This document is a Statement of Work (SOW) for a breathing air compressor required by the Colorado Army National Guard 8th Weapons of Mass Destruction Civil Support Team (CST). The contractor shall provide and install a breathing air compressor for the current SCBA bottle fill station, including unscheduled maintenance, repair, and initial user-level operation and maintenance training. The compressor must be compatible with the Scott's Safety Revolve Air Change Station, have a 6000 psig working pressure and a minimum charging rate of 13.0 CFM, and include CO and H2S monitoring with an audible alarm. The compressor must meet specific size, electrical, and noise requirements. The contractor must provide a 24-month warranty and complete installation and training within one work week. Pricing must include freight and shipping. This requirement is solicited under Solicitation Number W912LC-24-Q-0039, which is a 100% small business set-aside. Quotes are due by the closing date and time specified in the solicitation.

View the file

Other files

File Type Posted
W912LC-24-Q-0039.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)-TitleBreathing Air Compressor

Purpose Statement / Objective – The Colorado Army National Guard 8th Weapons of Mass Destruction Civil Support Team (CST) require a breathing air compressor for the current SCBA bottle fill station.

Scope of Work – The contractor shall provide and install breathing air compressor for the current SCBA bottle fill station. Provide unscheduled maintenance and repair and initial user level operation and maintenance training.

Delivery address:

19070 E SUNLIGHT WAY, BLDG 1000A, MS36, BSFB, AURORA, CO 80011

Schedule (Performance Objectives):

Breathing Air Compressor must be compatible with Scott’s Safety Revolve Air Change Station

1)Breathing Air Compressor size not to exceed overall dimensions of L55” x W35” x H70”
2)Must have 6000 psig working pressure and a minimum charging rate of 13.0 CFM.
3)Must have CO and H2S monitoring system with audible alarm.
4)Must have a touchscreen display.
5)Noise shall not exceed 72 DB at one meter
6)Must meet the following electrical requirements
a. 208 three phase electric
b. 65 amps

7) Must be able to support unscheduled warranty maintenance within 24-48 hours after notification of service.

a. Must include Factory warranty consisting of at least the following.

i. Manufactured compressors, compressor systems and accessory equipment are warrantied for twenty-four (24) months from date of equipment installation and acceptance.

8)Must include installation. Must include installation. All installation and cleanup activities and end user training must be completed within one 40-hour work week Tuesday-Friday between 0800-1700 hours.
9)Pricing must include freight and shipping.
10)Must include 1-day user level operation and maintenance training.

Special Requirements/Conditions (If Needed): There are no specific special requirement or conditions to be considered.

Acceptance: Vendor must demonstrate equipment performs up to manufacturer specifications, is compatible with the Scott’s Safety Revolve Air Change Station and meets unit requirements of a breathing air compressor for the current SCBA bottle fill station.

Payment–Payment terms and schedule etc.

· Vendor/Contractor must Invoice through Wide Area Workflow (WAWF)

· Vendor must be registered in WAWF in order to submit an invoice

· https://piee.eb.mil/