About this file

This document is an amendment to a solicitation for nature-based solutions to increase resilience at US Marine Corps resources. The amendment provides answers to seven questions submitted by offerors. It clarifies that experience will be evaluated as outlined in the solicitation, recommends offerors scope nature-based solution projects for each installation, and confirms the correct points of contact and that there is no page limit unless otherwise stated. The amendment also specifies that small scale pilot projects are expected to be included in field study plans to characterize sites and scope nature-based solutions, but preliminary data collection is for identifying information needs rather than collecting full datasets. This is a new contract for new work.

View the file

Other files

File Type Posted
W912HZ23R00320001 Amendment 0001.pdf PDF
W912HZ23R0032 SOLICITATION.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Amendment is to answ er questions submitted.

Please see the continuation page for all answ ers to questions submitted.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Aug-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912HZ23R0032

X 9B. DATED (SEE ITEM 11)

13-Aug-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Aug-2023

CODE

ERDC CONTRACTING OFFICE

3909 HALLS FERRY ROAD

VICKSBURG MS 39180-6199

W912HZ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HZ23R0032

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS AND ANSWERS

The purpose of this amendment is to respond to questions submitted during the question and answer period.

Q1. Please confirm that five projects with a combined dollar value that amounts to half the proposed services for the five projects outlined in the PWS meet the Subfactor 1 requirement to demonstrate relevant corporate experience.

A1. Subfactor 1 requirements are technical in nature and represent the offeror’s experience. Experience will be evaluated as outlined in the Section M.

Q2. Can additional project locations details be provided regarding size of desired project, either in shoreline length, site acreage, or a map showing proposed project extents?

A2. The purpose of the contract is for the offeror to eventually scope NBS projects specific for each installation.

The offeror shall provide recommendations on the size, locale, dimensions, and type of NBS projects placed in the landscape for the installations.

Q3. On page 23 of 27 under Part III – Price Proposal “Price proposals shall consist of the following basic components: (a) Fully completed SF 33 and Bidding Schedule. Question, should this have been SF 330 instead of SF 33? Also, if this is an SF 330 are we to complete the entire submittal in that format?

A3. The solicitation is built on a Standard Form 33.

Q4. Can you please clarify the difference between the requirements for Part I (a) Experience versus those for Part II Past Performance and indicate what content should be presented in each?

A4. The requirements for each Part are outlined in the Solicitation.

Q5. Please clarify and confirm the correct email addresses for both Amanda Andrews and Sonia Boyd. There are two (2) different email addresses identified for Amanda Andrews: Amanda.m.andrews@usace.army.mil (in Section C. Email Address under Solicitation, Offer and Award) and Amanda.Andrews@usace.army.mil (in both Section SF 30 Block 14 Continuation Page Summary of Changes under Changes Amendment of Solicitation / Modification of Contract).

A5. Amanda.Andrews@usace.army.mil Sonia.J.Boyd@usace.army.mil

Q6. Please clarify as there is no guidance on total length of proposal except what is stipulated in “page limitations and parts” table on page 2 of the amended solicitation.

A6. Unless otherwise stated there is no limitation on the proposal length. Please provide enough information to fully discuss all aspects of the proposal.

Q7. Regarding development of a field study plan under Task 3.2, the PWS reads that the plan may include small scale projects meant to simulate NBS alternatives. Please clarify if this is a PWS requirement or would a technical approach that demonstrates an exceptional approach and understanding without inclusion of implementation of small-scale NBS simulations meet the requirements for this task? Additionally, please confirm that the field study plan effort is for identification of additional information / data gaps / modelling required to develop the conceptual plans, but does not include collection of additional data such as bathymetry, development of hydrodynamic models, etc.

A7. For Task 3.2, it is expected that small scale projects meant to simulate NBS alternatives would be part of a field study plan. The field study plan does include preliminary data collection and/or modelling efforts for a site. For the plan, a site would be characterized and evaluated. Data would be collected to close gaps, then an NBS could be scoped.

W912HZ23R0032

Q8. We would like to know if this is a brand new contract OR if there is (was) an incumbent performing these services. If not brand new, could you please provide the current / previous contract number?

A8. This is a new contract for new work.

(End of Summary of Changes)