This Abstract of Offers document details a small business set-aside procurement for the U.S. Army Corps of Engineers (USACE) Galveston District, soliciting bids for improvements to Gulf Intracoastal Waterway, Texas Placement Area No. 118-A. The project involves dike repair and shoreline erosion protection, with a solicitation number W912HY26BA012 issued on 10/28/2025 and opened on 12/09/2025. Six offerors submitted bids, with total project costs ranging from approximately $5.15 million to $13.8 million, including base schedule and two optional components.

Key project elements include mobilization and demobilization, demolition and construction of drop-outlet structures, dike clearing and construction, training dike work, turfing, and as-built drawings. The government estimate was marked as a "Reasonable Contract (Including Profit)" type. Maverick Constructors LLC was noted as the apparent low bidder, being 30.62% below the government's estimate. The project involves multiple line items with varying quantities measured in jobs, cubic yards (CY), linear feet (L.F.), square yards (SY), and tons, covering comprehensive waterway infrastructure improvements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABSTRACT OF OFFERS - CONSTRUCTION

2. DATE ISSUED 3. DATE OPENED PAGE OF

PAGES

4. ISSUING OFFICE

6. NUMBER OF AMENDMENTS ISSUED

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

SIGNATURE DATE SIGNED

7B. DESCRIPTION OF OFFERED ITEM 7C. EST.

QUANTITY

D.

UNIT

E. UNIT

PRICE

F. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

8. GOVERNMENT ESTIMATE

(Check A, B or C and complete D, E, and F)

A. HIRED LABOR

B. REASONABLE CONTRACT

(Without Profit)

C. REASONABLE CONTRACT

(Including Profit)

9. OFFERS

NO. 1 NO. 2

A. OFFEROR

B. BID SECURITY (Type and amount)

C. AMENDMENTS ACKNOWLEDGED

A. OFFEROR

B. BID SECURITY (Type and amount)

C. AMENDMENTS ACKNOWLEDGED

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is usable

NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88)

7A.

ITEM

NO.

U.S. Army Corps of Engineers, Galveston District Contracting Division 2000 Fort Point Road Galveston, Texas 77550

5. PROJECT TITLE

Project Title: Small Business Set Aside Procurement For FY 26 USACE Galveston District GULF INTRACOASTAL

WATERWAY, TEXAS PLACEMENT AREA NO. 118-A

IMPROVEMENTS DIKE REPAIR AND SHORELINE

EROSION PROTECTION

1. SOLICITATION NUMBER

W912HY26BA012 1

Carol Hodges. Contracting Officer

12/09/202510/28/2025

12/10/2025

See Continuation Pages

UNIT

PRICE TOTAL

1 JOB $1,088,400.00 $1,088,400.00

1 JOB $51,000.00 $51,000.00

1 JOB $1,200,000.00 $1,200,000.00

1 JOB $433,000.00 $433,000.00

176,900 CY $14.83 $2,623,427.00

1,580 CY $12.52 $19,781.60

1 JOB $8,000.00 $8,000.00

1 JOB $270,200.00 $270,200.00

1 JOB $27,000.00 $27,000.00

$5,720,808.60

1,250 L.F $1,061.00 $1,326,250.00

4,470

CY $8.58 $38,352.60

2,020

CY $9.03 $18,240.60

$1,382,843.20

$7,103,651.80

3,605 SY $14.00 $50,470.00

4,995 TON $184.00 $919,080.00

TOTAL SCHEDULE NO.1 & OPTION NO.1

Revetment Foundation Excavation - OPTION 1

OPTION NO. 1

ITEM

NO.

ABSTRACT OF OFFERS Page 2 of 6

Solicitation No.: W912HY26BA012 Date Issued: 28 OCT 2025 Date Opened: 09 DEC 2025

Issuing Office: USACE-Galveston Project Title: Small Business Set Aside Procurement For FY 26 USACE Galveston District GULF INTRACOASTAL WATERWAY, TEXAS PLACEMENT AREA NO. 118-A IMPROVEMENTS DIKE REPAIR AND SHORELINE EROSION PROTECTION

Number of Amendments Issued: 2 Government Estimate (Without Profit)

QUANTITY

Turfing

New Drop-outlet Structure

SCHEDULE NO. 1

Containment Dike Clearing, Grubbing, and Stripping

Uncompacted Training Dike Construction

As-Built Drawings

DESCRIPTION

Semi-compacted Containment Dike Construction

Demolition of Drop-outlet Structure

Mobilization and Demobilization

Training Dike Clearing, Grubbing, and Stripping

TOTAL SCHEDULE NO. 1

TOTAL OPTION NO. 1

OPTION NO. 2

0013 Geotextile, Woven- OPTION 2

Riprap, R-700 OPTION 2

Revetment Backfill with Soil OPTION 1

Construct West End Revetment - OPTION 1

1,315 TON $180.20 $236,963.00

$1,206,513.00

$8,310,164.80

TOTAL OPTION NO. 2

TOTAL SCHEDULE NO.1 & OPTION NO. 1 & 2

Bedding Stone, R-20 -OPTION 2

* The apparent low bidder, Maverick Constructors LLC is 30.62 % below the Government's Estimate.

I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT ALL OFFERS RECEIVED IN RESPONSE TO

THIS SOLICITATION.

Carol Hodges

CONTRACTING OFFICER

1 JOB $1,055,000.00 $1,055,000.00

1 JOB $500,000.00 $500,000.00

1 JOB $2,175,000.00 $2,175,000.00

1 JOB $400,000.00 $400,000.00

176,900 CY $22.00 $3,891,800.00

1,580 CY $22.00 $34,760.00

1 JOB $250,000.00 $250,000.00

1 JOB $415,000.00 $415,000.00

1 JOB $175,000.00 $175,000.00

$8,896,560.00

1,250 L.F $750.00 $937,500.00

4,470 CY $23.15 $103,480.50

2,020 CY $22.45 $45,349.00

$1,086,329.50

$9,982,889.50

3,605 SY $24.80 $89,404.00

TOTAL SCHEDULE NO. 1

OPTION NO. 2

As-Built Drawings

Demolition of Drop-outlet Structure

Training Dike Clearing, Grubbing, and Stripping

Uncompacted Training Dike Construction

Turfing

Semi-compacted Containment Dike

NO. DESCRIPTION

Mobilization and Demobilization

Project Title: Small Business Set Aside Procurement For FY 26 USACE Galveston District GULF INTRACOASTAL WATERWAY, TEXAS PLACEMENT AREA NO. 118-A IMPROVEMENTS DIKE REPAIR AND SHORELINE EROSION PROTECTION

Solicitation No.: W912HY26BA012 Date Issued: 28 OCT 2025 Date Opened: 09 DEC 2025

New Drop-outlet Structure

Containment Dike Clearing, Grubbing, and Stripping

Offeror 1: TKTMJ INC

QUANTITY

Issuing Office: USACE-Galveston

ABSTRACT OF OFFERS (CONT'D) Page 3 of 6

Business Size:

ITEM SCHEDULE NO. 1

OPTION NO. 1

Revetment Foundation Excavation - OPTION 1

Construct West End Revetment - OPTION 1

TOTAL SCHEDULE NO.1 & OPTION NO.1

Geotextile, Woven- OPTION 2

Revetment Backfill with Soil OPTION 1

TOTAL OPTION NO. 1

4,995 TON $165.00 $824,175.00

1,315 TON $160.00 $210,400.00

$1,123,979.00

$11,106,868.50

UNIT

1 JOB $2,962,424.00 $2,962,424.00

1 JOB $197,233.00 $197,233.00

1 JOB $1,842,456.00 $1,842,456.00

1 JOB $1,373,644.00 $1,373,644.00

176,900 CY $20.82 $3,683,058.00

1,580 CY $60.00 $94,800.00

1 JOB $87,065.00 $87,065.00

1 JOB $596,876.00 $596,876.00

1 JOB $76,422.00 $76,422.00

$10,913,978.00

1,250 L.F $972.50 $1,215,625.00

4,470 CY $28.50 $127,395.00

SCHEDULE NO. 1

TOTAL SCHEDULE NO. 1

Solicitation No.: W912HY26BA012 Date Issued: 28 OCT 2025 Date Opened: 09 DEC 2025

Issuing Office: USACE-Galveston Project Title: Small Business Set Aside Procurement For FY 26 USACE Galveston District GULF INTRACOASTAL WATERWAY, TEXAS PLACEMENT AREA NO. 118-A IMPROVEMENTS DIKE REPAIR AND SHORELINE EROSION PROTECTION

Offeror 2: GENSIS 360

Bedding Stone, R-20 -OPTION 2

TOTAL OPTION NO. 2

TOTAL SCHEDULE NO.1 & OPTION NO. 1 & 2

Riprap, R-700 OPTION 2

Mobilization and Demobilization

Business Size:

ABSTRACT OF OFFERS (CONT'D) Page 4 of 6

ITEM

Uncompacted Training Dike Construction

As-Built Drawings

Turfing

Training Dike Clearing, Grubbing, and Stripping

New Drop-outlet Structure

Containment Dike Clearing, Grubbing, and Stripping

Demolition of Drop-outlet Structure

Revetment Foundation Excavation - OPTION 1

Construct West End Revetment - OPTION 1

Semi-compacted Containment Dike

OPTION NO. 1

2,020 CY $30.00 $60,600.00

$1,403,620.00

$12,317,598.00

3,605 SY 65.00 $234,325.00

4,995 TON 202.00 $1,008,990.00

1,315 TON 181.60 $238,804.00

$1,482,119.00

$13,799,717.00

TOTAL OPTION NO. 2

Revetment Backfill with Soil OPTION 1

TOTAL SCHEDULE NO.1 & OPTION NO.1

TOTAL SCHEDULE NO.1 & OPTION NO. 1& 2

OPTION NO. 2

TOTAL OPTION NO. 1

Geotextile, Woven- OPTION 2

Riprap, R-700 OPTION 2

Bedding Stone, R-20 -OPTION 2

1 JOB $1,035,769.00 $1,035,769.00

1 JOB $98,000.00 $98,000.00

1 JOB $925,000.00 $925,000.00

1 JOB $160,236.00 $160,236.00

176,900 CY $12.50 $2,211,250.00

1,580 CY $18.00 $28,440.00

1 JOB $4,344.00 $4,344.00

1 JOB $60,000.00 $60,000.00

1 JOB $65,000.00 $65,000.00

$4,588,039.00

1,250 L.F $408.00 $510,000.00

4,470 CY $5.00 $22,350.00

2,020 CY $15.00 $30,300.00

$562,650.00

$5,150,689.00

3,605 SY $6.00 $21,630.00

DESCRIPTION

ITEM SCHEDULE NO. 1

Turfing

Uncompacted Training Dike Construction

OPTION NO. 1

TOTAL SCHEDULE NO. 1

OPTION NO. 2

NO.

Training Dike Clearing, Grubbing, and Stripping

ABSTRACT OF OFFERS (CONT'D) Page 5 of 6

Demolition of Drop-outlet Structure

0013 Geotextile, Woven- OPTION 2

Revetment Foundation Excavation - OPTION 1

TOTAL SCHEDULE NO.1 & OPTION NO.1

Mobilization and Demobilization

Business Size:

Solicitation No.: W912HY26BA012 Date Issued: 28 OCT 2025 Date Opened: 09 DEC 2025

Issuing Office: USACE-Galveston

New Drop-outlet Structure

Containment Dike Clearing, Grubbing, and Stripping

Project Title: Small Business Set Aside Procurement For FY 26 USACE Galveston District GULF INTRACOASTAL WATERWAY, TEXAS PLACEMENT AREA NO. 118-A IMPROVEMENTS DIKE REPAIR AND SHORELINE EROSION PROTECTION

Offeror 3: MAVERICK CONSTRUCTION

QUANTITY

Revetment Backfill with Soil OPTION 1

Construct West End Revetment - OPTION 1

TOTAL OPTION NO. 1

As-Built Drawings

Semi-compacted Containment Dike

4,995 TON $95.00 $474,525.00

1,315 TON $90.00 $118,350.00

$614,505.00

$5,765,194.00

Bedding Stone, R-20 -OPTION 2

Riprap, R-700 OPTION 2

TOTAL SCHEDULE NO.1 & OPTION NO. 1& 2

TOTAL OPTION NO. 2

1 JOB $2,877,122.08 $2,877,122.08

1 JOB $74,551.20 $74,551.20

1 JOB $1,993,650.00 $1,993,650.00

1 JOB $309,934.67 $309,934.67

176,900 CY $15.10 $2,671,190.00

1,580 CY $34.38 $54,320.40

1 JOB $107,630.70 $107,630.70

1 JOB $199,038.83 $199,038.83

1 JOB $47,500.00 $47,500.00

$8,334,937.88

1,250 L.F $373.28 $466,600.00

4,470 CY $20.41 $91,232.70

2,020 CY $59.52 $120,230.40

$678,063.10

$9,013,000.98

ABSTRACT OF OFFERS (CONT'D) Page 6 of 6

Construct West End Revetment - OPTION 1

Revetment Foundation Excavation - OPTION 1

Revetment Backfill with Soil OPTION 1

TOTAL SCHEDULE NO.1 & OPTION NO.1

TOTAL OPTION NO. 1

OPTION NO. 2

Turfing

As-Built Drawings

OPTION NO. 1

Containment Dike Clearing, Grubbing, and Stripping

Semi-compacted Containment Dike

Uncompacted Training Dike Construction

TOTAL SCHEDULE NO. 1

Training Dike Clearing, Grubbing, and Stripping

New Drop-outlet Structure

Solicitation No.: W912HY26BA012 Date Issued: 28 OCT 2025 Date Opened: 09 DEC 2025

Issuing Office: USACE-Galveston Project Title: Small Business Set Aside Procurement For FY 26 USACE Galveston District GULF INTRACOASTAL WATERWAY, TEXAS PLACEMENT AREA NO. 118-A IMPROVEMENTS DIKE REPAIR AND SHORELINE EROSION PROTECTION

Offeror 4: SOUTHERN GULF SOLUTIONS Business Size:

ITEM

SCHEDULE NO. 1

Mobilization and Demobilization

Demolition of Drop-outlet Structure

3,605 SY $22.72 $81,905.60

4,995 TON $132.43 $661,487.85

1,315 TON $146.98 $193,278.70

$743,393.45

$9,756,394.43

UNIT

1 JOB $600,000.00 $600,000.00

1 JOB $50,000.00 $50,000.00

1 JOB $1,113,000.00 $1,113,000.00

1 JOB $45,000.00 $45,000.00

176,900 CY $9.74 $1,723,006.00

1,580 CY $27.00 $42,660.00

1 JOB $4,000.00 $4,000.00

1 JOB $65,000.00 $65,000.00

1 JOB $75,000.00 $75,000.00

$3,717,666.00

1,250 L.F $690.00 $862,500.00

4,470

CY $41.00 $183,270.00

ABSTRACT OF OFFERS (CONT'D) Page 7 of 7

TOTAL SCHEDULE NO. 1

OPTION NO. 1

0010 Construct West End Revetment - OPTION 1

Revetment Foundation Excavation - OPTION 1

Turfing

As-Built Drawings

0001 Mobilization and Demobilization

0002 Demolition of Drop-outlet Structure

Training Dike Clearing, Grubbing, and Stripping

New Drop-outlet Structure

0004 Containment Dike Clearing, Grubbing, and Stripping

0005 Semi-compacted Containment Dike

0006 Uncompacted Training Dike Construction

Solicitation No.: W912HY26BA012 Date Issued: 28 OCT 2025 Date Opened: 09 DEC 2025

Issuing Office: USACE-Galveston Project Title: Small Business Set Aside Procurement For FY 26 USACE Galveston District GULF INTRACOASTAL WATERWAY, TEXAS PLACEMENT AREA NO. 118-A IMPROVEMENTS DIKE REPAIR AND SHORELINE EROSION PROTECTION

Offeror 5: TEXAS DEWATERING Business Size:

ITEM

SCHEDULE NO. 1

Riprap, R-700 OPTION 2

TOTAL OPTION NO. 2

TOTAL SCHEDULE NO.1 & OPTION NO. 1& 2

Geotextile, Woven- OPTION 2

Bedding Stone, R-20 -OPTION 2

2,020

CY $12.00 $24,240.00

$1,070,010.00

$4,787,676.00

3,605 SY $34.00 $122,570.00

4,995 TON $158.00 $789,210.00

1,315 TON $149.00 $195,935.00

$1,107,715.00

$5,895,391.00

UNIT

PRICE TOTAL

1 JOB $1,000,000.00 $1,000,000.00

1 JOB $1,000,000.00 $1,000,000.00

1 JOB $1,000,000.00 $1,000,000.00

1 JOB $400,000.00 $400,000.00

176,900 CY $8.50 $1,503,650.00

1,580 CY $8.50 $13,430.00

1 JOB $20,000.00 $20,000.00

1 JOB $70,000.00 $70,000.00

1 JOB $50,000.00 $50,000.00

$5,057,080.00

ABSTRACT OF OFFERS (CONT'D) Page 8 of 8

TOTAL SCHEDULE NO. 1

0007 Training Dike Clearing, Grubbing, and Stripping

0008 Turfing

0009 As-Built Drawings

0006 Uncompacted Training Dike Construction

Demolition of Drop-outlet Structure

0003 New Drop-outlet Structure

Containment Dike Clearing, Grubbing, and Stripping

0005 Semi-compacted Containment Dike

Offeror 6: RLB Business Size:

ITEM

SCHEDULE NO. 1

NO. DESCRIPTION

Mobilization and Demobilization

QUANTITY

Solicitation No.: W912HY26BA012 Date Issued: 28 OCT 2025 Date Opened: 09 DEC 2025

Issuing Office: USACE-Galveston Project Title: Small Business Set Aside Procurement For FY 26 USACE Galveston District GULF INTRACOASTAL WATERWAY, TEXAS PLACEMENT AREA NO. 118-A IMPROVEMENTS DIKE REPAIR AND SHORELINE EROSION PROTECTION

Riprap, R-700 OPTION 2

Bedding Stone, R-20 -OPTION 2

TOTAL OPTION NO. 2

TOTAL SCHEDULE NO.1 & OPTION NO. 1& 2

Revetment Backfill with Soil OPTION 1

TOTAL OPTION NO. 1

TOTAL SCHEDULE NO.1 & OPTION NO.1

OPTION NO. 2

0013 Geotextile, Woven- OPTION 2

1,250 L.F $900.00 $1,125,000.00

4,470 CY $8.50 $37,995.00

2,020 CY $8.50 $17,170.00

$1,180,165.00

$6,237,245.00

3,605 SY $10.00 $36,050.00

4,995 TON $105.00 $524,475.00

1,315 TON $105.00 $138,075.00

$698,600.00

$6,935,845.00TOTAL SCHEDULE NO.1 & OPTION NO. 1& 2

0011 Revetment Foundation Excavation - OPTION 1

Revetment Backfill with Soil OPTION 1

TOTAL OPTION NO. 1

0014 Riprap, R-700 OPTION 2

0015 Bedding Stone, R-20 -OPTION 2

TOTAL OPTION NO. 2

TOTAL SCHEDULE NO.1 & OPTION NO.1

OPTION NO. 1

Construct West End Revetment - OPTION 1

OPTION NO. 2

0013 Geotextile, Woven- OPTION 2

Abstract Cover Page 26BA012 10DEC2025.pdf
Bid Abstract 26BA012 09DEC2025.pdf
2025-12-11T15:49:21-0600