QUESTIONS AND ANSWERS RELATED TO:

W912J6-12-R-0001

As of 21 Feb 2012

Make Sure You Have the Latest Version of this Web Page “Refresh” or “Reload”

Dated 02 Feb 2012

Q1. How do I access the files/documents for the Project?

A1. See, Sections 4.4, 4.5 & 4.7 of the FBO Vendor Guide available for download in PDF format via the Federal Business Opportunities / FBO Home Page. See also, Section 00100 of the Solicitation. Additionally, to view and/or download Export Controlled Materials, a company must be certified (via an approved DD Form 2345) by the Joint Certification Program (JCP) administered by the DLA Logistic Information Service (DLIS). This certification establishes that a company is a U.S. or Canadian contractor eligible to receive unclassified technical data that is under the control of the U.S. Department of Defense (DoD) or the Canadian Department of National Defense (DND). Questions about this program or DD Form 2345 should be addressed to U.S./Canada Joint Certification Office, DLA Logistics Information Services (DLIS), Federal Center, 74 Washington Avenue North, Battle Creek, MI 49017-3084. The Joint Certification Office may be contacted by telephone at: 1-(800) 352-3572; or email: jcp-admin@.dla.mil.

Q2. I am trying to access the [export controlled] packages and have a number as assigned on DD Form 2345 but cannot get the packages to open. Our DD 2345 Number is ####### expiration ##/##/2015.

A2. The U.S./Canada Joint Certification Program (JCP) office reported to this office that once a company is certified with the JCP office (normally 7 to 12 business days), the company should contact FBO to have them add their JCP number to their FBO account. The FBO help desk (Federal Service Desk) reported to this office that companies need to make sure that they are registered and login as a Vendor to FBO. When the Vendor click's to open an export controlled package/document, they should be asked for their MPIN. After entering the MPIN, the export controlled package/document should be viewable/downloadable by Vendors that have gone through the JCP process. If a Vendor still has problems, the Vendor should check to make sure that their CCR registration and MPIN are valid and up-to-date. If problems still persist, the Vendor may call the FBO help desk at 866-606-8220, selection option 2 for FBO issues, and ask for troubleshooting assistance.

Dated 14 Feb 2012

Q3. Paragraph 3.1 indicates to write all questions via Exhibit E, Proposal Inquiry Format.

Please provide this document.

A3. Exhibit E, Proposal Inquiry Format, is posted on FBO in Word format. The document is titled Exhibit D and E Jan 11.

Q4. It appears pages 9007 S-102, 9008 S-104, 9007 S-300, and S-510 are missing from the drawings. Please provide.

A4. PENDING

Dated 21 FEB 2012

Q5. The current specification has deleted the previous Section 071113 – Bituminous Damproofing. In the drawing sheets A-322 and A-323 wall details, the damproofing mastic note is still indicated on the wall section datails. Is this previous damproofing section to be replaced by the new Section 071400 – Fluid-Applied Waterproofing? Please kindly verify in your amendment.

A5. PENDING

Q6. On Drawing S-002 under “MICROPILE FOUNDATIONS” Note 11.A.b. indicates that the Micropile allowable and ultimate tension capacities are 90 kips and 180 kips respectively. However, the Geotechnical Report on page 14 indicates that TYPE I Micropiles have an allowable tension capacity of 60 kips. See the TYPE I table included above in the RFI Question 3. Please clarify the discrepancy between the allowable tension capacity of 90 kips on Drawing S-002 Note11.A.b. and the 40 kip capacity on Page 14 in the Geotechnical Report.

A6. Pending

Q7. On Drawing S-001 under "SOIL PREPARATION AND MICROPILES" Note 7 indicates that "DESIGN DEPTH FOR BOTTOM OF MICROPILES SHALL BE AT

ELEVATION -32'-0" PER SOILS REPORT. THE BONDED ZONE LENGTH IS 11FT

PER THE SOILS REPORT." However, on Drawing S-002 under "MICROPILE FOUNDATIONS" Note 6 indicates that "MINIMUM ROCK SOCKET (bonded zone)

LENGTH AS INDICATED ON DRAWINGS, OR AS DEEMED APPROPRIATE

PENDING RESULTS OF STATIC PILE LOAD TESTING."; and Note 10 indicates that

"THE FINAL LENGTH OF THE PRODUCTION MICROPILES SHALL BE

DETERMINED SUCH THAT THE REQUIRED GEOTECHNICAL CAPACITY IS

DEVELOPED BY SKIN FRICTION BETWEEN THE GROUT AND SOIL OVER A

SUITABLE LENGTH IN AN APPROPRIATE BEARING STRATUM (BOND ZONE)."

The Notes on these two sheets appear to be in conflict. Our questions are:

a. If the Notes on Drawing S-001 govern, and the Micropile Pre-Production Test indicates that longer Micropile lengths are required in order to provide the required Design Capacity, how are we to be paid for the required additional depth below Elevation -32’- 0” and additional bond length beyond 11FT? There is currently no provision in the bid documents for an ADD Price for Additional Length of Micropiles. Please clarify.

b. However, if the Notes on Drawing S-002 govern then would you please modify or delete the conflicting notes on Drawing S-001?

A7. PENDING

Q8. On Drawing S-001 under “SOIL PREPARATION AND MICROPILES” Note 9.b indicates that “RETAINING WALLS AT BUILDING STRUCTURES SHOULD BE

DESIGNED IN ACCORDANCE WITH THE RECOMMENDATIONS CONTAINED IN

THE MICROPILE FOUNDATION NOTES.” However, the “MICROPILE

FOUNATIONS” Notes on Drawing S-002 do not address anything about Designing Retaining Walls. Would you please clarify the intent of Note 9.b?

A8. PENDING

Q9. On Drawing S-002 under “MICROPILE FOUNDATIONS” Note 11.A indicates that the Micropile piles are to be “TYPE I.” Then Note 11.A.a. indicates that the Micropile allowable and ultimate compression capacities are 120 kips and 240 kips respectively.

However, the Geotechnical Report on page 13 indicates that TYPE I Micropiles have an allowable compression capacity of 20 tons (40 kips). See the TYPE I table below. Please clarify the discrepancy between the allowable compression capacity of 120 kips on Drawing S-002 Note 11.A.a. and the 40 kip capacity on Page 13in the Geotechnical Report.

A9. PENDING

Q10. Section 01 33 29 LEED Documentation references in several places “Table 1” which identifies the LEED credit items that are designed into the project. No such table exists in the project specifications. Please provide.

A10. PENDING

Q11. Sections 00110 paragraph 3.4.2.4 and 00120 paragraph 2.2.2.3 discuss the requirement to submit a construction schedule with Offeror’s proposal and how the Government will evaluate the schedule.

Nowhere does it state if a proposed schedule that is quicker than the 540 calendar days allowed by the RFP will be receive more favorable consideration. Please verify.

A11. No favorable consideration will be given, as a reminder the completion date includes punchlistand all closeout activities.

Q12. Reference is made to drawing sheet E-801 details 3 and 4 and what appears to be a reinforced underground ductbank. Please advise if the ductbank is to be reinforced around the conduits and if so, what the reinforcing requirements are.

A12. PENDING

Q13. Specification Section 01 33 29 LEED (™) DOCUMENTATION, paragraph 1.3, references a Table 1. Please provide Table 1.

A13.PENDING

Q14.Please provide specification section 08 91 00 – METAL WALL AND DOOR

LOUVERS

A14. PENDING

Q15. Please provide specifications for bike racks as shown on drawing CS-101.

A15. PENDING

Q16. Reference is made to drawing 9008 A-103 and note that building 9008 is an additivie option 7. Please explain.

A16. PENDING

Q17. On Drawing S-001 under "SOIL PREPARATION AND MICROPILES" Note 7 indicates that "DESIGN DEPTH FOR BOTTOM OF MICROPILES SHALL BE AT

ELEVATION -32'-0" PER SOILS REPORT. THE BONDED ZONE LENGTH IS 11FT

PER THE SOILS REPORT." However, on Drawing S-002 under "MICROPILE FOUNDATIONS" Note 6 indicates that "MINIMUM ROCK SOCKET (bonded zone)

LENGTH AS INDICATED ON DRAWINGS, OR AS DEEMED APPROPRIATE

PENDING RESULTS OF STATIC PILE LOAD TESTING."; and Note 10 indicates that

"THE FINAL LENGTH OF THE PRODUCTION MICROPILES SHALL BE

DETERMINED SUCH THAT THE REQUIRED GEOTECHNICAL CAPACITY IS

DEVELOPED BY SKIN FRICTION BETWEEN THE GROUT AND SOIL OVER A

SUITABLE LENGTH IN AN APPROPRIATE BEARING STRATUM (BOND ZONE)."

The Notes on these two sheets appear to be in conflict. Our questions are:

a. If the Notes on Drawing S-001 govern, and the Micropile Pre-Production Test indicates that longer Micropile lengths are required in order to provide the required Design Capacity, how are we to be paid for the required additional depth below Elevation -32’0” and additional bond length beyond 11FT? There is currently no provision in the bid documents for an ADD Price for Additional Length of Micropiles. Please clarify.

b. However, if the Notes on Drawing S-002 govern then would you please modify or delete the conflicting notes on Drawing S-001?

A17. PENDING

Q18. On Drawing S-001 under “SOIL PREPARATION AND MICROPILES” Note 9.b indicates that “RETAINING WALLS AT BUILDING STRUCTURES SHOULD BE

DESIGNED IN ACCORDANCE WITH THE RECOMMENDATIONS CONTAINED IN

THE MICROPILE FOUNDATION NOTES.” However, the “MICROPILE FOUNATIONS” Notes on Drawing S-002 do not address anything about Designing Retaining Walls. Would you please clarify the intent of Note 9.b?

A18. PENDING

Q19. On Drawing S-002 under “MICROPILE FOUNDATIONS” Note 11.A indicates that the Micropile piles are to be “TYPE I.” Then Note 11.A.a. indicates that the Micropile allowable and ultimate compression capacities are 120 kips and 240 kips respectively.

However, the Geotechnical Report on page 13 indicates that TYPE I Micropiles have an allowable compression capacity of 20 tons (40 kips). See the TYPE I table below. Please clarify the discrepancy between the allowable compression capacity of 120 kips on Drawing S-002 Note 11.A.a. and the 40 kip capacity on Page 13in the Geotechnical Report.

A19. PENDING

Q20. Current TYPE I Micropile Load provisions from the Geotechnical Report and the Contracting Drawings listed in Table 1 below:

TYPE1MP

Allowable

Compression Ultimate Compression

Allowable Tension

Ultimate Tension

From the Geotechnical Report, pages 13-14

40 kips

60 kips

From Drawing S-002 Micropile Foundations Note 11

120 kips 240 kips 90 kips 180 kips

A20. PENDING

Q21. On Drawing S-002 under “MICROPILE FOUNDATIONS” Note 11.A.b. indicates that the Micropile allowable and ultimate tension capacities are 90 kips and 180 kips respectively. However, the Geotechnical Report on page 14 indicates that TYPE I Micropiles have an allowable tension capacity of 60 kips. See the TYPE I table included above in the RFI Question 3. Please clarify the discrepancy between the allowable tension capacity of 90 kips on Drawing S-002 Note11.A.b. and the 40 kip capacity on Page 14 in the Geotechnical Report.

A21. PENDING

Q22. Please provide missing Structural drawings (S-101 and S-510)

A22. PENDING

Q23. Please provide specs for Louvers

A23. PENDING

Q24. The connection detail (Sheet 9013 S-402 Detail 3 or Detail 5) show 4ea #5 bars withACI hooks. This is a typical connection detail. Typically we see the reinforcing barextending into the pile cap with a nut-plate-nut connection to achieve the required loadtransfer. Will the Air National guard accept alternate connection details?

A24. PENDING

Q25. Sheet S-002 Micropile Foundation note 3 states that the minimum diameter of the casing be .545 wall. This size does not exist. There is 7.625 x .500 wall or 9.625by .545 wall.

Which one is it?

A25. PENDING

Q26. The Structural Drawings from the www.fbo.gov website appear to be missing some pages. The table of contents G-002 show there being sheets S-102, S-104, S-300 and S-510 but did not see them in the drawings package. Please provide these missing sheets.

A26. PENDING

Q27. We are a subcontractor bidding to the prime contractors for the micropile work on the reference project. Would you please send us a copy of the list of planholders for this job, or let us know how to obtain the list?

A27. Persons to have registered for this project can be located at www.fbo.gov. Additionally, a list of those persons who have attended the Pre Proposal Conference can be locaed on www.fbo.gov.

Q28. Under 3.3 Proposal Format 3.3.4 the RFP states that "Written proposals shall be prepared on standard 8.5 x 11 inch paper ...." To aid in readability and allow a more reasonable timescale to be displayed, can the schedule be printed on 11x17 paper, folded to fit into an 8.5x11 binder?

A28. Yes, will amend para 3.3.4 of Section 110 to reflect this direction.

Q29. Under 19 (Work Progress and Preparation of Progress Schedules and Reports)

19.3 states that "...the contractor shall provide a project plan in the most current version of Microsoft Project to define work tasks and track progress." Would it be permissable to provide a project plan using Primavera P3, P6 or Suretrak instead of Microsoft Project?

A29. Yes, if awarded the Government will consider other formats to be negotiated with the Contracting Officer.

Q30. The SF 1442, Item 13.B. indicates that an Offer Guarantee is NOT required.

Please confirm a Bid Bond is not required to be submitted with our Proposal that is currently due 3/6/12.

A30. Bid Bond is not required.

Q31. Buildings 9007 & 9008 appear to have the same foundation footprint, and seem to have the same micropile layout. However, Building 9007 shows 51 micropiles while Building 9008 shows 56. It appears that some of Building 9007 micropiles may have been omitted from the drawing due to a drafting error. Would you please clarify if the number of micropiles shown on Drawing 9007 S-101 is the correct number?

A31. PENDING