QUESTIONS AND ANSWERS FOR
SOLICITATION W912LC-18-B-0001
COARNG-Space Battalion Readiness Center Project No. 080115 17 September 2018
Date: 2 October 2018
Question 1: The Company has applied for clearance using DD2345 to the Joint Certification Office but has not receive the final approval. Would the Government consider accepting the emailed confirmation of receipt & processing, and providing access to the documents for this project via AMRDEC or some other safe site?
Answer 1: The government is not offering the drawings and specs via AMRDEC/email. The pre-solicitation notice for this project was published on 05/15/2018, which identified the requirement to obtain export controlled authorization AND MPIN.
Question 2: Are you able to grant us access to download the plans and specifications? I entered a valid MPIN, but am not able to view the controlled documents. The DD2345 is approved. Please assist.
Answer 2. No. You are required to have an approved DD 2345 and MPIN. If you have both, the U.S./Canada Joint Certification Program (JCP) office reported to this office that once a company is certified with the JCP office (normally 7 to 12 business days), the company should contact FBO to have them add their JCP number to their FBO account. The FBO help desk (Federal Service Desk) reported to this office that companies need to make sure that they are registered and login as a Vendor to FBO. When the Vendor click's to open an export controlled package/document, they should be asked for their MPIN. After entering the MPIN, the export controlled package/document should be viewable/downloadable by Vendors that have gone through the JCP process. If a Vendor still has problems, the Vendor should check to make sure that their SAM registration and MPIN are valid and up-to-date. If problems still persist, the Vendor may call the FBO help desk at 866-606-8220 and ask for troubleshooting assistance.
Question 3: Is there a fax line that we may submit our DD Form 2345, Military Critical Data Agreement IOT submit our form for faster access to the Locked Documents on this solicitation.
Answer 3: Instructions to fill out and submit the DD2345 can be located from:
http://www.dla.mil/HQ/InformationOperations/Offers/Products/LogisticsApplicatio ns/JCP/SpecificDD2345Instructions.aspx
Question 4: Suggested change to section 26 32 13, Diesel Generator Sets, paragraph 2.01: Request to add GENERAC as an acceptable generator http://www.dla.mil/HQ/InformationOperations/Offers/Products/LogisticsApplications/JCP/SpecificDD2345Instructions.aspx http://www.dla.mil/HQ/InformationOperations/Offers/Products/LogisticsApplications/JCP/SpecificDD2345Instructions.aspx supplier?
Answer 4: GENERAC is added as an acceptable supplier. Amendment is forthcoming to reflect revision.
Question 5: Please provide list of alternate/approved lighting control systems that meet the intent of the controls system specified, i.e. Wattstopper, Encillium, etc.
Answer 5: Revise 26 09 43 - NETWORK LIGHTING CONTROLS, PART 2, paragraph 2.10 to include other manufacturers as acceptable:
PART 2 - PRODUCTS
2.01 MANUFACTURERS:
A. Subject to compliance with requirements, provide lighting control equipment from
a. Lutron Electronic, Inc.
B. Approved equals include the following:
1. Wattstopper
2. Crestron Electronics – Zum
3. Acuity Brands – nLight
B. Basis of Design Product: Vive by Lutron Electronic, Inc.
Amendment is forthcoming to reflect revision.
Question 6: Please confirm that the specified Lutron Vive control system specified has been coordinated and is compatible with specified lighting fixtures as shown on the fixture schedule.
Answer 6: Yes. The fixtures specified in the fixtures schedule have been coordinated with the Lutron Vive system. Lutron Vive can work with a variety of drivers, we have gone with the typical 0-10V driver throughout all dimming fixtures.
Amendment is forthcoming to reflect change.
Question 7: I can’t view the “interested vendors list”. Can you change this to Allow vendors to view interested vendors list?
Answer 7: Working on having this changed. A help desk ticket has been submitted to the federal help desk to make the change.
| QUESTIONS AND ANSWERS FOR SOLICITATION W912LC-18-B-0001 |
| Question 2: Are you able to grant us access to download the plans and specifications? I entered a valid MPIN, but am not able to view the controlled documents. The DD2345 is approved. Please assist. |