6) SHOWN ABOVE. WITH REGARD TO THE OPTIONS ON SCHEDULE A AND SCHEDULE B -
EACH SCHEDULE WILL BE EVALUATED INDIVIDUALLY AND NO COMBINATION OF
SCHEDULES SHALL BE PERMITTED.
NOTE 3: REGARDING OPTION ITEMS, THE GOVERNMENT MAY ELECT TO AWARD ANY
COMBINATION OF OPTION ITEMS OR NONE OF THE OPTION ITEMS. IF ANY OF THE OPTION
ITEMS ARE AWARDED, THE GOVERNMENT RESERVES THE RIGHT TO LIMIT THE QUANTITY OF
MATERIAL UP TO THE ESTIMATED QUANTITY OF EACH OPTION ITEM. IF OPTIONS ARE
AWARDED, THEY WILL BE AWARDED WITHIN SIXTY (60) DAYS OF THE CONTRACT AWARD.
SCHEDULE B
Bid on Bidding Schedule will be based upon repairing a portion of the East and West Arrowhead Breakwater in Cleveland, Ohio. Bid shall include all required types/sizes of stone indicated on the contract drawings.
Duration for Base Bid is 447 calendar days – See section 01 35 13, Paragraph 1.2.2 Commencement (Schedule B) .
PRICE
Mobilization & Demobilization
Record (As-Built) Drawings
East Arrowhead Breakwater Repair of approximately 880 feet of breakwater a Bedding Stone 1,708 TN $_______ $ b Underlayer Stone 3,434 TN $_______ $ c Armor Stone 25,472 TN $_______ $
Total Estimated Amount (Items 1 ~ 3) $
“OPTION 1”
4 West Arrowhead Breakwater Repair of approximately 150 feet of breakwater a Bedding Stone 128 TN $ $
3,158
Total Estimated Amount of Option 1 $ ___
PRICE
“OPTION 2”
5 East Arrowhead Breakwater a Bedding Stone 320 TN $ $
4,606
Total Estimated Amount of Option 2 $ ___
“OPTION 3”
6 East Arrowhead Breakwater a Bedding Stone 195 TN $ $
3,442
Total Estimated Amount of Option 3 $ _
Total Estimated Amount of All Line Items (Items 1 ~ 6) $
NOTE 1: BIDDERS ARE REQUIRED TO PROPOSE TO "SCHEDULE A" AND "SCHEDULE B". THE
GOVERNMENT RESERVES THE RIGHT TO MAKE AWARD TO THE LOWEST BIDDER (BASE +
OPTIONS) ON "SCHEDULE A" OR "SCHEDULE B". THE CONTRACTING OFFICER WILL
DETERMINE AN OFFER UNRESPONSIVE FOR FAILURE TO BID ON BOTH SCHEDULES.
NOTE 2: FOR BID EVALUATION PURPOSES, THE TOTAL BID WILL BE BASED UPON THE BASE
BID AMOUNT SHOWN ABOVE (ITEMS 1 THROUGH 3) AND THE TOTAL OF THE OPTIONS (ITEMS
4,5, & 6) SHOWN ABOVE. WITH REGARD TO THE OPTIONS ON SCHEDULE A AND SCHEDULE B -
EACH SCHEDULE WILL BE EVALUATED INDIVIDUALLY AND NO COMBINATION OF
SCHEDULES SHALL BE PERMITTED.
NOTE 3: REGARDING OPTION ITEMS, THE GOVERNMENT MAY ELECT TO AWARD ANY
COMBINATION OF OPTION ITEMS OR NONE OF THE OPTION ITEMS. IF ANY OF THE OPTION
ITEMS ARE AWARDED, THE GOVERNMENT RESERVES THE RIGHT TO LIMIT THE QUANTITY OF
MATERIAL UP TO THE ESTIMATED QUANTITY OF EACH OPTION ITEM. IF OPTIONS ARE
AWARDED, THEY WILL BE AWARDED WITHIN SIXTY (60) DAYS OF THE CONTRACT AWARD.
W912P4-14-B-0003
CLEVELAND HARBOR
EAST & WEST ARROWHEAD BREAKWATER
REHABILITATION
CLEVELAND, OH
AMENDMENT NO . н
Replace Section 01 35 13
1с APRIL 2014
FY14 CLEV. EAST/WEST ARROWHEAD REPAIR Certified Final - RTA
FY14CLVARROWSPW AMENDMENT NO. 2 W912P4-14-B-0003
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 13
SPECIAL PROJECT PROCEDURES
07/06
PART 1 GENERAL
1.1 SUBMITTALS
1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
1.2.1 Commencement (Schedule A)
1.2.2 Commencement (Schedule B)
1.2.3 Schedule of Work
1.2.4 Certificate of Insurance
1.2.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.2.6 Contract Accruals
1.2.7 PROJECT/SITE CONDITIONS
1.2.7.1 Condition and Use of Project Site
1.2.7.2 Physical Conditions
1.2.7.3 Existing Structures, Equipment, Utilities & Improvements
1.2.7.4 Use of Local Roads
1.2.7.5 Plan of Operations
1.2.7.6 Datums and Control
1.2.7.7 Damage To Work
1.2.7.8 Restoration
1.2.7.9 Notifications
1.2.8 Waterways Navigation, Traffic and Notice to Mariners
1.2.9 Navigation
1.2.10 Temporary Lights, Signals and Buoys Required by the Coast Guard
PART 2 PRODUCTS
2.1 Stone Sources
PART 3 EXECUTION
3.1 CONTRACTOR RESPONSIBILITIES
3.2 LAYOUT OF WORK
3.3 Construction Procedure
-- End of Section Table of Contents --
SECTION 01 35 13 Page 1028
REPLACEMENT PAGES 04/16/14
SECTION 01 35 13
SPECIAL PROJECT PROCEDURES
07/06
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Stone Sources; G, DC
Schedule of Work; G, AOF
Contractor shall submit a complete Schedule of Work.
Certificate of Insurance; G, AOF
Plan of Operations; G, AOF
Contractor shall submit an overall plan of operations for all phases of work.
SD-07, Certificates
Notice to Mariners; G, AOF
Certificate of Insurance; G, AOF
Notifications; G, AOF
Submit notification contacts, including date, time and individual contacted.
1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
Each Bidding Schedule (Schedule A and Schedule B) has a separate 'Commencement' sub-paragraph. The Contractor shall structure its bid on each schedule to correspond to the applicable sub-paragraph.
1.2.1 Commencement (Schedule A)
The Contractor shall be required to commence work under this contract within ten (10) calendar days after the date of receipt by the Contractor of the Notice to Proceed to prosecute said work diligently, and to complete the base bid work not later than one hundred eighty (180) calendar days from the date of receipt by the Contractor of the Notice to Proceed.
Additional time will be allowed for each option awarded and is shown below.
Of this one hundred eighty (180) day performance period, thirty (30) days have been allocated for submittal review and approval. The time stated for
SECTION 01 35 13 Page 1029 completion shall include final clean-up of the premises. The Contractor shall comply with the milestone schedule below.
Milestone Maximum Calendar Days After Receipt of Notice to Proceed
Commence Work (Submittals, Administration, etc.) 10
Commence Actual On-site Operations (see "B" below) 40
Complete Base Bid Work 180
Complete Option 1 Work (additional days) 20
Complete Option 2 Work (additional days) 20
Complete Option 3 Work (additional days) 20
240 Total Days
A. The Notice to Proceed will be issued on or about 9 May 2014.
B. The "Maximum Calendar Days After Receipt of Notice to Proceed" includes a period of 23 days from 9 May 2014 through 31 May 2014 when no in-water work shall be permitted.
C. The Contractor is advised that no work will be permitted from 26 August 2014 through 1 September 2014 due the Cleveland National Air Show. Contractor shall contact Air Show personel to verify dates and restrictions (Mr. Dan Biggs Tel: 216-781-0747, Cell 216-224-7442). All schedules by the contractor shall include this "No Work" period and shall not be used for the purpose of obtaining a time extension to complete the work.
C. The work shall be performed in the following order:
1. Base Bid
2. Option 1
3. Option 2
4. Option 3
1.2.2 Commencement (Schedule B)
The Contractor shall be required to commence work under this contract within ten (10) calendar days after the date of receipt by the Contractor of the Notice to Proceed to prosecute said work diligently, and to complete the base bid work not later than four hundred forty-seven (447) calendar days from the date of receipt by the Contractor of the Notice to Proceed.
Additional time will be allowed for each option awarded and is shown below.
Of this four hundred forty-seven (447) day performance period, thirty (30) days have been allocated for submittal review and approval. The time stated for completion shall include final clean-up of the premises. The Contractor shall comply with the milestone schedule below.
Milestone Maximum Calendar Days After Receipt of Notice to Proceed
SECTION 01 35 13 Page 1030
Commence Work (Submittals, Administration, etc.) 10
Commence Actual On-site Operations (see "B" below) 40
Complete Base Bid Work 447
Complete Option 1 Work (additional days) 20
Complete Option 2 Work (additional days) 20
Complete Option 3 Work (additional days) 20
507 Total Days
A. The Notice to Proceed will be issued on or about 9 May 2014.
B. The "Maximum Calendar Days After Receipt of Notice to Proceed includes one optional non-work periods of 121 days (1 December 2014 through 31 March 2015). During the optional non-work periods, the contractor may work at their own discretion, however, weather delays occurring during those time periods shall not be including for determining time extensions as stated in paragraph 1.2.4 "TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER". It also includes two periods when no in-water work shall be permitted: 23 days from 9 May 2014 through 31 May 2014 and 77 days from 15 April 2015 through 30 June 2015.
C. The Contractor is advised that no work will be permitted from 26 August 2014 through 1 September 2014 due the Cleveland National Air Show. Contractor shall contact Air Show personel to verify dates and restrictions (Mr. Dan Biggs Tel: 216-781-0747, Cell 216-224-7442). All schedules by the contractor shall include this "No Work" period and shall not be used for the purpose of obtaining a time extension to complete the work. The dates for the 2015 Air Show have not been set, although the Contractor should account for a similar period of no work as that prescribed for 2014. Contact the local authorities for exact dates for all shows.
(http://www.clevelandairshow.com/)
D. If the contractor decides not to work during the optional non-work period, it is the contractors responsibility to secure the work completed up to the stoppage of work, from damage, during the non-work period. Any repairs needed, and/or additional stone needed, to fix damage due to contractor neglect or deficient work, shall be at the contractors expense and shall not be used to determining time extensions as stated in paragraph 1.2.4 "TIME EXTENSIONS FOR UNUSUALLY
SEVERE WEATHER".
E. The work shall be performed in the following order:
1. Base Bid
2. Option 1
3. Option 2
4. Option 3
SECTION 01 35 13 Page 1031
1.2.3 Schedule of Work
The Contractor shall submit a complete schedule of work covering the period of time from the Notice of Award through the specified duration of the contract to the Contracting Officer within ten (10) calendar days of receipt of the Notice of Award.
1.2.4 Certificate of Insurance
The Contractor shall submit a Certificate of Insurance within ten (10) calendar days of receipt of the Notice of Award.
1.2.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1. This provision specifies the procedures for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.
2. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
14 9 7 5 6 6 4 4 6 6 6 9
3. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph 2, above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction)".
SECTION 01 35 13 Page 1032
1.2.6 Contract Accruals
The Contractor shall submit a monthly listing of accruals. Accruals are used to provide projections of the incremental costs not yet paid for, but earned. The accrual submittal shall be made one week before the end of each month throughout the contract duration. The accrual information shall be provided for each line item of the Bidding Schedule.
1.2.7 PROJECT/SITE CONDITIONS
1.2.7.1 Condition and Use of Project Site
The drawings indicate elevations and the reference drawings indicate the latest elevations at the project site. A notification of at least five (5) calendar days shall be given to the Contracting Officer prior to bringing any equipment or material to the work site. The Contractor shall be responsible for damages that may be suffered due to his operations. The Contractor shall note Clause entitled "Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements."
1.2.7.2 Physical Conditions
The physical conditions shown on the drawings are indicative of those that prevailed at the time of the site investigations and may be different than those at the time of construction.
1.2.7.3 Existing Structures, Equipment, Utilities & Improvements
General locations of applicable existing utilities, vegetation, structures, equipment and improvements, based upon latest information available to the Government have been shown on the drawings. However, it is the responsibility of the Contractor to establish the exact horizontal and vertical location and size of all existing utility lines which are located within the required work area. The Contractor shall confer with the owners of the crossings regarding their exact locations and elevations and will be held responsible for any damages done to them by the construction operations. If the Contractor damages any existing utility line, vegetation, structure, equipment or improvement, a report thereof shall be made immediately to the Contracting Officer. In any event, existing utility lines, vegetation, structures, equipment or improvements shall be protected from damage, and if damaged, shall be repaired by the Contractor at his own expense.
1.2.7.4 Use of Local Roads
The Contractor will be responsible for making all arrangements (including approval of routes to be used and permits required) with all local Government officials or owners for use of public and private roads and streets for the operations, and shall conform to all requirements regarding such use. All costs in connection therewith, including any repairs, shall be borne by the Contractor.
1.2.7.5 Plan of Operations
The work shall be performed in accordance with an approved plan of operations submitted by the Contractor. Work schedules shall be included in the plan, and the Contracting Officer shall be notified at least 48 hours in advance of changes in work schedules. The plan shall provide for the coordination of construction activities indicated in the specifications and
SECTION 01 35 13 Page 1033 shown on the contract drawings.
1.2.7.6 Datums and Control
The vertical plane of reference is the Low Water Datum (L.W.D.) for Lake Erie, which is 569.2 feet above mean sea level at Rimouski, Quebec (International Great Lakes Datum of 1985 (IGLD85)). The horizontal datum shall be North American Datum of 1983 (NAD83), Ohio State Plane Coordinate System, North Zone. Horizontal and vertical control to be utilized for work performed by the contractor are shown on the contract drawings.
1.2.7.7 Damage To Work
The responsibility for damage to any part of the permanent work shall be as set forth in the clause of the contract entitled "Permits and Responsibilities." However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor will make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are not contract unit or lump sum prices applicable to any part of such work an equitable adjustment pursuant to the Contact Clause entitled "Changes" of the contract, will be made as full compensation for the repairs of the part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided damage to all work (including temporary construction, utilities, materials, equipment and plant) shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense regardless of the cause of such damage.
1.2.7.8 Restoration
Areas within the required work areas which are damaged by the Contractor's operations shall be restored in accordance with the requirements of the applicable section of the specifications.
1.2.7.9 Notifications
Within five (5) days of completing the notifications required under this contract, the Contractor shall submit to the Contracting Officer, written verification of these notifications, including the date, time and the name of the point of contact with whom correspondence occurred. These notifications shall be sent to:
Cleveland Area Office 1035 East 9th Street Cleveland, OH, 44114 Telephone: 216-685-1205
a. The Contractor is advised that no work will be permitted from 27 August 2014 through 3 September 2014 due the Cleveland Air Show. These dates are approximate. Contact the local authorities for exact dates.
(http://www.clevelandairshow.com/) All schedules by the contractor shall include this "No Work" period and shall not be used for the purpose of obtaining a time extension to complete the work.
SECTION 01 35 13 Page 1034
1.2.8 Waterways Navigation, Traffic and Notice to Mariners
There is a heavy amount of traffic in Cleveland Harbor consisting of fishing boats, recreational boats, tugs, barges, and all classes of lake vessels varying in length to a maximum of 1,000 feet. The Contractor shall acquaint himself with all information and regulations pertaining to navigation & vessel traffic within the waterways and shall coordinate with the U.S. Coast Guard Offices indicated in paragraph entitled "Notifications" of the Section, to assure that a "NOTICE TO MARINERS" is issued prior to his work activity at the project site. A copy of the requisite notice form is an attachment to this solicitation. The completed form shall arrive at the address (shown on the form) no less than two (2) weeks prior to the start of work activity at the project site. The Government will not undertake to keep the waterways free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917 (see Title 33 U.S.C.A. Sec. 1). The Contractor is further required to conduct his work in such a manner as to obstruct navigation as little as possible and, in case, the Contractor's plant so obstructs a channel as to make it difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford practicable passage. Upon completion of the work, the Contractor shall promptly remove his plant, including ranges, buoys, piles, and other marks placed by him under the contract in navigable waters or on shore.
1.2.9 Navigation
The work site is considered to be not sheltered and subject to wave action form lake storms. Information and regulations pertaining to navigation may be obtained from the current issue of the "United States Coast Pilot 6", issued annually by the U.S. Department of Commerce, National Oceanic and Atmospheric Administration (NOAA). The "United States Coast Pilot 6" may be obtained from National Ocean Survey, NOAA, Distribution Division-C44, Riverside, Maryland 20840.
1.2.10 Temporary Lights, Signals and Buoys Required by the Coast Guard
All temporary lights, signals and buoys required by the U.S. Coast Guard must be displayed during the project work. Information regarding required signals, lights, buoys and other requirements may be obtained from the Commander OAN), U.S. Coast Guard, Shore Maintenance Detachment, ATTENTION:
Aids to Navigation Branch, 1240 East Ninth Street, Cleveland, Ohio 44199-2060, Telephone (216) 522-3990.
PART 2 PRODUCTS
2.1 Stone Sources
For each type of stone material it proposes to furnish, the Contractor shall, within 10 days after receipt of the "Notice to Proceed," designate in writing one source or one (1) combination of sources. Submit information including: (1) areas and lifts of the quarry or pit to be worked, (2) the specific geological strata or stratas to be utilized, (3) available laboratory testing records, (4) bulk specific gravity range, and
(5) previous use records. If a proposed source is disapproved, submit the required data for a replacement source. The following listed stone sources
SECTION 01 35 13 Page 1035 have been inspected and tested and/or have previously furnished materials that meet the quality requirements stipulated in the specifications. Each source shown contained, at the time of inspection and testing and/or previous use, suitable in-place stone from which the specified material quality and type could be or was produced. More detailed information for each of the listed stone sources is available for inspection by the Contractor in the Coastal/Geotechnical Section, Department of the Army, United States Army Engineer District, Buffalo, 1776 Niagara Street, Buffalo, New York 14207-3199. The project materials are listed in the following table:
Type Material Size Range
A Armor Stone 4.1 ton - 9.0 ton B Underlayer Stone 540 lbs. - 1800 lbs.
C Bedding Stone ODOT Type "D"
1. Hanson Aggregates, 3945 Centennial Road, Sylvania, OH 43560; (419) 841-3014; rock formation, Niagaran limestone; listed for Type A, B and C stone production. Specific gravity: 2.61. Inspected by the Buffalo District in May 1993 and tested for stone use by the Ohio River Division Laboratory in August 1993.
2. LaFarge North America, Marblehead Stone Division, 522 Limestone Drive, Marblehead, OH 44131; (419) 798-4486; quarry at Marblehead, OH;
rock formations: Columbus limestone, Lucas and Amherstberg dolomites;
listed for Types A, B, and C stone production. Specific gravity: 2.58.
Inspected by the Buffalo District in July 2005 and tested for stone use by Ohio River Division Laboratory in July 1991.
3. Johnson Sandstone Products Inc., 202 State Street, Box 39, Kipton, OH 44049-0039; (440) 775-1913; quarry at Kipton, OH; rock formation: Berea andstone;listed for Type A, B and C stone production. Specific gravity:
2.24. Inspected by the Buffalo District in November 1995 and tested for stone use by Ohio River Division Laboratory in 1996.
4. Cleveland Quarry Ltd., P.O. Box 261, Amherst, OH 44011; (216) 986-4501; quarries at South Amherst, OH; rock formation: Berea sandstone; listed for Type A, B and C stone production; Specific gravity: 2.24. Inspected by the Buffalo District in May 1991 and tested for stone use by Ohio River Division Laboratory in 1875.
5. Wagner Quarries Co., 4203 Milan Road, Sandusky, OH 44870; (419) 625-8141; rock formation: similar to the Amherstberg member of the Detroit River group. Specific gravity: 2.41. Inspected by the Buffalo District in July 2001 and tested for stone use in September 2001.
6. Sandusky Crushed Stone, 9220 Portland Road, Castalia, OH 44824;
(419) 483-4390; rock formation: Delaware Group limestone and Columbus Formation dolomite and dolomitic limestone; listed for Type A, B, and C stone production. Specific gravity: 2.71. Inspected by the Buffalo District in August 1990 and tested for stone use by Ohio River Division Laboratory in June 1992.
SECTION 01 35 13 Page 1036
PART 3 EXECUTION
3.1 CONTRACTOR RESPONSIBILITIES
Transportation for Inspectors - The Contractor will be required to furnish, on the request of the Contracting Officer or any inspector, suitable transportation from all points on shore designated by the Contracting Officer to and from the various pieces of plant, and to and from the various parts of the work. Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting Officer, and the cost thereof will be deducted from any amounts due or to become due the Contractor.
The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to:
(1) conditions bearing upon transportation, disposal, handling, and storage of materials;
(2) the availability of labor, water, electric power, and roads;
(3) uncertainties of weather, river stages, tides, or similar physical conditions at the site;
(4) the character of equipment and facilities needed preliminary to and during work performance.
The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
3.2 LAYOUT OF WORK
The Government has established bench marks and horizontal control points at the site of the work. These are described and indicated on contract drawings.
From these control points the contractor shall lay out the work by establishing all lines and grades at the site necessary to control the work and shall be responsible for all measurements that may be required for the execution of the work to the location and limit marks prescribed in the specifications or on the contract drawings. The Contractor shall establish
SECTION 01 35 13 Page 1037 and maintain at the site of the work any horizontal and vertical controls shown on the contract drawings.
The Contractor shall furnish, at his own expense, all such stakes, spikes, steel pins, templates, platforms, equipment, tools and material and all labor as may be required in laying out any part of the work from the control points established by the Government. It shall be the responsibility of the contractor to maintain and preserve all stakes and other markers established by him until authorized to remove them. If any of the control points established at the site by the Government are destroyed by or through the negligence of the Contractor prior to their authorized removal, they may be replaced by the Contracting Officer, and the expense of replacement will be deducted from any amount due or which may become due the Contractor. The Contracting Officer may require that work be suspended at any time when horizontal and vertical control points established at the site by the Contractor are not reasonably adequate to permit checking the work. Such suspension will be withdrawn upon proper replacement of the control points.
3.3 Construction Procedure
The plan for repair of the East and West Arrowhead Breakeate is typical for a rubble mound stone structure. The order of the work is as follows:
A. Place and grade the bedding stone – Type “C” stone.
B. Place and grade the under layer stone – Type “B” stone on the bedding stone to the depth specified on the contract drawings. Note that the entire berm must be constructed prior to any construction above its top elevation to insure adequate slope stability.
C. The cover layer which is composed of Type “A” stone is to be constructed last by placing each unit individually in a random manner starting at the base of the slope and working toward the top. The cover layer shall be placed in a nominal two-layer thickness.
Construction practices for placement and quality of materials will follow those marine procedures normally found acceptable by the U.S. Army Corps of Engineers.
-- End of Section --
SECTION 01 35 13 Page 1038
| FY14 CLV ARROW REPAIRS W912P4-14-B-0003 - Amendment 2.pdf |
| 01 35 13.pdf |
| SPECIAL PROJECT PROCEDURES |
| 01 35 13 - SPECIAL PROJECT PROCEDURES |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK |
| 1.2.1 Commencment Schedule A |
| 1.2.2 Commencement Schedule B |
| 1.2.3 Schedule of Work |
| 1.2.4 Certificate of Insurance |
| 1.2.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER |
| 1.2.6 Contract Accruals |
| 1.2.7 PROJECT/SITE CONDITIONS |
| 1.2.7.1 Condition and Use of Project Site |
| 1.2.7.2 Physical Conditions |
| 1.2.7.3 Existing Structures, Equipment, Utilities & Improvements |
| 1.2.7.4 Use of Local Roads |
| 1.2.7.5 Plan of Operations |
| 1.2.7.6 Datums and Control |
| 1.2.7.7 Damage To Work |
| 1.2.7.8 Restoration |
| 1.2.7.9 Notifications |
| 1.2.8 Waterways Navigation, Traffic and Notice to Mariners |
| 1.2.9 Navigation |
| 1.2.10 Temporary Lights, Signals and Buoys Required by the Coast Guard |
| PART 2 PRODUCTS |
| 2.1 Stone Sources |
| PART 3 EXECUTION |
| 3.1 CONTRACTOR RESPONSIBILITIES |
| 3.2 LAYOUT OF WORK |
| 3.3 Construction Procedure |
| 01 35 13.pdf |
| SPECIAL PROJECT PROCEDURES |
| 01 35 13 - SPECIAL PROJECT PROCEDURES |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK |
| 1.2.1 Commencement Schedule A |
| 1.2.2 Commencement Schedule B |
| 1.2.3 Schedule of Work |
| 1.2.4 Certificate of Insurance |
| 1.2.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER |
| 1.2.6 Contract Accruals |
| 1.2.7 PROJECT/SITE CONDITIONS |
| 1.2.7.1 Condition and Use of Project Site |
| 1.2.7.2 Physical Conditions |
| 1.2.7.3 Existing Structures, Equipment, Utilities & Improvements |
| 1.2.7.4 Use of Local Roads |
| 1.2.7.5 Plan of Operations |
| 1.2.7.6 Datums and Control |
| 1.2.7.7 Damage To Work |
| 1.2.7.8 Restoration |
| 1.2.7.9 Notifications |
| 1.2.8 Waterways Navigation, Traffic and Notice to Mariners |
| 1.2.9 Navigation |
| 1.2.10 Temporary Lights, Signals and Buoys Required by the Coast Guard |
| PART 2 PRODUCTS |
| 2.1 Stone Sources |
| PART 3 EXECUTION |
| 3.1 CONTRACTOR RESPONSIBILITIES |
| 3.2 LAYOUT OF WORK |
| 3.3 Construction Procedure |
| FY14 CLV ARROW REPAIRS W912P4-14-B-0003 - Amendment 2_16Apr14.pdf |
| 01 35 13.pdf |
| SPECIAL PROJECT PROCEDURES |
| 01 35 13 - SPECIAL PROJECT PROCEDURES |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK |
| 1.2.1 Commencment Schedule A |
| 1.2.2 Commencement Schedule B |
| 1.2.3 Schedule of Work |
| 1.2.4 Certificate of Insurance |
| 1.2.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER |
| 1.2.6 Contract Accruals |
| 1.2.7 PROJECT/SITE CONDITIONS |
| 1.2.7.1 Condition and Use of Project Site |
| 1.2.7.2 Physical Conditions |
| 1.2.7.3 Existing Structures, Equipment, Utilities & Improvements |
| 1.2.7.4 Use of Local Roads |
| 1.2.7.5 Plan of Operations |
| 1.2.7.6 Datums and Control |
| 1.2.7.7 Damage To Work |
| 1.2.7.8 Restoration |
| 1.2.7.9 Notifications |
| 1.2.8 Waterways Navigation, Traffic and Notice to Mariners |
| 1.2.9 Navigation |
| 1.2.10 Temporary Lights, Signals and Buoys Required by the Coast Guard |
| PART 2 PRODUCTS |
| 2.1 Stone Sources |
| PART 3 EXECUTION |
| 3.1 CONTRACTOR RESPONSIBILITIES |
| 3.2 LAYOUT OF WORK |
| 3.3 Construction Procedure |
| 01 35 13.pdf |
| SPECIAL PROJECT PROCEDURES |
| 01 35 13 - SPECIAL PROJECT PROCEDURES |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK |
| 1.2.1 Commencement Schedule A |
| 1.2.2 Commencement Schedule B |
| 1.2.3 Schedule of Work |
| 1.2.4 Certificate of Insurance |
| 1.2.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER |
| 1.2.6 Contract Accruals |
| 1.2.7 PROJECT/SITE CONDITIONS |
| 1.2.7.1 Condition and Use of Project Site |
| 1.2.7.2 Physical Conditions |
| 1.2.7.3 Existing Structures, Equipment, Utilities & Improvements |
| 1.2.7.4 Use of Local Roads |
| 1.2.7.5 Plan of Operations |
| 1.2.7.6 Datums and Control |
| 1.2.7.7 Damage To Work |
| 1.2.7.8 Restoration |
| 1.2.7.9 Notifications |
| 1.2.8 Waterways Navigation, Traffic and Notice to Mariners |
| 1.2.9 Navigation |
| 1.2.10 Temporary Lights, Signals and Buoys Required by the Coast Guard |
| PART 2 PRODUCTS |
| 2.1 Stone Sources |
| PART 3 EXECUTION |
| 3.1 CONTRACTOR RESPONSIBILITIES |
| 3.2 LAYOUT OF WORK |
| 3.3 Construction Procedure |