W912JB-18-B-8001
BATTLE CREEK REPAIR ROOF 6923
RFI’S
1. Per the solicitation, offer and award form provided in section 10 it states that funds are not available however under the Delivery information page 4 it states that funds are available for this project. Please advise. ANSWER: Funds are presently available for this requirement.
2. Per the solicitation, offer and award form provided under section 11 it states 60 days of performance period however in section 1100 "Summary" page 2 section F its state to be substantially complete within 30 days. Due to the size of the project are we to be substantially complete in 60 days? Please advise. ANSWER: The period of performance is 60 calendar days.
Disregard Section F period of performance.