SCOPE OF WORK

Portable Crash Barrier System

1. CONTRACTOR RESPONSIBILITIES: Vendor shall provide and deliver a Portable Hydraulic Crash Barrier System to the 177FW, NJ Air National Guard, 400 Langley Road, Egg Harbor Twp., NJ 08234.

2. PROJECT DESCRIPTION: The Barrier System shall be Delta Scientific MP5000 or Approved Equal and shall include, at a minimum, the following components:

· A Basic Structure with at least a 20 FT clear opening

· Battery operated hydraulic pump with control station.

· Barrier trailer assembly – including spare tire, utility box and VIN Number.

The basic system shall have a quick deployment mobile barrier assembly, a hinged rigid crash plate assembly, and a trailer hitch assembly. Contractor shall provide color patterns for Government selection as well as complete instructions, start up, and trouble-shooting manuals.

The following options shall be included, at a minimum, with the basic system:

· Remote open/close push button station with at least a 20 ft. cable

· A barricade fully down auxiliary limit switch

· Booster PAK 12vdc

· Cable kit (which includes a jumper cable, utility outlet connection)

· Barrier turn Table

3. WORK WEEK AND HOURS OF OPERATION: Deliveries shall occur between Tuesday through Friday, 0700 to 1630. The vendor must make arrangements in advance to work outside of normal duty hours.

4. RESTRICTED AREAS: There are numerous areas that are restricted and access to these areas must be coordinated through the SFS Office. The Contractor shall coordinate, three days in advance, for arrangements required to work in any of these areas. Contactors working in restricted areas shall be required to provide the SFS Office with a list of names and social security numbers for all personnel expected to work in these areas.

5. DELIVERY: System shall be delivered and installed within 60 days after contract award.

Printed on: Saturday, August 18, 2018 @ 08:37