This document is an amendment to a solicitation (W912L9-24-R-0006) for an outdoor fiber optic cable project at Camp Atterbury, Indiana. The solicitation is a small business set-aside request for quotation with a NAICS code of 238210 (IT and Telecom Electrical Contractors and Other Wiring Installation Contractors).
The key details are:
- The contract is for fiber optic line updates and installations at Camp Atterbury, with a firm-fixed price contract type.
- A site visit is planned for May 16, 2024, which is not mandatory. Questions are due by May 20, 2024, and quotes are due by May 30, 2024.
- The amendment provides answers to 23 questions received, covering topics such as fiber specifications, pedestal/cabinet details, testing requirements, and work scheduling.
- Award will be made based on Lowest Price Technically Acceptable evaluation.
- Contractors must be registered in SAM and WAWF/iRAPT and be in good standing.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912L9-24-R-0006 Amendment 2.pdf | ||
| W912L9-24-R-0006 SOLICITATION.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE SCHEDULE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment #3 provides additional information to answ er specific questions.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 28-May-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912L924R0006
X 9B. DATED (SEE ITEM 11)
24-Apr-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-May-2024
CODE
USPFO FOR INDIANA-CAMP ATTERBURY
BLDG 244 EGGLESTON RD
EDINBURGH IN 46124
W912L9 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912L924R0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS AND ANSWERS
Questions for Commo Project W912L9‐24‐R‐0006
1. Is attendance at the scheduled site visit on May 16, 2024, mandatory for all bidders?
Answer: No, site visit was not required.
2. The RFQ lists the job completion date as May 18, 2024, on page 17, item number 3. Do you have updated date? Answer: Bid due date will be updated.
3. Could you specify how many channels each TFOCA connector needs to support?
A: There is 4 strands per TFOCA. There will be 2 TFOCA connects at each ped.
4. Statement of work references Clearfield vault and cabinets. Is there a specification on these that you can provide. Clearfield has a bunch of options and this will be needed to secure proper pricing. A: The size of the Clearfield vault and cabinet is 36hx18wx17d. It’s a single door cabinet, with a 72 strand bulkhead in it. The spice for the fiber will be done into a closure (coyote or what ever) in the bottom of the vault. You will bring 12 strands up to the bulkhead, terminated.
5. Do you have a specification on the single mode fiber cable. IE: Manufacture and or part number. A: It’s a 72 strand SM fiber cable, that has a sheath in it for grounding purpose.
We use corning.
6. Is this project prevailing wage? No, this is a supply contract with installation of cable.
7. Will permitting for digging be required and will private locates be needed?
A: We have permission for the digging. You are responsible for your own locates.
8. Will there be specific days and times of the week that work can be performed.
A: Work can be performed 7 days a week as long as it doesn’t interfere with training.
9. Is there a staging area for the crews to utilize during the construction period.
A: Yes, that will be directed by Range Control.
10. Is there a specific OTDR testing equipment requirement and any specific format for
OTDR test reports.
A: You can provide the report on the Asbuilt or send it to us through E‐Mail. The OTDR should show us the total route of every connection and the DB loss, etc.
11. Do all spare fibers terminated for future use? A: In the first Pedestal going east, the splice will be done in this Ped. You will only be splicing the 12 strands that goes west, which will be the white tube (60‐ 72). Also, in this Ped. you will be splicing the blue tube (1‐12) to the bulkhead. The orange tube (13‐24) will be spiced to the second ped. going east. The green tube (25‐36) will be splice into the third ped. going east. The brown tube (37‐48) will be splice into the fourth ped. going east. The slate tube (49‐60) will be in the fourth ped. not spliced for future Ped.
W912L924R0006
12. Is there a drawing or document showing drop count at each location from the 144ct and the 48ct.
A: Refer to question #11
13. ‐What will the specification for the 6‐pedestals be?
A: Refer to question # 4
14. ‐What will the specification for the cabinet be?
A: The ped/cabinet are the same in the field. In the como rooms you will be using the same cabinet that’s in place.
15. ‐We will be replacing the 3‐existing handholes with large to accommodate the 50 foot fiber loops. What size do they need to be?
A: The size will be 30x48x36, tier 22
16. ‐While we are there can both jobs be completed at the same time?
A: Yes, they can, as long as there is no problem with exercises going on at either place.
17. At FOB 3 ‐ HH3 will there be a splice to run fiber both directions to the peds?
A: There will be no splicing in HH3, it will be done in 1st ped going east (ped1).
18. At FOB 3 ‐ Can the 72 fiber be ran between the building to keep from having two different fibers?
A: Yes you can
19. PED Wrap ‐ Would D.O.T. tape stripping work?
A: would prefer vinyl wrap but D.O.T. tape stripping works. It’s for visibility.
20. TFOCA CONNECTION ‐ Is this a 4 channel Single Mode 7.5 mm Tactical cable assembly?
Please provide a part number.
A: Part # D‐004CSLS5KM, the web site is www.occfiber.com, the SN is 0297670004.
This is a 4 channel Single Mode optical cable
21. ‐Does anyone have the part number for the Clearfield Ped/vault?
A: Refer to question # 4 please
22. Does the Rail Head ped need the TFOCA connector?
A: Yes, it does. Same as Fob 3.
23. Is this project a Prevailing wage scale? No, this is a supply contract with installation of cable.
(End of Summary of Changes)