W912KC18Q5002_RFI_Responses.pdf
PDF 335 KB Posted
- Attached to
- Temporary Water Filtration Federal contract opportunity
- Solicitation number
- W912KC18Q5002
About this file
W912KC18Q5002 - Temporary Water Filtration RFI Responses
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PWS_-_Temporary_Water_Filter.pdf | ||
| Clauses_&_Provisions.docx | DOCX document | |
| Quote_Sheet_-_W912KC18Q5002.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912KC18Q5002 - Temporary Water Filtration RFIs
# Question Government Response
1 Two wells are mentioned in the RFQ.
Presently there is filtration servicing at the new VOC stripping building after the forwarding pumps. Is this the location for current RFQ ?
The filtration will be conducted at the same locations currently being serviced.
2 Chlorination is mentioned on the RFQ.
Presently another vendor services and monitors this portion of the water. Is this part of the current RFQ?
Correct, this is not a requirement as chlorination is a responsible action on a separate contract.
3 Presently we use Carbon and Resin on the site. Will this continue to be acceptable?
Yes, the use of carbon and resin is acceptable.
4 Presently we are testing 2x/month. With resin and performance of the resin 1x/month should be adequate. We have a mid-bed sample point that will give us a warning for PFOS&PFOA and we have about 25% of the resin after the mid bed sample point for safety. This will save testing costs which are expensive. Would 1x/month be acceptable?
Yes, one month testing will be acceptable with the use of resin.
5 Will power for heat tracing and container heating continue to be available?
Yes, power will still be available.