Submittal_Schedule.pdf

PDF 12 KB Posted

Attached to
Weather Seal Multiple Facilities
Solicitation number
W912J3-17-T-1002
Issued by

About this file

Submittal Schedule

View the file

Other files

File Type Posted
Addendum_0001.pdf PDF
Questions_and_Answers_1.pdf PDF
Solicitation_-_W912J3-17-T-1002.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHEDULE OF MATERIAL SUBMITTALS

PROJECT NUMBER

MHMV172506

PROJECT TITLE

Weather Seal Multiple Facilities

SOLICITATION/CONTRACT NO.

W912J3-17-T-1002

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACTING

L i n e N u m b e r

ITEM OR DESCRIPTION OF ITEM,

CONTRACT REFERENCE, TYPE OF

SUBMITTAL

NO. OF

COPIES

REQUIRED

REQUIRED

SUBMISSION

DATE

DATE

RECEIVED IN

CONTRACTING

DATE TO

CIVIL

ENGINEERING

RETURN

SUSPENSE

DATE

FOLLOW-UP

DATE

CONTRACTOR

NOTIFIED

CONTRACTOR

RESUBMITTED

FINAL

APPROVAL

REMARKS

APPROVED DISAPPROVED

1 Weather Sealant/Caulking to include MSDS Sheets

3 Prior to work

2 Control Joint Material 3

Prior to work