Abstract of Offers Summary

This is an Abstract of Offers for Construction document issued by the U.S. Army Corps of Engineers, Galveston District Contracting Division for Solicitation No. W912HY26BA015. The procurement is for an Unrestricted Procurement FY26 HSC Sims to Turning Basin Dredging project located in Harris County, Texas. The solicitation was issued on August 10, 2026, with offers opened on September 10, 2026. Two amendments were issued. The Government Estimate (Without Profit) totaled $15,014,181.00 for Schedule No. 1 and $8,436,628.00 for Option No. 1, for a combined total of $23,450,809.00.

Three offerors submitted bids: Orion Marine Construction, Inc. ($23,450,809.00 total), Matthews Brothers Dredging LLC ($16,148,700.00 total—31.14% below Government Estimate), and Callan Marine, Ltd. ($39,000,000.00 total). All offerors are classified as Other Than Small business entities. The work includes mobilization and demobilization, pipeline management, site management, HSC dredging in multiple sections with unit prices ranging from $9.75 to $40.00 per cubic yard, and tire and debris removal at unit prices from $250.00 to $1,500.00 per net ton. Option No. 1 covers PHA Dock Dredging (Sections 8-22), additional tire and debris removal, and standby hours for PHA Docks. Matthews Brothers Dredging LLC was identified as the apparent low bidder.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF

PAGES

4. ISSUING OFFICE

5. PROJECT TITLE

6. NUMBER OF AMENDMENTS ISSUED

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

SIGNATURE DATE SIGNED

7B. DESCRIPTION OF OFFERED ITEM 7C. EST.

QUANTITY

D.

UNIT

E. UNIT

PRICE

F. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

8. GOVERNMENT ESTIMATE

(Check A, B or C and complete D, E, and F)

A. HIRED LABOR

B. REASONABLE CONTRACT

(Without Profit)

C. REASONABLE CONTRACT

(Including Profit)

9. OFFERS

NO. 1 NO. 2

A. OFFEROR

B. BID SECURITY (Type and amount)

C. AMENDMENTS ACKNOWLEDGED

A. OFFEROR

B. BID SECURITY (Type and amount)

C. AMENDMENTS ACKNOWLEDGED

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is usable

NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88)

7A.

ITEM

NO.

0001 and 0002

X

SEE ATTACHED PAGES

1 4

10 Sept 2026

U.S. Army Corps of Engineers, Galveston District Contracting Division 2000 Fort Point Road Galveston, Texas 77550

Unrestricted Procurement FY26 HSC Sims to Turning Basin Dredging

Curtis Cole, Jr., Contracting Officer

8/10/26 9/10/26W912HY26BA015

ABSTRACT OF OFFERS

ITEM SCHEDULE NO. 1 UNIT

NO. DESCRIPTION PRICE TOTAL

0001 Mobilization and Demobilization 1 JOB $3,866,800.00 $3,866,800.00 0002 Pipeline Management 1 JOB $786,200.00 $786,200.00 0003 Site Management 1 JOB $109,300.00 $109,300.00 0004 HSC Dredging Sections 1 - 4 273,000 CY $15.48 $4,226,040.00 0005 HSC Dredging Sections 5 - 7 270,000 CY $11.27 $3,042,900.00 0006 HSC Tire & Debris Removal Sections 1 - 7 1,300 Net Ton $2,294.57 $2,982,941.00

TOTAL SCHEDULE NO. 1 $15,014,181.00

OPTION NO. 1

0007 Option No. 1: PHA Dock Dredging Sections 8 - 22 227,000 CY $18.31 $4,156,370.00 0008 Option No. 1: PHA Tire & Debris Removal Sections 8 - 22 1,800 Net Ton $2,294.57 $4,130,226.00 0009 Option No. 1: Standby for PHA Docks 100 Hours $1,500.32 $150,032.00

TOTAL OPTION NO. 1 $8,436,628.00

TOTAL SCHEDULE NO.1 & OPTION NO. 1 $23,450,809.00

ITEM SCHEDULE NO. 1 UNIT

NO. DESCRIPTION PRICE TOTAL

0001 Mobilization and Demobilization 1 JOB $3,000,000.00 0002 Pipeline Management 1 JOB $2,670,000.00 0003 Site Management 1 JOB $100,000.00 0004 HSC Dredging Sections 1 - 4 273,000 CY $26.00 $7,098,000.00 0005 HSC Dredging Sections 5 - 7 270,000 CY $12.50 $3,375,000.00 0006 HSC Tire & Debris Removal Sections 1 - 7 1,300 Net Ton $250.00 $325,000.00

TOTAL SCHEDULE NO. 1 $16,568,000.00

OPTION NO. 1

Number of Amendments Issued: 2 Government Estimate (Without Profit)

QUANTITY

Offeror 1: Orion Marine Construction, Inc.

Business Size: Other Than Small

QUANTITY

Solicitation No.: W912HY26BA015 Date Issued: 10 AUG 2026 Date Opened: 10 SEPT 2026 Issuing Office: USACE-Galveston Project Title: FY26 HSC Sims to Turning Basin Dredging Project Location: Harris County, Texas

0007 Option No. 1: PHA Dock Dredging Sections 8 - 22 227,000 CY $35.00 $7,945,000.00 0008 Option No. 1: PHA Tire & Debris Removal Sections 8 - 22 1,800 Net Ton $250.00 $450,000.00 0009 Option No. 1: Standby for PHA Docks 100 Hours $3,500.00 $350,000.00

TOTAL OPTION NO. 1 $8,745,000.00

TOTAL SCHEDULE NO.1 & OPTION NO. 1 $25,313,000.00

ITEM SCHEDULE NO. 1 UNIT

NO. DESCRIPTION PRICE TOTAL

0001 Mobilization and Demobilization 1 JOB $4,150,000.00 0002 Pipeline Management 1 JOB $1,102,500.00 0003 Site Management 1 JOB $200,000.00 0004 HSC Dredging Sections 1 - 4 273,000 CY $9.75 $2,661,750.00 0005 HSC Dredging Sections 5 - 7 270,000 CY $9.75 $2,632,500.00 0006 HSC Tire & Debris Removal Sections 1 - 7 1,300 Net Ton $765.00 $994,500.00

TOTAL SCHEDULE NO. 1 $11,741,250.00

OPTION NO. 1

0007 Option No. 1: PHA Dock Dredging Sections 8 - 22 227,000 CY $13.35 $3,030,450.00 0008 Option No. 1: PHA Tire & Debris Removal Sections 8 - 22 1,800 Net Ton $765.00 $1,377,000.00 0009 Option No. 1: Standby for PHA Docks 100 Hours $0.00 $0.00

TOTAL OPTION NO. 1 $4,407,450.00

TOTAL SCHEDULE NO.1 & OPTION NO. 1 $16,148,700.00

ITEM SCHEDULE NO. 1 UNIT

NO. DESCRIPTION PRICE TOTAL

0001 Mobilization and Demobilization 1 JOB $4,430,000.00 0002 Pipeline Management 1 JOB $2,800,500.00 0003 Site Management 1 JOB $600,500.00 0004 HSC Dredging Sections 1 - 4 273,000 CY $32.00 $8,736,000.00 0005 HSC Dredging Sections 5 - 7 270,000 CY $40.00 $10,800,000.00 0006 HSC Tire & Debris Removal Sections 1 - 7 1,300 Net Ton $1,500.00 $1,950,000.00

TOTAL SCHEDULE NO. 1 $29,317,000.00

OPTION NO. 1

0007 Option No. 1: PHA Dock Dredging Sections 8 - 22 227,000 CY $29.00 $6,583,000.00 0008 Option No. 1: PHA Tire & Debris Removal Sections 8 - 22 1,800 Net Ton $1,500.00 $2,700,000.00

Business Size: Other Than Small

QUANTITY

Offeror 2: Matthews Brothers Dredging LLC Business Size: Other Than Small

QUANTITY

Offeror 3: Callan Marine, Ltd.

Offeror 2: Matthews Brothers Dredging LLC

0009 Option No. 1: Standby for PHA Docks 100 Hours $4,000.00 $400,000.00

TOTAL OPTION NO. 1 $9,683,000.00

TOTAL SCHEDULE NO.1 & OPTION NO. 1 $39,000,000.00

10 Sept 26

File details come from the government source that posted it. Updated .