COLORADO ARMY NATIONAL GUARD

FY19 SPACE BATTALION

READINESS CENTER

FT. CARSON, COLORADO

Agenda

9:00- 9:05 Welcome and Introductions

9:05 - 9:15 Purpose of Facility

9:15- 9:30 Contracting Overview

9:30- 9:40 Travel to site

9:40- 10:30 Site Visit October 3, 2018

UNCLASSIFIED

COLORADO ARMY NATIONAL GUARD

FY19 SPACE BATTALION

READINESS CENTER

FT. CARSON, COLORADO

PRE-BID CONFERENCE & SITE VISIT

October 3, 2017

Introduction of Staff Contracting Officer (KO)

Contracting Specialist

Contracting Officer Representative (COR)

Description of Project The project includes the construction of an approximately 36,870 square foot building, steel frame with metal stud walls, exterior metal panels, standing seam and flat roofs, storefront and windows, site work, associated utility work, sediment and erosion control, and stormwater management. The project will include emergency power generator backup for the facility; geothermal mechanical system, and LED lighting, and automated HVAC controls. The building will be constructed to obtain LEED certified Silver Rating in accordance with USGBC LEED certification. Construction will be located on a 15-acre Site near Barger Road and Barkley Avenue at Ft. Carson, Colorado Springs, Colorado.

Synopsis Project Magnitude: $10,000,000 - $25,000,000 Set Aside: 100% Small Business North American Industry Classification Code: 236220 Contract Duration: 510 days after NTP Additional 30 days for Option 1 Documents: listed on www.FBO.gov Bid Opening: October 18, 2018 @ 2PM Local Buckley AFB, Building 1005, Classroom 107/108

Bid with Options

New Construction Of A Space Battalion Readiness Center, Fort Carson, Colorado Option 1: West End of the Facility Option 2: Unheated Storage Building Option 3: Concrete Pavement On Military Parking Lot Option 4: Three Interior Overhead Doors at Assembly Hall Option 5: Operable Partition, Cabinets, Countertops in Classrooms Option 6: 2" Asphalt Surface on Eastern portion of POV lot Option 7: Provide Landscaping Option 8: Provide Front Entry Patio, Wall and Sign Option 9: MDF Wainscoting Wall Panels Option 10: 2 HVLS Ventilation Fans In Entry Hall

Evaluation of Options IAW 52.217-3 Evaluation of Exclusive of Options

The Government will evaluate offers for award purposes by including only the price for the basic requirement; i.e., options will not be included in the evaluation for award purposes.

Sole Source /Brand Name Items

SmartStruxture HVAC Controls/Westover Corporation CoreMax - Hardware Lock Cores CommScope (Formerly TE Connectivity) American Power Conversion (APC-UPS)

Complete Bid Package

(a) Offer, Standard Form (SF) 1442 front and back Original Official Signature

(b) Contract Line Items- All Items Priced

(c) Bid Bond: Standard Form 24

(d) Section 00600, Representations and Certifications and the offeror must have entered current and complete data within the pas year in www.sam.gov

(e) Acknowledgement of All Amendments

(f) Sealed in an envelope marked “BID No. W912LC-18-B-0001” with Name and Address of Bidder

RFI during the Site Visit Please do not direct questions to the COR, Staff, and/or A-E firm during the site visits. All questions need to be formally submitted to the contracting office via email as described in the solicitation.

EMAIL

whitney.l.arkle.civ@mail.mil sabrina.m.deramus.civ@mail.mil and sandra.m.Kenzie.civ@mail.mil

Subject Line: Reference No. RFI for Solicitation No. W912LC-18-B-0001, Space Battalion Readiness Center

Site Visit Overview

Parking Safety Photographs image2.png image3.png image1.emf

File details come from the government source that posted it.