W912LC-18-B-0001-Amendment_2.pdf

PDF 142 KB Posted

Attached to
Space Battalion Readiness Center
Solicitation number
W912LC-18-B-0001
Issued by

About this file

Amendment to incorporate revised drawings/specifications, update wage determination, and attach the Geotechnical Report.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USPFO-PNC-CO

660 S. ASPEN ST., MS #66, BLDG 1005

BUCKLEY AIR FORCE BASE

AURORA CO 80011-9551

080115

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Project Title: (National Guard) Space Battalion Readiness Center, Fort Carson, Colorado.

Project Number: PN080115

Amendment 2 is issued as follow s:

1) Add specification section 05 40 00.

2) Add Geothermal Report, dated 1/3/2017

3) Revise Wage Determination

4) Revise Table of Contents, Submittal Register, and various draw ings and specification sections as described on block 14 continuation page.

1. CONTRACT ID CODE PAGE OF PAGES

1 10

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 17-Oct-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912LC18B0001

X 9B. DATED (SEE ITEM 11)

17-Sep-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-Oct-2018

CODE

NATIONAL GUARD BUREAU-AQ

111 SOUTH GEORGE MASON DR

BLDG. 2, 4TH FLOOR

ARLINGTON VA 22202-1373

W9133L 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W912LC

FACILITY CODECODE

EMAIL:TEL:

W912LC18B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 2

CHANGES TO THE SPECIFICATIONS WITHOUT REISSUING SPECIFICATIONS:

1. Revised Volume 1, section 10 14 00, Part I-GENERAL from “(See Message Schedule attached to this section 10 14 00)” to “(See Signage Schedule attached to this section 10 14 00)

2. REVISE Specification Section 26 09 43 - NETWORK LIGHTING CONTROLS, PART 2, paragraph 2.10 to include other manufacturers as acceptable:

DELETE:

2.01 MANUFACTURERS:

A. Subject to compliance with requirements, provide lighting control equipment from Lutron Electronic, Inc. or approved equal.

B. Basis of Design Product: Vive by Lutron Electronic, Inc.

ADD:

2.01 MANUFACTURERS:

A. Subject to compliance with requirements, provide lighting control equipment from but not limited to:

1. Lutron Electronic, Inc.

2. Wattstopper

2. Crestron Electronics – Zum

3. Acuity Brands – nLight

B. Basis of Design Product: Vive by Lutron Electronic, Inc.

3. REVISE SECTION 26 32 13 - DIESEL GENERATOR SETS to read as follows:

PART 2 - PRODUCTS

2.01 MANUFACTURERS:

A. Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. Caterpillar Tractor Co.

2. Detroit Diesel Allison Div; GM Corp.

3. Kohler Co.

4. Cummins/Onan Corp.

5. GENERAC

4. ADD to Specification Section 01 00 00-General Requirement, Paragraph 1.11: C. For purposes of assuring that the performance specification can be achieved, a list of manufacturers have been provided that are known to meet the requirement. The individual specifications that state "Manufacturers: Subject to compliance with requirements, provide products by one of the following:", is not limited to only those manufacturers. Therefore, products of other manufacturers may be allowed, provided that they meet the requirements of the performance specifications and are approved by the Contracting Officer.

5. REVISE SECTION 32 12 17 - HOT-MIX ASPHALTIC-CONCRETE PAVEMENT Paragraph 3.07:

ADD: B. If CDOT mix design is used, refer to Paragraph section 401.17 Compaction of the CDOT

Standard Specification for Road & Bridge Construction stating: Density of completed pavement shall be compacted to a density of 92 - 96% of the daily theoretical maximum specific gravity per CP 51.

Longitudinal joints shall be compacted to a density of 92% (+/- 4%) of the theoretical maximum specific gravity. Density will be determined in accordance with CP 44.

CHANGES TO THE SPECIFICATIONS AND REISSUED SPECIFICATION(S):

1. Revised Table of Contents, dated 10/15/2018

2. Revised Specification Section 01 33 00-Submittal Register, dated 10/15/2018

3. Add Specification Section 05 40 00 COLD-FORMED METAL FRAMING, 10/15/2018

4. Add 10 14 00-“Signage Schedule” (dated May 2018) after page 10 14 00-5 of Specification section 10 14

CHANGES TO THE DRAWINGS WITHOUT REISSUING

1. REVISE Drawing C 501 Detail 3 DELETE: “PRIME COAT and arrow point to location between bottom of asphalt and top of aggregate.

2. REVISE Drawing A251, Detail for Roof System 2

DELETE

“90 MIL EPDM”

ADD

“60 MIL EPDM” in its place.

3. REVISE Drawing S401, VAULT PLAN:

DELETE:

The 7’ 4-5/8” measurement at the vault door openings

ADD:

The measurement 4’ 4 5/8” at the vault door openings and NOTE: Contractor to verify rough opening dimension with Vault Door supplier.

4. REVISE Drawing M506, Details 5 and 6: Change “Black Iron Pipe” to “Black Iron Pipe or HDPE”

5. Drawing C201: Change NEW ELEC DIESEL BACKUP GENERATOR (BY OTHERS) to NEW ELEC

DIESEL BACKUP GENERATOR

Change NEW ELEC SERVICE PAD MOUNTED TRANSFORMER (BY OTHERS) to NEW ELEC

SERVICE PAD MOUNTED TRANSFORMER

CHANGES TO THE DRAWINGS AND REISSUED DRAWING(S)

1. REPLACE Drawing Sheet A251 with new Drawing Sheet A251

2. REPLACE Drawing Sheet C003 with new Drawing Sheet C003

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been modified:

WAGE DETERMINATION

General Decision Number: CO180032 10/12/2018 CO32

Superseded General Decision Number: CO20170032

State: Colorado

Construction Type: Building

County: El Paso County in Colorado.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.

Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2018 1 01/12/2018 2 02/02/2018 3 03/02/2018 4 07/13/2018 5 08/03/2018 6 08/31/2018 7 10/12/2018

ASBE0028-002 07/01/2018

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR - MECHANICAL (Duct, Pipe & Mechanical System Insulation)......................$ 31.73 14.23

ELEC0113-005 06/01/2018

Rates Fringes

ELECTRICIAN (Includes Low Voltage Wiring)..................$ 31.80 15.90

ELEV0025-001 01/01/2018

Rates Fringes

ELEVATOR MECHANIC................$ 43.66 32.645

FOOTNOTE:

a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.

b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.

ENGI0009-017 05/01/2017

Rates Fringes

POWER EQUIPMENT OPERATOR

(Crane) 141 tons and over...........$ 29.82 10.10 50 tons and under...........$ 27.75 10.10 51 to 90 tons...............$ 27.92 10.10 91 to 140 tons..............$ 28.55 10.10

IRON0024-009 06/01/2018

Rates Fringes

IRONWORKER, ORNAMENTAL...........$ 27.45 12.34

IRON0024-011 06/01/2018

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 27.45 12.34

PAIN0079-009 08/01/2017

Rates Fringes

PAINTER (Spray)..................$ 20.50 8.41

PLAS0577-002 05/01/2018

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 27.13 12.10

* PLUM0058-003 07/01/2018

Rates Fringes

PLUMBER (Excludes HVAC Duct, Pipe and Unit Installation)......$ 32.75 14.85

* PLUM0058-004 07/01/2018

Rates Fringes

PIPEFITTER, Includes HVAC Pipe Installation (Excludes HVAC Duct and Unit Installation)....................$ 32.75 14.85

SFCO0669-002 04/01/2017

Rates Fringes

SPRINKLER FITTER (Fire Sprinklers)......................$ 36.73 20.47

SHEE0009-005 07/01/2018

Rates Fringes

SHEET METAL WORKER (Excludes HVAC Duct, Pipe and Unit Installation)....................$ 34.02 17.49

SUCO2013-008 07/31/2015

Rates Fringes

BRICKLAYER.......................$ 21.96 0.00

CARPENTER........................$ 22.63 6.98

LABORER: Common or General......$ 13.40 1.40

LABORER: Mason Tender - Brick...$ 15.99 0.00

LABORER: Mason Tender - Cement/Concrete..................$ 16.00 0.00

LABORER: Pipelayer..............$ 16.96 3.68

OPERATOR:

Backhoe/Excavator/Trackhoe.......$ 20.26 8.62

OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 18.58 2.42

OPERATOR: Grader/Blade..........$ 21.50 0.00

PAINTER (Brush and Roller).......$ 17.20 0.00

ROOFER...........................$ 16.71 0.00

SHEET METAL WORKER (HVAC Duct Installation Only)...............$ 25.18 6.30

SHEET METAL WORKER (HVAC Unit Installation Only)...............$ 24.00 2.18

TRUCK DRIVER: Dump Truck........$ 17.34 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

(End of Summary of Changes)