HAYW172853_-_Install_Flush_Mount_Tire_Shredders_Base_Gates_SOW.pdf

PDF 149 KB Posted

Attached to
Flush Mounted Tire Shredders
Solicitation number
W912LA-18-T-6053
Issued by

View the file

Other files

File Type Posted
CAPABILITIES_QUESTIONNAIRE.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

BUILDING 133 and 136 – INSTALL FLUSH MOUNT TIRE SHREDDERS

PROJECT NO.: HAYW172853

05 June 2017

144TH FIGHTER WING

CALIFORNIA AIR NATIONAL GUARD, FRESNO

TECHNICAL PROVISIONS

TABLE OF CONTENTS:

DESCRIPTION OF SERVICES

SITUS OF WORK

STATEMENT OF WORK

CONTRACTOR LICENSE REQUIREMENTS

PROJECT SPECIFIC REQUIREMENTS

GENERAL REQUIREMENTS

SUBMITTALS

CLOSEOUT DOCUMENTATION

DESCRIPTION OF SERVICES

This statement of work describes contractor requirements for the project titled “Building 133 and 136 – Security Forces- Install Flush Mount Tire Shredders at Base Gates”. All work will occur at the Fresno Air National Guard Station, Fresno, California. The contractor is responsible to furnish and install all labor and materials to complete the items listed in this Statement of Work. The contractor shall provide the government a complete and usable product that will be inspected/accepted by the government at the completion of the project. All information included in this document, along with the instructions and standards referenced in the document, should be considered as part of the Statement of Work.

SITUS OF WORK

All work will occur at the Fresno Air National Guard Station 5323 McKinley Ave, Fresno, CA. 93727

STATEMENT OF WORK

1. Objectives: The purpose of this project is to remove the existing surface mount tire shredders at the outbound lanes at the Main Gate and West Gate. Install new Flush Mount Tire Shredders at the outbound lanes of the Main Gate and West Gate.

2. Directions:

2.1. Complete all work according to the manufacturer’s specifications.

2.2. Flush Mount Tire Shredder shall have a lock down function and be rated vehicle weight of not less than 40,000 lbs. per single axle load.

2.3. Install 18’ section of Flush Mount Tire Shredders at the outbound gate of Building 133.

2.4. Install 12’ section of Flush mount Tire Shredders at the outbound gate of Building 136.

2.5. The locations of the new Flush Mount Tire Shredders will be placed where the removed Surface mount Tire Shredders are currently located.

2.6. Install Flush mount Tire Shredders with the hardware that the manufacture recommends along with the epoxy recommended by the manufacture for installation.

2.7. Install any base rock material or concrete as needed to ensure proper installation per manufacture specifications.

2.8. Reroute any Electrical, Communication or Utilities that will be impacted for the installation of the new Flush Mount Tire Shredders.

3. Demolition

3.1. Contractor must remove all asphalt and earth material off of 144th property and properly dispose.

3.2. Remove existing surface mount tire shredders and return to the 144th Civil Engineering Squadron in Building 125.

3.3. Saw, cut, and remove asphalt as needed to allow the new Flush Mount Tire Shredders to fit per manufactures specifications.

4. Finishing

4.1.1. Contractor will test to ensure all shredder devices lock-down securely and operate as designed.

CONTRACTOR LICENSE REQUIREMENTS

1. The contractor will possess a valid California “A” or “B” license and be able to provide proof of competence in the area of work. The contractor may self-perform sections of the project.

2. All listed sub-contractors working for the contractor will possess the applicable California Contractors license. Refer to the Project Specific Requirements section for the required license from the Contractor.

PROJECT SPECIFIC REQUIREMENTS

1. The contractor will possess a valid California “A” or “B” license and be able to provide proof of competence in the area of interior remodels and masonry. The contractor may self-perform sections of the project.

2. All subcontractors working for the contractor will possess the applicable California Contractors license. For example, the contractor must be able to provide a contractor C- 21 or C-32 licenses.

3. The project will be completed no later than 30 working days post Notice to Proceed (NTP).

Moving furniture and removal/replacement of wall hung items such as bulletin boards is the responsibility of the government. Cabinets and fixtures will remain in place during the project. The contractor and government will negotiate the final phasing (if applicable), and schedule during a review of the project at the pre-construction conference.

4. Materials. The following lists out materials requirements for this project. Contractor may request substitutes for an approved equal during the pre-construction conference. All substitution requests shall be made in writing on the AF Form 3000. Requests for material substitutions made after the pre-construction conference may not be granted by the Government.

a. Flush Mount Tire Shredders

b. Epoxy

c. Hardware for Flush Mount Tire Shredders

d. Concrete 3000 PSI

e. Base Course

f. Manuals

GENERAL REQUIREMENTS

1 When required, the Contractor will attend a Pre-Construction Conference. The Pre- Construction Conference will generally be scheduled after award but prior to the NTP. At a minimum, the contractor shall have their project manager and site superintendent attend the meeting. The Contractor will provide the following documents at the Pre- Construction Conference

a. Project Schedule

b. Contract Schedule of Values

c. Safety Plan

d. Quality Control Plan

e. Material Submittals

f. Safety Data Sheets

g. Draft DD 1354 – Final draft to be submitted at conclusion of project

h. AF 103 – Dig Permit

2 Government Furnished Property and Services. The government will provide water, sewer and electrical connections. Unsecure outdoor storage area at the base is available and must be requested through the project manager prior to utilizing. Secured storage is the responsibility of the contractor.

3 Quality Control. Contractor shall develop and maintain a quality program to ensure work is performed as described in this Statement of Work and in accordance with all local, state and federal rules.

4 Quality Assurance. The Government will maintain a Quality Assurance Program to ensure work is performed as described in this Statement of Work and in accordance with all local, state, and federal rules. The Project Manager will manage the Government’s QA program.

5 Hours of Operation. The hours of work shall be between 7:00 a.m. and 5:00 p.m. Monday through Friday unless otherwise prescribed by this statement of work. Work shall not be performed on Weekends and Federal Holidays without prior coordination from the Project Manager.

6 Base Access. Base security personnel require that all personnel entering the installation are cleared for access. The contractor will provide first name, last name, driver’s license number and applicable vehicle data for all personnel accessing the base. The contractor shall submit this information to the base Contracting Office NLT two working days prior to the date of required access. Personnel must maintain a valid driver’s license, vehicle registration and proof of insurance at all time while on the base.

7 The Contractor, and all listed sub-contractors, must be licensed within the State of California. Refer to the Project Specific Requirements section for the required license from the Contractor.

8 Technical Competence and Ability. If requested by the Government, the Contractor shall provide proof of technical competence and experience in the area of expertise required by this Statement of Work. The contractor shall be prepared to submit documents providing proof of successful competence such as training certificate or accreditations from recognized industry leaders. Contractors shall also be prepared to provide proof of successful project experience through references of former clients in related project types.

9 Dimensions and Quantity. All dimensions and quantities provided in the Statement of Work are estimates only. They are provided as a courtesy for contractors to estimate the magnitude of work or materials necessary to complete a task. They are not intended to be final measurements. The Contractor is responsible for verifying all dimensions and quantities in the field prior to starting work.

10 Submittals. All submittals will be transmitted with an AF Form 3000. When submitting on a finish, texture or other material characteristic where a photograph is unacceptable, the Contractor will provide a sample of the material for review and approval along with the product cut-sheet.

11 Warranty. The contractor shall guarantee all workmanship and materials covered under this statement of work for a period of no less than one (1) year from the date of project acceptance. This contractor’s warranty shall be included with any manufacturer’s warranties that accompany materials or systems installed as part of this statement of work.

SUBMITTALS

All submittals will be transmitted with an AF Form 3000. When submitting on a finish, texture or other material characteristic where a photograph is unacceptable, the Contractor will provide a sample of the material for review and approval along with the product cut-sheet.

CLOSEOUT DOCUMENTATION

• 10% Retainage will be released upon receipt of the following items:

Contractor workmanship letter of warranty up to one year.

Certificates of no debts to suppliers and vendors.

Electronic pictures showing the area before and after repair.

Recycling or Landfill proof of disposition document (if available).

All applicable O&M manuals.

DESCRIPTION OF SERVICES
SITUS OF WORK
STATEMENT OF WORK
CONTRACTOR LICENSE REQUIREMENTS
SUBMITTALS
CLOSEOUT DOCUMENTATION

File details come from the government source that posted it.