Statement of Work Communications Install (Inside Plant) Bldg. 635 Ft. Sill Project
XHZG-09-0001
Ref: Request for Purchase # F9L3SX0231AC01
PART 1 – GENERAL
| 1.01 | DESCRIPTION OF WORK: |
| A. | The extent of the communications CAT-6 / Fiber Optic install within Bldg. 635 at Ft. Sill, OK is indicated by drawings and the requirements set forth by the Technical Criteria for Information Installation Infrastructure (I3A Tech. Criteria) and TIA-EIA-606-A per U.S. Army Information Systems Engineering Command. Requested communication install completion date NLT 15 October 2010. |
| B. | Pull cable through 1” Conduit/3000 Series Wiremold and terminate 72 Quad Jack Outlets (2 Voice / 2 Data per Outlet) in designated locations (1-Basement, 32-1st Floor, 39-2nd Floor). Complete terminations for all communication cabling in Telecommunication Room (TR) designated on first floor of Bldg. 635. |
| C. | Contractor shall provide a complete working network infrastructure, to include all terminations to 8 pin-modular connectors/Patch panels, installation of wire management as required by this section and obtained drawings. These materials are Government-Furnished and Contractor-Installed. |
| D. | Hazardous Locations: Areas identified as such will be defined in the design package and verified by Ft. Sill Directorate of Public Works (DPW). Disposal of waste materials shall be accomplished by the installer per I3A Tech Criteria para 3.4. Environmental and Historical Considerations. |
| 1.02 | QUALITY ASSURANCE: |
| A. | Products: Catalog and model numbers are intended to indicate type and quality of design and material as well as exact operating features required. |
| B. | Acceptable Manufacturers: |
Leviton Siemons Beldin CommScope Superior Essex Panduit
| C. | Installer: A firm with at least five (5) years of successful communication installation experience on projects with work similar to that required for this project. |
| D. | Compliance: Comply with National Electrical Code (NFPA No. 70), I3A Technical Criteria (Feb 2010), and TIA/EIA-606-A (May 2002). Special condition shall be discussed with Ft. Sill Contractor Network Enterprise Center (NEC), and agreements shall be document per I3A Tech Criteria para 3.4.1. |
| E. | UL and Labels: Provide labeling for all terminations and pathways as indicated in TIA/EIA-606-A. As a minimum all outlet/patch panels shall be labeled with room numbers and alpha/numeric designator. Labeling shall be a minimum of ¼ inch (6mm) high. Hand written labels shall not be used for final configuration. |
| 1.03 | SUBMITTALS: |
| A. | Manufacturer’s Data: Submit manufacturer's data on all purchased equipment. |
| B. | Shop Drawings: Submit dimensioned (3) 2’X3’ drawings of installed cabling and system equipment showing accurately scaled basic units. PDF format preferred if available. |
| C. | Include with shop drawings a riser, wiring diagrams, and specification data sheets. Submittals indicating typical single line risers and typical specification sheets only will not be acceptable. |
| 1.04 | DELIVERY, STORAGE AND HANDLING: Handle communication equipment carefully to prevent internal components damage, breakage, and denting and scoring the enclosure finish. Do not install damaged equipment. Store equipment in a clean dry space. Protect from dirt, fumes, water, construction debris and physical damage. |
PART 2 - PRODUCTS
| 2.01 | MATERIALS AND EQUIPMENT: |
| A. | General: Except as otherwise indicated, provide manufacturer's standard materials and components as indicated by their published product information, designed and constructed as recommended by the manufacturer, and as required for a complete installation. |
| B. | Materials (Cabinets, cabling, outlet faceplates, 8-pin modules, and patch panels) located in storage warehouse north of Bldg 635 is solely for use in Bldg 635 for this contract. Cabling and termination end equipment will be Government-Furnished and Contractor-Installed. |
| C. | Gray and Blue CAT-6 Plenum Rated UTP: |
| 1. | Gray CAT-6 cable with Gray 8-pin modular connectors will be utilized for voice and Blue CAT-6 with White 8-pin modular connectors for data. Contactor will use Siemon faceplates with colored coded device designator labels (Gray phone – Voice, Blue monitor – Data). Materials furnished by Government, installed by Contractor. |
| 2. | 2 - Standard 19U enclosed cabinets will be designated to separate voice and data. Cabinets will be separated as such to differentiate between first and second floor; voice and data. |
| 3. | 110 patch panels to include rack mount wire management will be used in the enclosed cabinets for communication terminations in the Telecommunication Room. |
| D. | Fiber Optic / CAT-3 Cross Connects: |
| 1. | Contractor shall install and terminate 400ft (12 Strand MIC) Fiber Optic Cable and 400ft (100 Pair) CAT-3 Cross connect cable from basement to 1st Floor Telecommunication Room. Materials provided by contractor. |
| 2.02 | CONDUIT AND WIRING: All communication system wiring shall be installed in minimum 1” (27 mm) electrical metallic tubing (EMT) or 2”-4” 3000 Series Wiremold. Refer to I3A Tech Criteria para 2.4.4.3. |
PART 3 - EXECUTION
| 3.01 | INSTALLATION: Install communication cabling and system equipment where shown, in accordance with the manufacturer’s instructions and with recognized industry practices to ensure that the equipment complies with these requirements and serves the intended purposes. |
| 3.03 | TESTING: Upon completion conduct a total system test for the Contracting Officer where each outlet shall be tested for proper operation. Test all terminations per I3A Tech Criteria para 2.10. Provide three sets of “As Built” drawings, including plan layout, conduit runs, and labeled wiring diagrams as finally installed. |
END OF SECTION