DOR_Generator_USACE_ERDC.pdf
PDF 285 KB Posted
- Attached to
- Engine Driven Generator Set USACE ERDC Federal contract opportunity
- Solicitation number
- W912HZ19Q9801
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESCRIPTION OF REQUIREMENT
175kW 3 phase 120/208V 60Hz Engine Driven Generator Set
Summary:
The USACE Engineer and Development Center (ERDC) in Vicksburg, MS has a requirement to purchase a 175kW 3 phase 120/208 60Hz Engine Driven Generator Set.
Requirements Description:
There is a need for the Vicksburg ERDC-DPW to have standby power. The subject engine generator set is needed as follows in the description.
a. Coordinate all work with DPW.
b. Delivery location: ERDC DPW Building 3072 3909 Halls Ferry Rd Vicksburg, MS 39180
Specifications:
Description of Requirement:
The following list of generator specifications shall be purchased in order to provide standby power to the DPW facility. All specifications shall be met.
A. Engine Driven Generator Set
a. Rated at 175 kW
b. EPA Stationary Standby
c. 120/208V
d. 3-phase
e. 60 Hz
B. Diesel Fueled Engine
a. Heavy Duty Air Cleaner w/Service Indicator
b. Ambient Radiator
c. Electronic Isochronous Governor
C. Alternator
a. Brushless Rotating Field Generator with Class H Insulation - 1800 rpm
b. 1.0% AVR, w/PMG
D. Circuit Breaker
a. 600 Amp, T6 Frame, 100% Rated, Electronic Trip (Long & Short), Main Line Circuit Breaker
E. Control Panel
a. Digital Control and Metering
F. Heavy Duty Integral Vibration Isolators between Engine/Alternator and Base
G. Oil Drain Kit (Oil Drain Piped to Edge of Skid with Valve)
H. Coolant Drain Kit
I. Lube Oil and Antifreeze
J. Battery Rack and Cables
K. Wide Skid Base
L. Flex Fuel Lines
M. 120V, 1500W Block Heater
N. Battery Charger (6Arnp/12Volt)
0. 12V Lead Acid Battery, P. Sound Attenuated Weather Enclosure with Internal Critical Silencer. 1 inch UL- 94 Sound Attenuating Foam. Heavy Duty Steel
a. Peaked Roof
b. Bolted Construction
c. Lockable Doors
d. Stainless Steel Hardware
e. Powder Coat Finish
Q. Minimum 375 Gallon, UL 142, Subbase Tank, Closed Top Diked Rupture Basin
a. Emergency and Normal Vents (Internal)
b. Low Fuel Level & Fuel in Basin Switch
c. Mechanical Fuel Level Gauge
d. Fuel Level Sender
e. Manual Fill with Locking Cap
f. Minimum 60 hour run time @ 50% load
R. One Hour Factory Load Bank Test
S. 2 Year Warranty
T. O&M Manual
U. Certified to UL2200
V. Startup and Inspection Performed after Completion of Installation
a. Onsite Training: Shall include controller operation at generator and transfer switch
W. Factory Authorized Service Center must be within 100 miles of Vicksburg-ERDC
X. Transfer Switch
a. 600 Amp, 4 Pole, NEMA 3R Enclosure , Programmed, Contactor, Automatic Transfer Switch