Bid Schedule

View the file

Other files

File Type Posted
FY11 - REVISED_C S BRL BUF - SOW 25 MAY 2011.pdf PDF
Wage_Determination.pdf PDF
FY11 - C S BRL BUF - SOW 24 MAY 2011.pdf PDF
Form 1442.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE

SNAG & CLEAR OF BLACK ROCK CHANNEL & LOCK, BUFFALO RIVER, & BUFFALO HARBOR WITH MISCELLANEOUS WORK Note: Contractor is not required to bid Item No. 4 (Optional), Relocation of Concrete Block or Stone; the price bid for this item will not be included in the selection criteria for this contract. All disposals are in Buffalo CDF4 at South Buffalo Harbor (except for tires, demolition debris, trash and other non-degradable items). Numbers of days are estimates and will be refined through individual pre-work tours. Optional items or days are on a per-day basis and the Government may choose to award any number of optional days in extension of the Base Items and the Mobilization/Demobilization period.

YEAR 1 (2011-2012), BASE/OPTION ITEM(S)

Item No.
Description
Bid Quantity
Bid Unit
Unit Price ($)
Price Extended ($)
1 (Base)
Mobilization/Demobilization
1
Lump Sum
2 (Base)
Snag and Clear Black Rock Channel and Lock, Buffalo River and Harbor
2
Day
3 (Option)
Snag and Clear Black Rock Channel and Lock, Buffalo River and Harbor
1
Day
4 (Option)
Relocation of Concrete Block or Stone
1
Lump Sum

TOTAL BID AMOUNT (Item No. 1-3):________________