Cover_003_20101008_Revised.pdf
PDF 71 KB Posted
- Solicitation number
- W912L111R0010
About this file
addendum
View the file
Other files
| File | Type | Posted |
|---|---|---|
| E-601.pdf | ||
| A-203.pdf | ||
| S-511.pdf | ||
| A-105.pdf | ||
| A-606.pdf | ||
| P-601.pdf | ||
| Cover_002.pdf | ||
| C-001.pdf | ||
| FA-101.pdf | ||
| A-506.pdf | ||
| M-502.pdf | ||
| 930303M-401.pdf | ||
| E-401.pdf | ||
| 930303E-401.pdf | ||
| S-002.pdf | ||
| M-501.pdf | ||
| M-802.pdf | ||
| A-505.pdf | ||
| E-103.pdf | ||
| A-301.pdf | ||
| S-550.pdf | ||
| F-001.pdf | ||
| S-103.pdf | ||
| C-102.pdf | ||
| A-107.pdf | ||
| A-201.pdf | ||
| A-304.pdf | ||
| 930303T-101.pdf | ||
| E-502.pdf | ||
| A-401.pdf | ||
| Specifications.pdf | ||
| E-503.pdf | ||
| A-802.pdf | ||
| M-102.pdf | ||
| 930303FA101.pdf | ||
| CD-101.pdf | ||
| P-101.pdf | ||
| P-102.pdf | ||
| M-801.pdf | ||
| A-104.pdf | ||
| P-901.pdf | ||
| M-503.pdf | ||
| A-603.pdf | ||
| G-100.pdf | ||
| A-502.pdf | ||
| 930303TY101.pdf | ||
| FX-501.pdf | ||
| AD-201.pdf | ||
| 930303M-802.pdf | ||
| T-001-TY-601.pdf |
Show 40 more
Latest 50 of 123 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KELL099067-F-16-Mission Training Center (Flight Sim) Facility Kelly Field Annex W90FYQ-09-D-0006-9C02 Texas Air National Guard
ADDENDUM 003 (Revised)
October 8, 2010
This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents.
Acknowledge receipt of this Addendum in the space provided in the Bid Form. Failure to do so may subject Bidder to disqualification.
This Addendum consists of all attachments noted herein.
MODIFICATIONS TO PREVIOUS ADDENDA:
N/A
MODIFICATIONS TO SPECIFICATIONS:
SPECIFICATION SECTION 01 00 00 GENERAL REQUIREMENTS
Subparagraph 1.11 IEPA Requirements: DELETE All references to Illinois EPA permit requirements.
ADD Permit requirements as defined by the Texas Commission on Environmental Quality.
ADD Permit requirements as defined by the City of San Antonio, TX.
Subparagraph 1.15 Dust Control: ADD “or when directed by BCE” Subparagraph 1.23 Precedence of Air Operations: ADD “beyond line markers or as directed by airfield manager” Subparagraph 1.7 Work Scheduling: REVISE “Normal duty hours for work shall be from 07:00 a.m. to 5:00 p.m.
SPECIFICATION SECTION 01 11 00 SUMMARY OF WORK
Subparagraph 10.10.1 Utility Outage Request: DELETE Contracting Officer and replace with BCE.
SPECIFICATION SECTION 01 14 00 WORK RESTRICTIONS
Subparagraph 1.4.2: Working Hours: REVISE Normal duty hours for work shall be from 07:00 a.m. to 5:00 p.m.
SPECIFICATION 01 33 00 SUBMITTAL PROCEDURES
Subparagraph 1.15 Status Report on Material Orders: ADD “Only those materials placed on backorder that may impact overall construction schedule beyond period of performance”.
SUBMITTAL REGISTER
Activity Hazardous Analysis (Page 1) Delete “G” Section 01 33 00 Pg 2 of 65 submittal register:
Add SD-06 test reports “as incident occurs” Accident reports: G Crane reports: G SD-07 certificates; Add “G” as follows:
Confined space entry permit: G Hot work permit: G Certificate of compliance: G
SPECIFICATION SECTION 01 35 26 GOVERNMENT SAFETY REQUIREMENTS
Subparagraph 1.8 Activity Hazard Analysis add The Start of Each Phase “As Requested by BCE”
Texas Air National Guard
SPECIFICATION SECTION 08 11 13 STEEL DOORS AND FRAMES
Subparagraph 1.2 References: ADD All facility penetrations shall comply with JAFAN 6/9 Security Measures.
SPECIFICATION SECTION 08 34 73 SOUND CONTROL DOOR ASSEMBLIES
Subparagraph 2.5 Door Hardware: ADD Door hardware to be exit only, no out trim for doors 117B and 131B Hardware Group 04.
SPECIFICATION SECTION 23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST
SYSTEMS
Subparagraph 2.14 Energy Recovery Devices: DELETE this Subparagraph in its entirety.
ADD the following Subparagraph
2.11.1.2 In-Line Centrifugal Fans
Provide in-line fans with centrifugal backward inclined blades, stationary discharge conversion vanes, internal and external belt guards, and adjustable motor mounts. Mount fans in a welded tubular or rectangular casing. Provide a fan that axially flows the air in and out. Enclose and isolate fan bearings and drive shafts from the air stream. Bearings shall be heavy duty regreasable ball type in a pillowblock cast iron housing selected for a minimum L50 life in excess of 200,000 hours at maximum cataloged operating speed. Motor shall be heavy duty type with permanently lubricated sealed ball bearings and furnished in the specified voltage, phase and enclosure. Belts shall be oil and heat resistant, not-static type. Drives shall be precision machined cast iron type, keyed and securely attached to the wheel and motor shafts.
Drives shall be sized for 150% of the installed motor horsepower. Variable pitch drives shall be factory set to deliver the specified cfm at the indicated static pressure.
SPECIFICATION SECTION 23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST
SYSTEMS
ADD All facility penetrations shall comply with JAFAN 6/9 Security Measures.
SPECIFICATION Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
Appendix D: DELETE the column on the Table Titled, “Energy Recovery Unit ERU-1 System”.
SPECIFICATION Section 23 08 00.00 10 COMMISSIONING OF HVAC
Appendix A: DELETE Energy Recovery Unit, ERU-1 from the list of HVAC Equipment and Systems to be commissioned.
SPECIFICATION SECTION 23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR
HVAC
ADD the following Subparagraph
2.3.4 Combination Air Monitoring Station with Integral Damper
Furnish and install at location shown on the plans, an IAQ damper with integral airflow measurement station. The airflow sensing section shall be an integral part of the outside air damper assembly and shall incorporate an aluminum honeycomb air straightening section and measuring ports for air velocity and static pressure sensing. The assembly shall measure and control the minimum amount of outside air as recommended by ASHRAE Standard 62. The overall depth of the air measurement section and damper assembly shall not exceed 11”. The IAQ damper frame shall be 6” x 1.375” x .125” 6063T5 extruded aluminum. The outside air damper blades shall be airfoil type 6063T5 extruded aluminum with neoprene blade edge seals mechanically fastened to the extruded blade seal pocket (glued or clip-on seals are not acceptable). Integral extruded aluminum pitot sensing blades shall include a clear anodized
Texas Air National Guard finish to reduce corrosion. Leakage shall not exceed 4 CFM per sq. ft. of damper face area at 1” w.g. Pressure drop through the entire assembly shall not exceed .13” w.g. at an air velocity of 1,000 FPM. Each IAQ damper assembly shall include 24VAC electric, spring return, modulating actuator(s) to work in concert with an application specific controller. Each controller shall be factory calibrated and correspond with blade/actuator position. Programming logic and calibration shall be nonvolatile EPROM. Control panel shall include 120VAC primary to 24VAC secondary transformer, microprocessor-based control board, transducer and wiring terminal strip. All internal piping and wiring within the control panel shall be performed by the damper manufacturer. Piping on the IAQ damper assembly shall be out of the air stream and shall be of plenum rated material. Complete piping and wiring details describing these features shall be included in the submittal package and shall accompany the product upon shipping. Entire assembly shall control and report airflow within an accuracy of 5%. The complete assembly, including all piping and wiring of IAQ controller, shall be assembled and commissioned in an ISO certified manufacturing facility. Controller shall be capable of control and communication with Building Direct Digital Control (DDC) System. DDC system shall send a variable output signal to IAQ controller to adjust damper position. IAQ controller shall send a variable output signal to the DDC system which is proportional to the CFM measured at the damper.
MODIFICATIONS TO DRAWINGS:
Drawings:
G-002 Sheet Index: General Notes: Add general note ALL FACILITY PENETRATIONS SHALL
COMPLY WITH JAFAN 6/9 SECURITY MEASURES.
M-101 Mechanical Ductwork Plan – Bid Package 2 Drawing revised and reissued.
M-401 Enlarged Mechanical Room Plan and Sections – Bid Package 2 Drawing revised and reissued.
M-601 Mechanical Schedules – Bid Package 2 Drawing revised and reissued.
M-602 Enlarged Mechanical Schedules – Bid Package 2 Drawing revised and reissued.
M-801 Mechanical Control Input and Output Diagram – Bid Package 2 Drawing revised and reissued.
M-802 Mechanical Control Sequence of Operation – Bid Package 2 Drawing revised and reissued.
E-401 Enlarged Plans – Bid Package 2 Drawing revised and reissued.
E-603 Electrical Panel Schedules – Bid Package 2 Drawing revised and reissued.
E-604 Electrical Panel Schedules – Bid Package 2 Drawing revised and reissued.
FA-101 Fire Alarm Mass Notification – Bid Package 2 Drawing revised and reissued.
T-100 Communications Site Plan Revise MH126 to MH216A at Key Note 1 & 2.
Texas Air National Guard
T-101 Communication Floor Plan-Bid Package 2 Drawing revised and reissued.
TY101 Security Floor Plan-Bid Package 2 Drawing revised and reissued
TY601 Security One-Line Diagram Drawing revised and reissued
ATTACHMENTS:
Drawings: M-101, M-401, M-601, M-602, M-801, M-802, E-401, E-603, E-604, T-101, TY101, TY601, FA101
END OF ADDENDUM 003