Bid Abstract
W912LQ-10-B-0002
Issued: 6 July 10
Opened: 12 August 10
Issuing Office: VaARNG USPFO-AQS W912LQ
Project Title: Energy Upgrades
Number of Amendments Issued: 3
CLIN # Est Qty Unit Unit Price Extended Amount Unit Price Extended Amount Unit Price Extended Amount
0001 1 JB -$ -$ 558,994.00$ 558,994.00$ 398,891.16$ 398,891.16$
0002 1 JB -$ -$ 154,311.00$ 154,311.00$ 201,853.81$ 201,853.81$
0003 1 JB -$ -$ 89,211.00$ 89,211.00$ 126,185.48$ 126,185.48$
0004 1 JB -$ -$ 139,851.00$ 139,851.00$ 314,983.74$ 314,983.74$
0005 1 JB -$ -$ 141,388.00$ 141,388.00$ 314,983.74$ 314,983.74$
0006 1 JB -$ -$ 163,671.00$ 163,671.00$ 171,104.61$ 171,104.61$
0007 1 JB -$ -$ 355,081.00$ 355,081.00$ 846,998.08$ 846,998.08$
0008 1 JB -$ -$ 17,416.00$ 17,416.00$ 35,201.40$ 35,201.40$
0009 1 JB -$ -$ 73,446.00$ 73,446.00$ 85,127.27$ 85,127.27$
0010 1 JB -$ -$ 287,394.00$ 287,394.00$ 721,028.28$ 721,028.28$
0011 1 JB -$ -$ 329,000.00$ 329,000.00$ 737,316.36$ 737,316.36$
0012 100 BF -$ -$ 7.50$ 750.00$ 11.54$ 1,154.00$
0012 450 BF -$ -$ 7.50$ 3,375.00$ 11.54$ 5,193.00$
0012 50 BF -$ -$ 7.50$ 375.00$ 11.54$ 577.00$
0013 -$ 2,314,263.00$ 3,960,597.93$
0014 1 JB 750.00$ 750.00$ 235.32$ 235.32$ 208.26$ 208.26$
0015 1 JB 5,500.00$ 5,500.00$ 3,463.20$ 3,463.20$ 208.26$ 208.26$
0016 1 JB 750.00$ 750.00$ 235.32$ 235.32$ 2,704.48$ 2,704.48$
0017 1 JB 5,500.00$ 5,500.00$ 3,463.20$ 3,463.20$ 2,704.78$ 2,704.78$
0018 1 JB 2,500.00$ 2,500.00$ 3,856.88$ 3,856.88$ 5,059.02$ 5,059.02$
0019 1 JB 3,900.00$ 3,900.00$ 4,648.68$ 4,648.68$ 4,616.65$ 4,616.65$
0020 1 JB 17,700.00$ 17,700.00$ 18,659.84$ 18,659.84$ 12,908.63$ 12,908.63$
0021 1 JB 18,900.00$ 18,900.00$ 20,646.00$ 20,646.00$ 20,030.13$ 20,030.13$
0022 1 JB 24,800.00$ 24,800.00$ 20,848.76$ 20,848.76$ 20,109.90$ 20,109.90$
0023 1 JB 50,600.00$ 50,600.00$ 19,467.92$ 19,467.92$ 44,221.48$ 44,221.48$
0024 1 JB 9,500.00$ 9,500.00$ 18,985.44$ 18,985.44$ 19,816.92$ 19,816.92$
0025 1 JB 17,700.00$ 17,700.00$ 20,073.24$ 20,073.24$ 20,537.77$ 20,537.77$
0026 1 JB 14,000.00$ 14,000.00$ 7,515.44$ 7,515.44$ 8,590.77$ 8,590.77$
Lighting Facility T0218
Lighting Facility T0212
HVAC Bldg 218
Description of Item
HVAC Bldg 134
HVAC Bldg 147
HVAC Bldg 311
Lighting Facility 00001
Lighting Facility 00002
HVAC Bldg 1613
HVAC Bldg 2601
Lighting Facility T0229
Lighting Facility 00005
Lighting Facility DGIF1
Lighting Facility T0049
HVAC Bldg 1485
HVAC Bldg T0049
Lighting Facility T0222
Lighting Facility T0224
Lighting Facility T0216
BIDS
# _1__
Lighting Facility T0215
Lighting Facility 00003
HVAC Bldg 234
HVAC Bldg 472
HVAC Bldg 471
I certify that I have opened, read and recorded on this abstract all bids received in response to this solicitation.
Signature & Date:
Name & Title of Certifying Official:
Total 0001-0012
Bid Security: Y
Amendments Acknowledged: N
Bidder: Boykin, West Columbia, SC
Deteriorated Wood
Deteriorated Wood
Deteriorated Wood
Bidder: Iron Cross, Chester, VA
Bid Security: Y
Amendments Acknowledged: Y
# _2__ # _3__
Bidder: Trifecta, Annapolis Junction, MD
Bid Security: Y
Amendments Acknowledged: Y
Page ___ of ___
Issued: 6 July 10
Opened: 12 August 10
Issuing Office: VaARNG USPFO-AQS W912LQ
Project Title: Energy Upgrades
Number of Amendments Issued: 3
CLIN # Est Qty Unit Unit Price Extended Amount Unit Price Extended Amount Unit Price Extended Amount
0001 1 JB 484,497.00$ 484,497.00$ 68,046.00$ 68,046.00$ 593,230.00$ 593,230.00$
0002 1 JB 88,063.00$ 88,063.00$ 92,716.00$ 92,716.00$ 178,618.00$ 178,618.00$
0003 1 JB 172,359.00$ 172,359.00$ 51,636.00$ 51,636.00$ 133,808.00$ 133,808.00$
0004 1 JB 132,869.00$ 132,869.00$ 90,046.00$ 90,046.00$ 243,530.00$ 243,530.00$
0005 1 JB 142,895.00$ 142,895.00$ 105,078.00$ 105,078.00$ 250,280.00$ 250,280.00$
0006 1 JB 205,348.00$ 205,348.00$ 60,605.00$ 60,605.00$ 180,952.00$ 180,952.00$
0007 1 JB 271,963.00$ 271,963.00$ 326,804.00$ 326,804.00$ 253,630.00$ 253,630.00$
0008 1 JB 53,530.00$ 53,530.00$ 15,846.00$ 15,846.00$ 38,316.00$ 38,316.00$
0009 1 JB 52,352.00$ 52,352.00$ 38,643.00$ 38,643.00$ 173,770.00$ 173,770.00$
0010 1 JB 154,857.00$ 154,857.00$ 211,198.00$ 211,198.00$ 221,572.00$ 221,572.00$
0011 1 JB 197,487.00$ 197,487.00$ 148,924.00$ 148,924.00$ 164,317.00$ 164,317.00$
0012 100 BF 12.00$ 1,200.00$ 25.00$ 2,500.00$
0012 450 BF 10.00$ 4,500.00$ 25.00$ 11,250.00$
0012 50 BF 12.00$ 600.00$ 25.00$ 1,250.00$
0013 1,962,520.00$ 1,212,870.00$ 2,447,023.00$
0014 1 JB 2,410.00$ 2,410.00$ -$ -$ 332.00$ 332.00$
0015 1 JB 2,434.00$ 2,434.00$ -$ -$ 332.00$ 332.00$
0016 1 JB 4,084.00$ 4,084.00$ -$ -$ 2,828.00$ 2,828.00$
0017 1 JB 4,084.00$ 4,084.00$ -$ -$ 2,828.00$ 2,828.00$
0018 1 JB 5,109.00$ 5,109.00$ -$ -$ 3,677.00$ 3,677.00$
0019 1 JB 3,298.00$ 3,298.00$ -$ -$ 6,548.00$ 6,548.00$
0020 1 JB 18,797.00$ 18,797.00$ -$ -$ 12,807.00$ 12,807.00$
0021 1 JB 26,062.00$ 26,062.00$ -$ -$ 17,618.00$ 17,618.00$
0022 1 JB 29,106.00$ 29,106.00$ -$ -$ 17,500.00$ 17,500.00$
0023 1 JB 84,710.00$ 84,710.00$ -$ -$ 34,585.00$ 34,585.00$
0024 1 JB 20,706.00$ 20,706.00$ -$ -$ 57,011.00$ 57,011.00$
0025 1 JB 26,135.00$ 26,135.00$ -$ -$ 21,336.00$ 21,336.00$
0026 1 JB 27,643.00$ 27,643.00$ -$ -$ 6,754.00$ 6,754.00$
3,328.00$
Lighting Facility T0224
Lighting Facility T0049
Lighting Facility T0229
Lighting Facility T0222
Lighting Facility T0215
Lighting Facility 00005
Lighting Facility T0218
Lighting Facility T0212
Lighting Facility T0216
Lighting Facility DGIF1
Lighting Facility 00001
Deteriorated Wood
Lighting Facility 00003
Total 0001-0012
Lighting Facility 00002
Deteriorated Wood
HVAC Bldg T0049
Deteriorated Wood
HVAC Bldg 218
HVAC Bldg 311
HVAC Bldg 2601
HVAC Bldg 1485
HVAC Bldg 471
HVAC Bldg 234
HVAC Bldg 472
HVAC Bldg 1613
HVAC Bldg 147
Bidder: Lanier Contracting, Suwanee, GA
BIDS
# _4__ # _5__ # _6__
Bidder: Ameriphysics Energy, Knoxville, TN
Bidder: SDV East, Sarasota, FL
Description of Item
Bid Security: Y Bid Security: Y Bid Security: Y
HVAC Bldg 134
Amendments Acknowledged: Y Amendments Acknowledged: Y Amendments Acknowledged: Y
Issued: 6 July 10
Opened: 12 August 10
Issuing Office: VaARNG USPFO-AQS W912LQ
Project Title: Energy Upgrades
Number of Amendments Issued: 3
CLIN # Est Qty Unit Unit Price Extended Amount Unit Price Extended Amount Unit Price Extended Amount
0001 1 JB 414,781.00$ 414,781.00$ 490,418.00$ 490,418.00$ 723,741.00$ 723,741.00$
0002 1 JB 107,587.00$ 107,587.00$ 102,082.00$ 102,082.00$ 209,374.00$ 209,374.00$
0003 1 JB 97,145.00$ 97,145.00$ 82,084.00$ 82,084.00$ 163,245.00$ 163,245.00$
0004 1 JB 150,324.00$ 150,324.00$ 155,162.00$ 155,162.00$ 267,217.00$ 267,217.00$
0005 1 JB 164,865.00$ 164,865.00$ 165,310.00$ 165,310.00$ 273,317.00$ 273,317.00$
0006 1 JB 143,268.00$ 143,268.00$ 159,828.00$ 159,828.00$ 220,762.00$ 220,762.00$
0007 1 JB 297,981.00$ 297,981.00$ 208,625.00$ 208,625.00$ 277,404.00$ 277,404.00$
0008 1 JB 38,759.00$ 38,759.00$ 33,985.00$ 33,985.00$ 46,745.00$ 46,745.00$
0009 1 JB 40,334.00$ 40,334.00$ 39,200.00$ 39,200.00$ 165,029.00$ 165,029.00$
0010 1 JB 260,499.00$ 260,499.00$ 182,077.00$ 182,077.00$ 227,618.00$ 227,618.00$
0011 1 JB 257,147.00$ 257,147.00$ 178,500.00$ 178,500.00$ 179,116.00$ 179,116.00$
0012 100 BF 11.06$ 1,106.00$ 1.60$ 160.00$ 25.00$ 2,500.00$
0012 450 BF 11.06$ 4,977.00$ 1.60$ 720.00$ 25.00$ 11,250.00$
0012 50 BF 11.06$ 553.00$ 1.60$ 80.00$ 25.00$ 1,250.00$
0013 1,979,326.00$ 1,798,231.00$ 2,768,568.00$
0014 1 JB 3,069.00$ 3,069.00$ 351.00$ 351.00$ 405.00$ 405.00$
0015 1 JB 3,443.00$ 3,443.00$ 351.00$ 351.00$ 405.00$ 405.00$
0016 1 JB 7,164.00$ 7,164.00$ 1,813.00$ 1,813.00$ 3,450.00$ 3,450.00$
0017 1 JB 7,164.00$ 7,164.00$ 1,813.00$ 1,813.00$ 3,450.00$ 3,450.00$
0018 1 JB 4,818.00$ 4,818.00$ 3,151.00$ 3,151.00$ 4,486.00$ 4,486.00$
0019 1 JB 8,413.00$ 8,413.00$ 2,203.00$ 2,203.00$ 7,989.00$ 7,989.00$
0020 1 JB 17,479.00$ 17,479.00$ 11,163.00$ 11,163.00$ 15,625.00$ 15,625.00$
0021 1 JB 20,225.00$ 20,225.00$ 13,094.00$ 13,094.00$ 21,494.00$ 21,494.00$
0022 1 JB 20,225.00$ 20,225.00$ 13,284.00$ 13,284.00$ 21,350.00$ 21,350.00$
0023 1 JB 35,579.00$ 35,579.00$ 15,259.00$ 15,259.00$ 42,194.00$ 42,194.00$
0024 1 JB 22,407.00$ 22,407.00$ 26,682.00$ 26,682.00$ 69,553.00$ 69,553.00$
0025 1 JB 34,567.00$ 34,567.00$ 18,922.00$ 18,922.00$ 26,030.00$ 26,030.00$
0026 1 JB 15,522.00$ 15,522.00$ 6,491.00$ 6,491.00$ 8,240.00$ 8,240.00$ Lighting Facility T0229
Lighting Facility T0218
Lighting Facility T0222
Lighting Facility T0224
Lighting Facility T0215
Lighting Facility T0216
Lighting Facility DGIF1
Lighting Facility T0049
Lighting Facility T0212
Lighting Facility 00002
Lighting Facility 00003
Lighting Facility 00005
Deteriorated Wood
Total 0001-0012
Lighting Facility 00001
HVAC Bldg 311
HVAC Bldg 218
Deteriorated Wood
Deteriorated Wood
HVAC Bldg 1485
HVAC Bldg T0049
HVAC Bldg 1613
HVAC Bldg 2601
HVAC Bldg 472
HVAC Bldg 471
HVAC Bldg 147
HVAC Bldg 234
Description of Item
HVAC Bldg 134
Amendments Acknowledged: 3 Amendments Acknowledged: Y Amendments Acknowledged: Y
Bid Security: Y Bid Security: Y Bid Security: Y
Bidder: American Veteran, Chester, VA Bidder: Eagle Crossing, VA Beach, VA
Bidder: MNM Corporation, Burstonville, MD
# _7__ # _8__ # _9__
BIDS
Issued: 6 July 10
Opened: 12 August 10
Issuing Office: VaARNG USPFO-AQS W912LQ
Project Title: Energy Upgrades
Number of Amendments Issued: 3
CLIN # Est Qty Unit Unit Price Extended Amount Unit Price Extended Amount Unit Price Extended Amount
0027 1 JB 21,500.00$ 21,500.00$ 23,632.64$ 23,632.64$ 24,113.03$ 24,113.03$
0028 1 JB 32,000.00$ 32,000.00$ 29,401.68$ 29,401.68$ 29,041.52$ 29,041.52$
0029 1 JB 18,000.00$ 18,000.00$ 18,878.88$ 18,878.88$ 16,174.95$ 16,174.95$
0030 1 JB 5,800.00$ 5,800.00$ 3,960.48$ 3,960.48$ 6,439.81$ 6,439.81$
0031 1 JB 10,900.00$ 10,900.00$ 9,427.60$ 9,427.60$ 9,178.18$ 9,178.18$
0032 1 JB 29,000.00$ 29,000.00$ 23,423.96$ 23,423.96$ 19,579.06$ 19,579.06$
0033 1 JB 21,000.00$ 21,000.00$ 21,551.76$ 21,551.76$ 20,487.01$ 20,487.01$
0034 1 JB 6,000.00$ 6,000.00$ 7,039.64$ 7,039.64$ 6,310.72$ 6,310.72$
0035 1 JB 9,000.00$ 9,000.00$ 8,621.00$ 8,621.00$ 9,292.76$ 9,292.76$
0036 1 JB 3,500.00$ 3,500.00$ 2,317.68$ 2,317.68$ 2,329.35$ 2,329.35$
0037 1 JB 6,000.00$ 6,000.00$ 5,239.20$ 5,239.20$ 6,763.25$ 6,763.25$
0038 1 JB 24,000.00$ 24,000.00$ 21,963.20$ 21,963.20$ 19,406.46$ 19,406.46$
0039 1 JB 21,000.00$ 21,000.00$ 17,385.56$ 17,385.56$ 19,525.39$ 19,525.39$
0040 1 JB 3,000.00$ 3,000.00$ 24,829.96$ 24,829.96$ 2,529.51$ 2,529.51$
0041 1 JB 8,000.00$ 8,000.00$ 6,214.52$ 6,214.52$ 7,326.01$ 7,326.01$
0042 1 JB 91,000.00$ 91,000.00$ 110,761.72$ 110,761.72$ 99,189.04$ 99,189.04$
0043 1 JB 54,200.00$ 54,200.00$ 28,778.60$ 28,778.60$ 36,236.99$ 36,236.99$
0044 1 JB 2,500.00$ 2,500.00$ 4,583.56$ 4,583.56$ 3,884.19$ 3,884.19$
0045 1 JB 5,000.00$ 5,000.00$ 2,023.16$ 2,023.16$ 1,924.69$ 1,924.69$
0046 1 JB 5,400.00$ 5,400.00$ 54,270.12$ 54,270.12$ 4,718.18$ 4,718.18$
0047 1 JB 9,700.00$ 9,700.00$ 5,943.68$ 5,943.68$ 7,362.27$ 7,362.27$
0048 1 JB 46,300.00$ 46,300.00$ 32,947.76$ 32,947.76$ 32,570.36$ 32,570.36$
0049 1 JB 11,800.00$ 11,800.00$ 8,193.28$ 8,193.28$ 8,830.08$ 8,830.08$
0050 1 JB 7,200.00$ 7,200.00$ 6,843.52$ 6,843.52$ 7,017.07$ 7,017.07$
0051 1 JB 7,200.00$ 7,200.00$ 7,512.48$ 7,512.48$ 7,613.19$ 7,613.19$
0052 1 JB 6,500.00$ 6,500.00$ 1,394.16$ 1,394.16$ 9,724.98$ 9,724.98$
0053 1 JB 2,500.00$ 2,500.00$ 2,202.24$ 2,202.24$ 1,785.45$ 1,785.45$
0054 1 JB 8,100.00$ 8,100.00$ 6,051.72$ 6,051.72$ 6,429.66$ 6,429.66$
0055 1 JB $20,100.00 20,100.00$ 19,423.52$ 19,423.52$ 18,177.96$ 18,177.96$
Lighting Facility T0764
Bidder: Bidder: Bidder:
Amendments Acknowledged: Amendments Acknowledged: Amendments Acknowledged:
# _1__ # _2__
Bid Security: Bid Security:
# _3__
Bid Security:
Lighting Facility T0230
Description of Item
Lighting Facility T0234
Lighting Facility T0303
Lighting Facility T0309
Lighting Facility T0311
Lighting Facility T0312
Lighting Facility T0232
Lighting Facility T0763
Lighting Facility AT495
Lighting Facility T0495
Lighting Facility 503
Lighting Facility 561
Lighting Facility AT562
Lighting Facility T0562
Lighting Facility T0563
Lighting Facility AT564
Lighting Facility T0564
Lighting Facility T0761
Lighting Facility T0762
Lighting Facility T0320
Lighting Facility T0321
Lighting Facility T0468
Lighting Facility T0469
Lighting Facility T0471
Lighting Facility T0472
Lighting Facility T0765
Lighting Facility T0767
Lighting Facility T1307
Issued: 6 July 10
Opened: 12 August 10
Issuing Office: VaARNG USPFO-AQS W912LQ
Project Title: Energy Upgrades
Number of Amendments Issued: 3
CLIN # Est Qty Unit Unit Price Extended Amount Unit Price Extended Amount Unit Price Extended Amount
0027 1 JB 29,296.00$ 29,296.00$ -$ -$ 22,289.00$ 22,289.00$
0028 1 JB 60,774.00$ 60,774.00$ -$ -$ 25,191.00$ 25,191.00$
0029 1 JB 20,443.00$ 20,443.00$ -$ -$ 13,522.00$ 13,522.00$
0030 1 JB 9,056.00$ 9,056.00$ -$ -$ 5,501.00$ 5,501.00$
0031 1 JB 12,642.00$ 12,642.00$ -$ -$ 13,083.00$ 13,083.00$
0032 1 JB 32,564.00$ 32,564.00$ -$ -$ 21,477.00$ 21,477.00$
0033 1 JB 30,552.00$ 30,552.00$ -$ -$ 24,065.00$ 24,065.00$
0034 1 JB 8,798.00$ 8,798.00$ -$ -$ 6,303.00$ 6,303.00$
0035 1 JB 11,406.00$ 11,406.00$ -$ -$ 8,494.00$ 8,494.00$
0036 1 JB 4,457.00$ 4,457.00$ -$ -$ 3,645.00$ 3,645.00$
0037 1 JB 9,347.00$ 9,347.00$ -$ -$ 8,402.00$ 8,402.00$
0038 1 JB 26,784.00$ 26,784.00$ -$ -$ 14,959.00$ 14,959.00$
0039 1 JB 26,510.00$ 26,510.00$ -$ -$ 14,048.00$ 14,048.00$
0040 1 JB 3,859.00$ 3,859.00$ -$ -$ 3,933.00$ 3,933.00$
0041 1 JB 9,580.00$ 9,580.00$ -$ -$ 7,915.00$ 7,915.00$
0042 1 JB 140,801.00$ 140,801.00$ -$ -$ 85,456.00$ 85,456.00$
0043 1 JB 33,677.00$ 33,677.00$ -$ -$ 33,909.00$ 33,909.00$
0044 1 JB 3,003.00$ 3,003.00$ -$ -$ 2,755.00$ 2,755.00$
0045 1 JB 6,202.00$ 6,202.00$ -$ -$ 5,607.00$ 5,607.00$
0046 1 JB 7,444.00$ 7,444.00$ -$ -$ 3,753.00$ 3,753.00$
0047 1 JB 28,672.00$ 28,672.00$ -$ -$ 6,551.00$ 6,551.00$
0048 1 JB 43,026.00$ 43,026.00$ -$ -$ 35,235.00$ 35,235.00$
0049 1 JB 9,780.00$ 9,780.00$ -$ -$ 8,822.00$ 8,822.00$
0050 1 JB 9,609.00$ 9,609.00$ -$ -$ 8,541.00$ 8,541.00$
0051 1 JB 8,431.00$ 8,431.00$ -$ -$ 9,201.00$ 9,201.00$
0052 1 JB 9,465.00$ 9,465.00$ -$ -$ 6,782.00$ 6,782.00$
0053 1 JB 2,734.00$ 2,734.00$ -$ -$ 2,530.00$ 2,530.00$
0054 1 JB 8,410.00$ 8,410.00$ -$ -$ 8,540.00$ 8,540.00$
0055 1 JB $30,024.00 30,024.00$ -$ -$ 23,452.00$ 23,452.00$
Lighting Facility T0761
Lighting Facility T0767
Lighting Facility T0762
Lighting Facility T0763
Lighting Facility T0765
Lighting Facility AT564
Lighting Facility T1307
Lighting Facility T0764
Lighting Facility T0564
Lighting Facility AT562
Lighting Facility T0495
Lighting Facility T0563
Lighting Facility 561
Lighting Facility T0562
Lighting Facility AT495
Lighting Facility T0469
Lighting Facility 503
Lighting Facility T0472
Lighting Facility T0471
Lighting Facility T0321
Lighting Facility T0468
Lighting Facility T0312
Lighting Facility T0320
Lighting Facility T0309
Lighting Facility T0311
Lighting Facility T0234
Lighting Facility T0303
# _4__ # _5__ # _6__
Bidder: Bidder: Bidder:
Bid Security: Bid Security: Bid Security:
Lighting Facility T0230
Amendments Acknowledged: Amendments Acknowledged: Amendments Acknowledged:
Lighting Facility T0232
Description of Item
Issued: 6 July 10
Opened: 12 August 10
Issuing Office: VaARNG USPFO-AQS W912LQ
Project Title: Energy Upgrades
Number of Amendments Issued: 3
CLIN # Est Qty Unit Unit Price Extended Amount Unit Price Extended Amount Unit Price Extended Amount
0027 1 JB 40,300.00$ 40,300.00$ 18,986.00$ 18,986.00$ 27,193.00$ 27,193.00$
0028 1 JB 45,422.00$ 45,422.00$ 19,010.00$ 19,010.00$ 30,733.00$ 30,733.00$
0029 1 JB 17,493.00$ 17,493.00$ 9,686.00$ 9,686.00$ 16,497.00$ 16,497.00$
0030 1 JB 7,219.00$ 7,219.00$ 5,924.00$ 5,924.00$ 6,711.00$ 6,711.00$
0031 1 JB 13,883.00$ 13,883.00$ 5,689.00$ 5,689.00$ 15,961.00$ 15,961.00$
0032 1 JB 20,117.00$ 20,117.00$ 13,130.00$ 13,130.00$ 26,202.00$ 26,202.00$
0033 1 JB 23,727.00$ 23,727.00$ 18,783.00$ 18,783.00$ 29,359.00$ 29,359.00$
0034 1 JB 14,105.00$ 14,105.00$ 5,772.00$ 5,772.00$ 7,690.00$ 7,690.00$
0035 1 JB 14,980.00$ 14,980.00$ 7,672.00$ 7,672.00$ 10,363.00$ 10,363.00$
0036 1 JB 5,525.00$ 5,525.00$ 1,959.00$ 1,959.00$ 4,447.00$ 4,447.00$
0037 1 JB 10,495.00$ 10,495.00$ 4,389.00$ 4,389.00$ 10,250.00$ 10,250.00$
0038 1 JB 19,783.00$ 19,783.00$ 9,956.00$ 9,956.00$ 18,250.00$ 18,250.00$
0039 1 JB 23,074.00$ 23,074.00$ 12,194.00$ 12,194.00$ 17,139.00$ 17,139.00$
0040 1 JB 7,538.00$ 7,538.00$ 2,765.00$ 2,765.00$ 4,798.00$ 4,798.00$
0041 1 JB 5,025.00$ 5,025.00$ 6,009.00$ 6,009.00$ 9,656.00$ 9,656.00$
0042 1 JB 85,345.00$ 85,345.00$ 69,734.00$ 69,734.00$ 104,256.00$ 104,256.00$
0043 1 JB 52,634.00$ 52,634.00$ 19,146.00$ 19,146.00$ 41,369.00$ 41,369.00$
0044 1 JB 5,025.00$ 5,025.00$ 1,541.00$ 1,541.00$ 3,361.00$ 3,361.00$
0045 1 JB 6,663.00$ 6,663.00$ 2,619.00$ 2,619.00$ 6,841.00$ 6,841.00$
0046 1 JB 5,025.00$ 5,025.00$ 2,706.00$ 2,706.00$ 4,579.00$ 4,579.00$
0047 1 JB 36,290.00$ 36,290.00$ 3,979.00$ 3,979.00$ 7,992.00$ 7,992.00$
0048 1 JB 31,265.00$ 31,265.00$ 18,502.00$ 18,502.00$ 42,987.00$ 42,987.00$
0049 1 JB 9,620.00$ 9,620.00$ 5,360.00$ 5,360.00$ 10,763.00$ 10,763.00$
0050 1 JB 6,885.00$ 6,885.00$ 5,705.00$ 5,705.00$ 10,420.00$ 10,420.00$
0051 1 JB 7,538.00$ 7,538.00$ 6,175.00$ 6,175.00$ 11,225.00$ 11,225.00$
0052 1 JB 6,334.00$ 6,334.00$ 7,160.00$ 7,160.00$ 8,274.00$ 8,274.00$
0053 1 JB 2,513.00$ 2,513.00$ 1,643.00$ 1,643.00$ 3,087.00$ 3,087.00$
0054 1 JB 6,234.00$ 6,234.00$ 4,099.00$ 4,099.00$ 10,419.00$ 10,419.00$
0055 1 JB $22,518.00 22,518.00$ 10,506.00$ 10,506.00$ 28,611.00$ 28,611.00$ Lighting Facility T1307
Lighting Facility T0764
Lighting Facility T0765
Lighting Facility T0767
Lighting Facility T0762
Lighting Facility T0763
Lighting Facility AT564
Lighting Facility T0564
Lighting Facility T0761
Lighting Facility AT562
Lighting Facility T0562
Lighting Facility T0563
Lighting Facility AT495
Lighting Facility T0495
Lighting Facility 503
Lighting Facility 561
Lighting Facility T0469
Lighting Facility T0471
Lighting Facility T0472
Lighting Facility T0321
Lighting Facility T0468
Lighting Facility T0312
Lighting Facility T0320
Lighting Facility T0309
Lighting Facility T0311
Lighting Facility T0234
Lighting Facility T0303
Lighting Facility T0230
Lighting Facility T0232
Description of Item
Amendments Acknowledged: Amendments Acknowledged: Amendments Acknowledged:
Bid Security: Bid Security: Bid Security:
Bidder: Bidder: Bidder:
# _7__ # _8__ # _9__
Issued: 6 July 10
Opened: 12 August 10
Issuing Office: VaARNG USPFO-AQS W912LQ
Project Title: Energy Upgrades
Number of Amendments Issued: 3
CLIN # Est Qty Unit Unit Price Extended Amount Unit Price Extended Amount Unit Price Extended Amount
0056 1 JB 12,400.00$ 12,400.00$ 13,912.00$ 13,912.00$ 11,722.20$ 11,722.20$
0057 1 JB 17,300.00$ 17,300.00$ 14,292.36$ 14,292.36$ 14,672.33$ 14,672.33$
0058 1 JB 40,200.00$ 40,200.00$ 31,109.60$ 31,109.60$ 33,337.62$ 33,337.62$
0059 1 JB 17,500.00$ 17,500.00$ 18,625.80$ 18,625.80$ 16,682.59$ 16,682.59$
0060 1 JB 3,400.00$ 3,400.00$ 4,052.24$ 4,052.24$ 3,668.08$ 3,668.08$
0061 1 JB 3,000.00$ 3,000.00$ 2,477.52$ 2,477.52$ 2,735.47$ 2,735.47$
0062 1 JB 7,900.00$ 7,900.00$ 5,894.84$ 5,894.84$ 6,866.23$ 6,866.23$
0063 1 JB 6,900.00$ 6,900.00$ 6,338.84$ 6,338.84$ 7,278.15$ 7,278.15$
0064 1 JB 11,200.00$ 11,200.00$ 11,415.24$ 11,415.24$ 12,525.72$ 12,525.72$
0065 788,100.00$ 765,034.96$ 715,166.56$
0066 788,100.00$ 3,079,297.96$ 4,675,764.49$
Bid Security: Bid Security:
Lighting Facility 1485
# _1__ # _2__ # _3__
Bidder:
Bid Security:
Amendments Acknowledged:
Description of Item
Lighting Facility T1309
Amendments Acknowledged: Amendments Acknowledged:
Bidder: Bidder:
Lighting Facility T2856
Lighting Facility T1613
Lighting Facility T2204
Lighting Facility T2360
Lighting Facility T2361
Lighting Facility T2372
Lighting Facility T2373
TOTAL 0014-0064
TOTAL 0013 & 0065
Issued: 6 July 10
Opened: 12 August 10
Issuing Office: VaARNG USPFO-AQS W912LQ
Project Title: Energy Upgrades
Number of Amendments Issued: 3
CLIN # Est Qty Unit Unit Price Extended Amount Unit Price Extended Amount Unit Price Extended Amount
0056 1 JB 14,264.00$ 14,264.00$ -$ -$ 9,772.00$ 9,772.00$
0057 1 JB 19,720.00$ 19,720.00$ -$ -$ 12,996.00$ 12,996.00$
0058 1 JB 15,382.00$ 15,382.00$ -$ -$ 29,632.00$ 29,632.00$
0059 1 JB 22,241.00$ 22,241.00$ -$ -$ 13,537.00$ 13,537.00$
0060 1 JB 5,076.00$ 5,076.00$ -$ -$ 3,573.00$ 3,573.00$
0061 1 JB 3,662.00$ 3,662.00$ -$ -$ 3,549.00$ 3,549.00$
0062 1 JB 8,769.00$ 8,769.00$ -$ -$ 7,967.00$ 7,967.00$
0063 1 JB 9,274.00$ 9,274.00$ -$ -$ 6,313.00$ 6,313.00$
0064 1 JB 14,815.00$ 14,815.00$ -$ -$ 13,731.00$ 13,731.00$
0065 1,005,127.00$ -$ 719,187.00$
0066 2,967,647.00$ 1,212,870.00$ 3,166,210.00$
Alternative bid for HVAC
TOTAL 0014-0064
TOTAL 0013 & 0065
Lighting Facility T2373
Lighting Facility T2856
Lighting Facility T2361
Lighting Facility T2372
Lighting Facility T2204
Lighting Facility T2360
Lighting Facility 1485
Amendments Acknowledged:
Lighting Facility T1309
Lighting Facility T1613
Bidder: Bidder:
Amendments Acknowledged: Amendments Acknowledged:
Bid Security: Bid Security: Bid Security:
# _4__ # _5__ # _6__
Bidder:
Description of Item
Issued: 6 July 10
Opened: 12 August 10
Issuing Office: VaARNG USPFO-AQS W912LQ
Project Title: Energy Upgrades
Number of Amendments Issued: 3
CLIN # Est Qty Unit Unit Price Extended Amount Unit Price Extended Amount Unit Price Extended Amount
0056 1 JB 9,402.00$ 9,402.00$ 6,307.00$ 6,307.00$ 11,922.00$ 11,922.00$
0057 1 JB 16,937.00$ 16,937.00$ 11,367.00$ 11,367.00$ 15,855.00$ 15,855.00$
0058 1 JB 28,752.00$ 28,752.00$ 22,197.00$ 22,197.00$ 36,151.00$ 36,151.00$
0059 1 JB 17,493.00$ 17,493.00$ 10,613.00$ 10,613.00$ 16,515.00$ 16,515.00$
0060 1 JB 5,025.00$ 5,025.00$ 1,921.00$ 1,921.00$ 4,359.00$ 4,359.00$
0061 1 JB 4,372.00$ 4,372.00$ 1,711.00$ 1,711.00$ 4,330.00$ 4,330.00$
0062 1 JB 7,538.00$ 7,538.00$ 5,891.00$ 5,891.00$ 9,720.00$ 9,720.00$
0063 1 JB 7,538.00$ 7,538.00$ 5,660.00$ 5,660.00$ 7,702.00$ 7,702.00$
0064 1 JB 14,980.00$ 14,980.00$ 6,975.00$ 6,975.00$ 16,752.00$ 16,752.00$
0065 864,687.00$ 488,018.00$ 877,410.00$
0066 2,844,013.00$ 2,286,249.00$ 3,645,978.00$ TOTAL 0013 & 0065
Lighting Facility T2856
TOTAL 0014-0064
Lighting Facility T2372
Lighting Facility T2373
Lighting Facility T2360
Lighting Facility T2361
Lighting Facility T1613
Lighting Facility T2204
Lighting Facility T1309
Lighting Facility 1485
Amendments Acknowledged: Amendments Acknowledged:
Description of Item
Bid Security: Bid Security:
Amendments Acknowledged:
Bidder: Bidder:
Bid Security:
# _7__ # _8__ # _9__
Bidder:
File details come from the government source that posted it. Updated .