This statement of work requests two mezzanines to be delivered to a military maintenance facility in Little Falls, Minnesota. The mezzanines should each measure 12 feet by 24 feet with an 8 foot deck clearance. They must support up to 125 pounds per square foot and include a stairway, kickplate, railing, removable panel for a forklift, and be floor anchored as stand-alone, self-supporting structures. Drawings must be submitted with responses. The mezzanines will store parts, cabinets, pallets, crates, and tire assemblies up to a maximum pallet load of 1,500 to 2,000 pounds. No installation is required beyond delivery.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C 04 - Clarifications - Mezzanine.docx | DOCX document | |
| Statement of Work Mezzanine V2.docx | DOCX document | |
| B 01 - Combined Synopsis_Solicitation - Mezzanine.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Parts Mezzanine
· Deliver to USPFO Warehouse 15000 highway 115, Camp Ripley, Little Falls, MN, 56345.
· Quantity: 2
· Mezzanines will be used to store parts, bench stock and special tool kits for a military maintenance facility.
· Size of parts mezzanine should be 12’x24’ with 8’ deck clearance.
· Decking should be 3/16” smooth or plate flooring
· Each mezzanine must include one stairway that is internal to the frame.
· Mezzanines must include a kickplate (at least 4”) and a railing.
· Mezzanines must be rated for at least 5,000 lbs.
· Mezzanines must have a removable panel on the end large enough to accommodate a forklift dropping a standard pallet on mezzanine.
· Vendor must submit a drawing along with the solicitation response.
· Mezzanines must be stand alone, self-supporting, Floor anchored.
· All connectors, parts, anchors must be included in the purchase - no welding on site should be required.
Questions answered
· Do you require installation of the mezzanines, or are these only a drop shipment?
No installation is required.
· For the capacity, are you saying you require 5,000 pounds for the entire mezzanine? The are normally rated at a X pounds per square foot.
For a 12X24 mezzanine with an approximate live weight of 10,000Lbs it comes out to 34.7. Typical industrial weight is 125lbs per sq ft. I think that we should go with the 125lsb per sq ft.
· What do you plan to store on the mezzanine? Is it just pallets or will there be cabinets/shelving/etc to store small parts in as well?
There will be storage cabinets with tools and parts. There will be the potential for crates, pallets and tire assemblies.
· What is the maximum load for a pallet being stored on the mezzanine? We need this to determine the point load of a pallet jack on the mezzanine floor.
I would say 1,500 to 2,000lbs for a MAXIMUM load on a pallet.