Transformer Replacement Federal contract opportunity
Solicitation number
W912LA-19-Q-6051
Issued by
Department of the Army California Army National Guard

About this file

Solicitation

View the file

Other files for this federal contract opportunity

Other files attached to Transformer Replacement, newest first.
File Type Posted
W912LA19Q6051_0002_(Amendment).pdf PDF
SOW_with_Specifications,_Replace_Transformer_P167.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F6W2LG9214A003

The 144th Fighter Wing - Fresno Air National Guard Base is seeking a transformer replacement and light excavation. The solicitation W912LA-19-Q-6051 is 100% set aside for small business IAW DFARS 219.502-2(a(i). If there is an after hour point of contact, please include in the quote.

The North American Industry Classif ication System (NAICS) code is 238210 and the small business size standard is $15.0M. The disclosure of magnitude for this project is betw een $25,000 and $100,000 IAW FAR 36.204(b).

An organized site visit w ill be offered to all interested parties. The details are provided w ith FAR provision 52.236-27 Alternate I Site Visit (Construction).

JARROD SANCHEZ 559-454-5129

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

26-Aug-2019

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________30 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________23 Sep 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______10 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

144 BASE CONTRACTING OFFICE

5323 E MCKINLEY AVE

FRESNO CA 93727-2197

W912LA

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

559-454-5118FAX:TEL: 559-454-5129 TEL: FAX:

W912LA19Q6051 134

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section 00010 - Solicitation Contract Form

SECTION 00010

SECTION 00010 Solicitation Contract Form

TABLE OF CONTENTS

SOLICITATION, OFFER, AND AWARD SF 1442 and SF 1442 BACK

SECTION 00010 - PRICING SCHEDULE, NOTES

SECTION 00100 - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

SECTION 00600 – REPRESENTATIONS & CERTIFICATIONS

SECTION 00700 - CONTRACT CLAUSES

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

ATTACHMENT 1 – SOW with Specifications, Replace Transformer P167

SECTION 00010 NOTES

NOTES

1. Instructions for the preparation of proposals are located in Sections 00100, and 00120.

2. Offeror’s attention is invited to the insurance requirement contained in this solicitation (FAR Clause 52.228-5

Insurance – Work on a Government Installation). Certification of the required coverage for the prime contractor shall be furnished prior to beginning work on this contract, and the Contracting Officer may request evidence of the required insurance at any time during the life the contract.

3. Reference DFARS Provision 252.236-7008, Contract Prices – Bidding Schedules. The term “Bidding Schedule” shall also be construed to mean “Offer Schedule” or “Schedule”. The terms “bid” and “offer”, and “bidder” and “offeror” shall be construed as having the same meaning in this solicitation and resulting contract.

End of Section 00010

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

150KVA MINERAL OIL ELECTRICAL TRANSFORME

FFP

150KVA MINERAL OIL ELECTRICAL TRANSFORMER replacement in accordance with SOW.

FOB: Destination

PURCHASE REQUEST NUMBER: F6W2LG9214A003

SIGNAL CODE: A

PSC CD: N059

NET AMT

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 30 dys. ANP 1 144 MAINTENANCE GROUP - F6W2LG

ANGELA BARBE

5323 E.MCKINLEY AVE.

FRESNO CA 93727

559-454-5299 FOB: Destination

F6W2LG

Section 00100 - Bidding Schedule/Instructions to Bidders

SECTION 00100

Section 00100 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

1. SCOPE

1.1. You are invited to submit a proposal in response to our Request for Proposal W912LA19Q6051 for Project No. HAYW192108 at 144FW ANGB. As a result of this solicitation, the Government intends to award a single Firm Fixed Price (FFP) contract to the responsible offeror whose proposal represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.

1.2. This solicitation is set-aside 100% for small businesses.

2. NOTICE OF PRE-PROPOSAL CONFERENCE

Not Applicable

3. FORMAL COMMUNICATION, OFFEROR EXPLANATIONS

3.1. Submit all questions via email to the contracting office at the address shown below. Do NOT contact the A-E or Engineering personnel directly. Doing so will only delay the response to your question.

Subject Line: Reference No. W912LA19Q6051, Replace Transformer P167.

Email: jarrod.a.sanchez.mil@mail.mil

INQUIRIES SHALL BE SUBMITTED VIA EMAIL AND INCLUDE THE FOLLOWING INFORMATION:

Date of Proposal Inquiry:

From: ______________________________

Company Name: ___________________________

Phone Number: ____________________________

Email address: _____________________________

Proposal Inquiry: Be specific as to part of solicitation you are questioning.

3.2. Any explanation desired by an offeror regarding the meaning or interpretation of the solicitation, or proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach offerors before the submission of their offer.

3.3. The Contracting Officer reserves the right to address questions received after the fifth day prior to solicitation closing with those offers deemed compliant and/or in the competitive range after closing. All questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to closing and will be posted not later than two working days prior to closing. OFFERORS ARE STRONGLY ENCOURAGED

TO SUBMIT QUESTIONS EARLY IN THIS PROCESS.

3.4. Any interpretations made will be in the form of an amendment of the solicitation, drawings, specifications, etc., and will be furnished to all prospective offerors via posting to www.fbo.gov.

3.4.1. Receipt by the offeror must be acknowledged in the space provided on the SF 1442 or by returning a signed copy of the amendment by the time set for receipt of proposals. Explanations or instructions given in a form other than an amendment to the solicitation shall not be binding. Questions (on a non-attribution basis) and answers shall be furnished to all prospective offerors via the web site.

3.4.2. For security reasons, all technical and engineering data related to this solicitation will be distributed using the Federal Business Opportunities (www.FedBizOpps.gov or www.fbo.gov) system. FedBizOpps is a web-based dissemination tool designed to safeguard acquisition-related information for all Federal agencies. Interested bidders/offerors must register with FedBizOpps before accessing the system. Registration instructions can be found on the FedBizOpps website at https://www.fbo.gov/?s=getstart. (Please note the registration for access to the secure site takes approximately 15 business days, so plan accordingly.)

3.4.2.2. Interested offerors must be registered in the System for Award Management (SAM). To register go to:

www.sam.gov. You will need your DUNS number to register. Instructions for registering are on the web page.

4. AMENDMENTS PRIOR TO DATE SET FOR RECEIPT OF PROPOSALS

4.1. The right is reserved, as the interest of the Government may require, to revise or amend, the specifications or drawings or both prior to and/or after the date set for receipt of proposals as necessary. Such amendments, if any, will be announced by an amendment or amendments to this Request for Proposal. All information relating to this RFP, including pertinent changes/amendments and information prior to the date set for receipt of proposals will be posted at www.fbo.gov.

4.2. Offerors are strongly cautioned to check this site frequently and to “refresh” their web page to ensure they have the latest information.

5. HAND CARRIED PROPOSALS/INVITATIONS

Not Applicable. Proposals must be e-mailed or mailed.

6. Bid Bonds

An Original Bid bond is required with submission of the proposal. The bid bond is due on the date as stated on the SF1442 block 13. The bid bond must be on a SF24 form. Rejection of a bid bond shall be in accordance with FAR 28.101-4 Noncompliance with bid guarantee requirements.

7. WAGE DETERMINATION

7.1. The Construction Wage Rate Requirements, formerly known as Davis Bacon Wage Rates, are applicable to this project. Current prevailing wage determination(s) at time of issuance of solicitation are CA20190018 for Fresno County, California.

In the event the current prevailing Wage Determination is changed by the Department of Labor prior to the closing date of the solicitation, the most current wage determination is in effect. Should the wage rate change after closing, but prior to award, the updated Wage Determination will be incorporated by amendment and issued to all offerors that have not been eliminated from the competition. If applicable, these offerors/contractors will be given a reasonable opportunity to provide revised proposals solely to amend proposals due to Wage Determination changes.

If the wage determination modification does not change any affected wage rates, then the provisions of FAR 22.404- 5(c)(4) will apply.

7.2. Applicable wage rates can be found at https://wdolhome.sam.gov/.

8. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

This RFP does not commit the Government to pay costs incurred in preparation and submission of initial and subsequent proposals or for other costs incurred prior to award of a formal contract.

9. REMOVAL OF SECTIONS AT TIME OF AWARD

Sections 00100, 00110, 00120, 00600 and all exhibits will be physically removed as a result of an award, but will be deemed to be incorporated by reference in that award.

10. DISPOSITION OF UNSUCCESSFUL PROPOSALS

In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful proposals. The Government will destroy extra copies of unsuccessful proposals. No destruction certificate will be provided.

11. INFORMATION REGARDING AVAILABILITY OF UTILITY SERVICES

It has been determined that all reasonable amounts of water, sewer and electrical utility services, where/if physically available, used in connection with this project will be furnished to contractor without cost. The offerors will take this into consideration when computing its offer. (FAR Clause 52.236-14, Availability and Use of Utility Services)

12. EXCEPTIONS

If the offeror takes exception to any of the requirements specified in this solicitation, the offeror shall clearly identify each such exception and include a complete explanation of why the exception was taken and what benefit accrues to the Government. All exceptions to the solicitation requirements (Sections 00010 through 00800) and supporting rationale shall be included in an addendum to the proposal and clearly labeled "Exceptions". An addendum is only required if the offeror takes exception to any requirement in the solicitation. (The Addendum does not have a page limitation, but shall only include information relevant to exceptions taken to the solicitation requirements.) The Government will assume an offeror takes no exceptions to any solicitation requirement if the offeror does not submit an Addendum identifying exceptions. Offerors are advised that solicitation requirements are not necessarily negotiable and such exceptions may render an offeror's proposal unacceptable and ineligible for award.

13. CLAUSES

13.1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.

13.2. Clauses and provisions in this document may not appear in consecutive order.

14. BRAND NAME REQUIREMENTS

Not Applicable

End of Section 00100

SECTION 00120

SECTION 00120 PROPOSAL EVALUATIONS AND BASIS FOR AWARD

1. GENERAL INFORMATION

1.1. This solicitation is for a Firm Fixed Price Contract. The Government intends to award a single contract to a qualified Small Business Offeror deemed responsible in accordance with the Federal Acquisition Regulation (FAR), whose proposal conforms to all the RFP's requirements and is judged to represent the Best Value to the Government in accordance with the evaluation scheme set out in this solicitation. The award will be made based on the lowest price, technically acceptable offer IAW the FAR 15.101-2. Best value is expected to result from selection of the technically acceptable proposal with the lowest evaluated price, with appropriate consideration given to the three (3) evaluation factors: Technical, Price, and Past Performance.

1.2. To arrive at a Best Value decision this acquisition will utilize the FAR Part 15.101-2 lowest price, technically acceptable process (LPTA) process. While the Government and the Source Selection Authority will strive for maximum objectivity, the evaluation process, by its nature, is subjective, and therefore, professional judgment is implicit throughout the entire evaluation process.

1.3. The source selection process will be conducted in accordance with FAR Subpart 15.3, Source Selection procedures. Offers will be evaluated using the criteria listed in “Evaluation Factors for Award.” Noncompliance with the RFP requirements may raise serious questions regarding an offeror’s technical ability, past performance and/or pricing and may be grounds to eliminate the proposal from consideration for contract award. Failure to include all information requested may adversely affect the evaluation. A proposal that merely reiterates or promises to accomplish the requirements of the RFP will be considered unacceptable. A proposal that is orderly and sufficiently documented will be easy for the Government to understand and will enable the Government to perform a thorough and fair evaluation.

1.4. The Contracting Officer will begin the evaluation process by conducting a proposal compliance review for all timely-received proposals for determination of basic proposal adequacy prior to providing the proposals to the evaluators. Failure to provide a complete proposal may result in the proposal being removed from further consideration for award. Failure to address any factor Technical, Past Performance and Price or any technical subfactor shall be grounds for elimination from evaluation and consideration for award.

1.5. Offerors must ensure that no pricing information is displayed in Volume 2, Technical and Past Performance Proposal.

1.6. Although the assessment of Past Performance as a specific evaluation factor is separate and distinct from the Determination of Responsibility required by FAR Part 9, Past Performance information obtained herein will be used during the Government’s responsibility determination. The Government also reserves the right to obtain additional information solely for the purpose of making a responsibility determination from all offerors after receipt of proposals. Requests for responsibility information do not constitute discussions.

1.7. The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer, in his/her sole discretion, later determines them to be necessary or appropriate. Further, the Government reserves the right to create or not to create a competitive range.

1.8. ENFORCEABILITY OF PROPOSAL: The proposal must set forth full, accurate and complete information as required by this solicitation. By submission of the offer, the Offeror agrees that all items proposed (if applicable e.g., key personnel, subcontractors, etc.) will be utilized for the duration of the contract and any substitutions shall require prior Contracting Officer's approval.

2. EVALUATION FACTORS FOR AWARD

2.1. The following evaluation factors and subfactors will be used to evaluate each proposal. Award will be made to the offeror whose proposal is most advantageous to the Government based upon an integrated assessment of the evaluation factors and subfactors described below.

Factor 1: The Technical factor is further divided into the following subfactors:

a. Experience and Capability

b. Construction Schedule

Evaluation of the offeror’s proposal shall address the acceptability of the response to each subfactor as it applies to the Plans and Specifications. A detailed explanation of the criteria for the evaluation is set forth in the “Evaluation Approach”, Paragraph C of this section. During evaluations of each proposal, the Government will assign each subfactor a rating of “Acceptable” or “Unacceptable” and write a narrative evaluation reflecting the identified findings. An offer which fails to provide information in any of the specified areas may be deemed Unacceptable, and eliminated from the competition and ineligible for further consideration.

Factor 2. Past Performance: Each offeror’s past performance will be reviewed to determine relevancy and acceptability

Factor 3. Cost/Price. The resulting award will be a firm fixed price contract type. Price Reasonableness will be utilized in the evaluation of the Firm-Fixed price effort.

All proposals shall be subject to evaluation by the Source Selection Evaluation Board (SSEB). The overarching evaluation approach for all factors and subfactors is to determine the acceptability of the response. The proposal will be evaluated to determine whether each requirement has been addressed in the proposal in order to meet the acceptability standards described in the RFP.

2.2. TECHNICAL PROPOSAL: TECHNICAL EVALUATION FACTOR RATINGS:

2.2.1. Technical Rating: Technical Capability will be evaluated on an Acceptable/Unacceptable basis. An offeror shall obtain an “Acceptable” rating to continue further in the competition. Offerors who are deemed to merit an “Unacceptable” rating in the Technical Capability Factor will be removed from further consideration for award.

Once the minimum requirements are established, the team shall evaluate the offeror's proposal against these requirements to determine whether the proposal is acceptable or unacceptable, using the ratings and descriptions outlined in Table below. Proposals are evaluated for acceptability, but not ranked using the non-price factors/subfactors. In order to be considered awardable, there must be an "acceptable" rating in every non-price factor/subfactor.

Adjectival Rating Description

Acceptable Proposal meets the requirements of the solicitation.

Unacceptable Proposal does not meet the requirements of the solicitation.

2.2.2. Subfactor 1 - Experience and Capability: Using the information in Technical Proposal, and the projects/contracts discussed and listed in the Exhibit As, the Government will evaluate the extent of related experience. To be deemed “Acceptable” the proposal must demonstrate experience and capability to perform a project of this magnitude and complexity.

2.2.2.2. The Government will evaluate the offeror’s understanding of the contract requirements, and determine to what degree their technical and administrative capabilities, proposed organization and management plan are acceptable to meet contract requirements. To be considered acceptable the Experience and Capability proposal will address the full spectrum of activities involved in the management of a resulting contract in a manner that gives the Government confidence that the offeror understands all of the requirements. An acceptable proposal will include the information necessary to give the Government confidence of the offeror’s ability to successfully perform complete project management of the scope requirements.

2.2.2.3. Proposal demonstrates, as a minimum, that the following key personnel: Project Manager, Site Superintendent(s), have experience in managing projects/contracts of the same/similar dollar magnitude, size, complexity and scope, in the capacity in which they are proposed for this project.

2.2.4. Subfactor 2 - Construction Schedule. To be considered acceptable, the schedule and narrative demonstrates an offeror’s understanding of the requirements. The Construction Schedule is an integrated and networked multi-layered schedule of program/project tasks. It identifies project events, accomplishment, and criteria and the expected dates of each. These dates are based on the calendar dates provided as the starting point and the logical flow of dates provided by calculating the addition of duration of all tasks using typical schedule networking tools. Each major task will be directly traceable to the requirements of the project. The NTP date for the schedule is for the purpose of evaluation only.

2.3. PAST/PRESENT PERFORMANCE EVALUATION

2.3.1. The Government will evaluate the offeror’s record of past and current performance to ascertain the probability of successfully performing the required efforts of the Plans and Specifications.

2.3.2. The past performance evaluation is an assessment of the offeror's probability of meeting the minimum past performance solicitation requirements. This assessment is based on the offeror's record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. The Past/Present Performance evaluation will consider such things as an offeror's business practices, customer relationship, ability to successfully perform as proposed, and other considerations as described in Past/Present Performance Sub-factors, elements and other considerations. Past/Present Performance includes current/on-going (present) performance complete to 70% percent. Projects currently in progress for the National Guard will also be considered regardless of percentage complete. In assessing performance confidence, the evaluator may: (1) evaluate present and past performance information through the use of questionnaires completed by the offeror's references; (2) use data independently obtained from other Government or commercial sources; from any other sources available to the Government, to include, but not limited to, the Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), or other databases; (3) interviews with Program/Project Managers, Contracting Officers or rely upon personal business experience with the offeror; (4) the information provided in the Offeror’s Past Performance Relevancy Questionnaire; and (5) consider any information the offeror submits which explains any problems encountered on the identified contract and the offeror's corrective actions. The Government reserves the rights to obtain and evaluate past performance information from any source it deems appropriate.

2.3.3. The evaluation may take into account Past/Present Performance information regarding predecessor companies, key personnel who have relevant experience or subcontractors that will perform major or critical aspects of the requirement when such information is relevant to this acquisition. The evaluation will also consider information provided relative to corrective actions taken to resolve problems on past or existing, contracts.

2.3.4. An offeror with no relevant Past/Present Performance may receive a rating based on the evaluation of its predecessor companies, key personnel, and/or subcontractors provided the offeror clearly states in the proposal that the information provided about predecessor companies, key personnel, and/or subcontractors is for the purposes of enhancing the offerors past performance proposal. These ratings may not have the same weight as the ratings of the proposing company. The weight that will be afforded for this type of past performance is within the sole discretion of the Government. If such information is not applicable (i.e., the offeror does not have a predecessor company, key personnel or subcontractors with relevant experience), the offeror shall be evaluated as Neutral. However, the proposal of an offeror with no relevant Past/Present Performance history, while rated Neutral in Past Performance, may not represent the most advantageous proposal to the Government and thus, may be an unsuccessful proposal when compared to the proposal of other offerors.

NOTE: In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a)(2)(iv)). Therefore, the offeror shall be determined to have unknown (or "neutral") past performance. In the context of acceptability/unacceptability, a neutral rating shall be considered acceptable.

2.3.5. In accordance with FAR 15.306(a)(2), if award will be made without conducting discussions, offerors may be given the opportunity to clarify certain aspects of their proposals, e.g., the relevance of an offeror's past/present performance information and adverse past/present performance information to which the offeror has not previously had an opportunity to respond or to resolve minor clerical errors.

The past performance evaluation is an assessment of the offeror’s probability of meeting the minimum past performance solicitation requirements. This assessment is based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements.

2.3.6 “Current” means performance occurring within the last five (5) years for the period beginning five years prior to the solicitation release date. Within this period, performance occurring later in the period may have greater significance than work occurring earlier in the period.

2.3.6.1. In assessing “relevancy” of an offeror’s previous contracts the Government may evaluate an offeror’s past performance for similarity of the construction methods, size, project scope, cost magnitude and complexity of work performed to those required for the proposed effort. The Government may also consider similarity of the client type (e.g. federal government) and/or the projects sustainability requirements. ANG projects will consider United States Green Building Council (USGBC) LEED®. The location at which work was performed may also be considered.

Relevancy weight will affect offeror’s overall Past Performance Confidence rating. The more relevant the project is weighted the greater confidence there will be in the past performance assessment as a predictor of future performance.

2.3.7. The following apply to weighting relevancy considering all the elements listed above;

Past Performance Relevancy Ratings Rating Definition

Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

Offerors who otherwise have satisfactory performance on previous construction projects may be rated “Unknown Confidence” (Neutral) if those projects are not considered relevant to the proposed acquisition and relevancy cannot be obtained through the evaluation of key personnel and/or subcontractors. Projects that are not current will not be considered in the evaluation.

2.3.8. The following ratings and related definitions will be used to define the performance confidence assessment.

Based on the evaluation results, the evaluators will assign the Past Performance factor one of the ratings as defined below.

NOTE: In the case of an offeror without a record of relevant past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305(2)(iv)). Therefore, the offeror shall be determined to have unknown (or neutral) past performance. In the context of acceptability/unacceptability, a neutral rating shall be considered "acceptable".

Adjectival Rating Description

Acceptable Based on the offeror's performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror's performance record is unknown. (See note above)

Unacceptable Based on the offeror's performance record, the Government does not have a reasonable expectation that the offeror will be able to successfully perform the required effort.

3. PRICE EVALUATION

3.1. This contract is a firm fixed price contract. Price is not rated. The purpose of the price/cost evaluation is to determine whether an offeror's proposed prices/costs for the project are determined to be fair and reasonable in comparison to the competition, the current market conditions and/or recent prices for the same or similar requirements. Reasonableness of an offeror's proposal is evaluated through cost or price analysis techniques as described in FAR Subpart 15.305(a)(1) and (4).

3.2. All offers will be analyzed to determine if the prices are unbalanced (FAR 15.404-1(g)). Offers may be rejected if it is determined the lack of balance poses an unacceptable risk to the Government.

3.3 The Government will examine price proposals for artificially low unit prices. Offers found to be unreasonably high or unrealistically low (an indication of a “buy-in”) may be considered unacceptable and may be rejected on that basis.

3.4. The Government reserves the right to obtain additional information concerning the price (cost) as necessary to obtain a better understanding of the price proposed. No proposal revisions will be allowed under these conditions.

Request for such information is for clarification purposes only. This does not constitute and shall not be construed as discussions. If a minor clerical error has occurred, in which case the offeror may be given an opportunity to correct the minor error within the constraints of the "clarifications" process or the Contracting Officer in his/her sole discretion later determines discussions to be necessary or appropriate.

3.5. In the event the Government does not award a contract pursuant to this solicitation within 90 calendar days after receipt of proposals and award will be made without discussions, the following will apply:

3.5.1 The Government reserves the right to allow offerors to make an adjustment in their price proposals to accommodate cost changes caused by fluctuating construction material market conditions. The Contracting Officer will notify Offerors, normally by electronic mail (email) of a common closing date for receipt of the adjusted price proposals. No additional proposal revisions will be allowed under these conditions. This does not constitute and shall not be construed as discussions. If a minor clerical error has occurred, in which case the offeror may be given an opportunity to correct the minor error within the constraints of the "clarifications" process or the Contracting Officer in his/her sole discretion later determines discussions to be necessary or appropriate.

3.6. In the event the current prevailing Wage Determination is changed by the Department of Labor after the closing date of this solicitation, the updated Wage Determination will be incorporated by amendment and issued to all offerors that have not been eliminated from the competition. If applicable, these offerors/contractors will be given a reasonable opportunity to provide revised proposals solely to amend proposals due to Wage Determination changes. This does not constitute and shall not be construed as discussions if award without discussions is contemplated.

4. AWARD and DEBRIEFINGS

4.1. Award: A written award or acceptance of offer mailed, or otherwise furnished to the successful offeror within the time for acceptance specified in the offer shall be deemed to result in a binding contract without further action by either party.

4.2. Debriefings

4.2.1. Offerors excluded from the competitive range or otherwise excluded from the competition before award may submit a written request for a debriefing to the Contracting Officer in accordance with FAR 15.505.

4.2.2. After award, unsuccessful offerors may submit a written request for a debriefing to the Contracting Officer in accordance with FAR 15.506.

End of Section 00120

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.204-22 Alternative Line Item Proposal JAN 2017 52.216-1 Type Of Contract APR 1984 52.222-5 Construction Wage Rate Requirements--Secondary Site of the

Work

MAY 2014

52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction

FEB 1999

52.225-10 Notice of Buy American Requirement--Construction Materials

MAY 2014

52.233-2 Service Of Protest SEP 2006 52.236-28 Preparation of Proposals--Construction OCT 1997 252.204-7008 Compliance With Safeguarding Covered Defense Information

Controls

OCT 2016

CLAUSES INCORPORATED BY FULL TEXT

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-- Thursday, September 5 at 9:00am

(c) Participants will meet at-- West Gate of the Fresno Air National Guard Base

5323 E McKinley Ave Fresno, CA 93727

(End of provision)

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil/ https://www.acq.osd.mil/dpap/

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

Section 00600 - Representations & Certifications

52.203-18 Prohibition on Contracting With Entities That Require Certain

Internal Confidentiality Agreements or Statements-- Representation

JAN 2017

52.204-8 Annual Representations and Certifications OCT 2018 52.204-19 Incorporation by Reference of Representations and

Certifications.

DEC 2014

52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.

AUG 2018

52.236-28 Preparation of Proposals--Construction OCT 1997 252.203-7005 Representation Relating to Compensation of Former DoD

Officials

NOV 2011

252.204-7007 Alternate A, Annual Representations and Certifications JUN 2019 252.204-7008 Compliance With Safeguarding Covered Defense Information

Controls

OCT 2016

Section 00700 - Contract Clauses

52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

OCT 2018

52.204-13 System for Award Management Maintenance OCT 2018 52.204-19 Incorporation by Reference of Representations and

Certifications.

DEC 2014

52.204-21 Basic Safeguarding of Covered Contractor Information Systems

JUN 2016

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities.

JUL 2018

52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment.

AUG 2019

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

AUG 2019

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

OCT 2015

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015

52.222-3 Convict Labor JUN 2003 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records AUG 2018 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and

Related Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for

Construction

APR 2015

52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-50 Combating Trafficking in Persons JAN 2019 52.223-6 Drug-Free Workplace MAY 2001 52.223-18 Encouraging Contractor Policies To Ban Text Messaging

While Driving

AUG 2011

52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright

Infringement

DEC 2007

52.228-2 Additional Bond Security OCT 1997 52.228-11 Pledges Of Assets AUG 2018 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.228-13 Alternative Payment Protections JUL 2000 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-8 Discounts For Prompt Payment FEB 2002 52.232-11 Extras APR 1984 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017

52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

DEC 2013

52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-21 Specifications and Drawings for Construction FEB 1997 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.244-6 Subcontracts for Commercial Items AUG 2019 52.249-2 Alt I Termination for Convenience of the Government (Fixed-

Price) (Apr 2012) - Alternate I

SEP 1996

52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber

Incident Reporting

OCT 2016

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

MAY 2016

252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials

SEP 2014

252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7048 Export-Controlled Items JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

DEC 2018

252.232-7006 Wide Area WorkFlow Payment Instructions DEC 2018 252.232-7010 Levies on Contract Payments DEC 2006 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.244-7000 Subcontracts for Commercial Items JUN 2013

Section 00800 - Special Contract Requirements

WAGE DETERMINATIONS - DBA

"General Decision Number: CA20190018 07/26/2019

Superseded General Decision Number: CA20180029

State: California

Construction Types: Building, Heavy (Heavy and Dredging) and Highway

Counties: Alameda, Calaveras, Contra Costa, Fresno, Kings, Madera, Mariposa, Merced, Monterey, San Benito, San Francisco, San Joaquin, San Mateo, Santa Clara, Santa Cruz, Stanislaus and Tuolumne Counties in California.

BUILDING CONSTRUCTION PROJECTS; DREDGING PROJECTS (does not include hopper dredge work); HEAVY CONSTRUCTION PROJECTS (does not include water well drilling); HIGHWAY CONSTRUCTION PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.60 for calendar year 2019 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.60 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2019. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/04/2019 1 02/01/2019 2 02/15/2019 3 02/22/2019 4 05/03/2019 5 07/26/2019

ASBE0016-004 01/01/2019

AREA 1: CALAVERAS, FRESNO, KINGS, MADERA, MARIPOSA, MERCED,

MONTEREY, SAN BENITO, SAN JOAQUIN, SANTA CRUZ, STANISLAUS &

TOULMNE COUNTIES

AREA 2: ALAMEDA, CONTRA COSTA, SAN FRANSICO, SAN MATEO & SANTA

CLARA COUNTIES

Rates Fringes

Asbestos Removal worker/hazardous material handler (Includes preparation, wetting, stripping, removal, scrapping, vacuuming, bagging and disposing of all insulation materials from mechanical systems, whether they contain asbestos or not) Area 1......................$ 28.20 9.27 Area 2......................$ 36.53 9.27

ASBE0016-008 01/01/2019

AREA 1: ALAMEDA, CONTRA COSTA, MONTEREY, SAN BENITO, SAN

FRANSICO, SAN MATEO, SANTA CLARA, & SANTA CRUZ

AREA 2: CALAVERAS, COLUSA, FRESNO, KINGS, MADERA, MARIPOSA,

MERCED, SAN JOAQUIN, STANISLAU, & TUOLUMNE

Asbestos Workers/Insulator (Includes the application of all insulating materials, Protective Coverings, Coatings, and Finishes to all types of mechanical systems) Area 1......................$ 68.11 23.32 Area 2......................$ 43.81 31.22

BOIL0549-001 10/01/2016

AREA 1: ALAMEDA, CONTRA COSTA, SAN FRANCISCO, SAN MATEO & SANTA

CLARA COUNTIES

AREA 2: REMAINING COUNTIES

BOILERMAKER

Area 1......................$ 43.28 37.91 Area 2......................$ 39.68 35.71

BRCA0003-001 08/01/2017

Rates Fringes

MARBLE FINISHER..................$ 32.60 15.31

BRCA0003-003 08/01/2017

Rates Fringes

MARBLE MASON.....................$ 44.60 26.83

BRCA0003-005 05/01/2017

Rates Fringes

BRICKLAYER

( 1) Fresno, Kings, Madera, Mariposa, Merced....$ 38.45 21.22 ( 7) San Francisco, San Mateo.......................$ 42.34 25.83 ( 8) Alameda, Contra Costa, San Benito, Santa Clara.......................$ 44.16 21.71 ( 9) Calaveras, San Joaquin, Stanislaus, Toulumne....................$ 39.66 20.76

(16) Monterey, Santa Cruz...$ 39.51 23.49

BRCA0003-008 09/01/2017

Rates Fringes

TERRAZZO FINISHER................$ 35.14 16.87

TERRAZZO WORKER/SETTER...........$ 44.11 26.36

BRCA0003-011 04/01/2018

AREA 1: Alameda, Contra Costa, Monterey, San Benito, San Francisco, San Mateo, Santa Clara, Santa Cruz

AREA 2: Calaveras, San Joaquin, Stanislaus, Tuolumne

AREA 3: Fresno, Kings, Madera, Mariposa, Merced

TILE FINISHER

Area 1......................$ 28.56 15.87 Area 2......................$ 25.60 14.30 Area 3......................$ 25.88 15.17

Tile Layer Area 1......................$ 47.77 18.29 Area 2......................$ 42.67 16.81 Area 3......................$ 38.15 17.70

CARP0022-001 07/01/2018

San Francisco County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 48.40 29.32 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 48.55 29.32 Journeyman Carpenter........$ 48.40 29.32 Millwright..................$ 48.50 30.91

CARP0034-001 07/01/2018

Rates Fringes

Diver Assistant Tender, ROV Tender/Technician...........$ 47.65 32.52 Diver standby...............$ 52.61 32.52 Diver Tender................$ 51.82 32.52 Diver wet...................$ 97.17 32.52 Manifold Operator (mixed gas)........................$ 56.82 32.52 Manifold Operator (Standby).$ 51.82 32.52

DEPTH PAY (Surface Diving):

050 to 100 ft…