This is Section 01 50 00 of a federal construction specification for Temporary Construction Facilities and Controls under Solicitation No. W912HY26BA004 (Amendment No. 0003), issued by the U.S. Army Corps of Engineers. The specification establishes comprehensive requirements for contractor-provided temporary facilities, site management, and cybersecurity protocols during construction activities.
Key products and services required include: temporary signage (bulletin boards, project identification signs, warning signs); temporary traffic control (haul roads, access ramps, barricades); safety fencing (polyethylene mesh, chain link panel, and post-driven options); temporary electrical wiring; temporary utilities (sanitation facilities, telephone services, fire protection equipment); administrative field offices with minimum specifications (12'x16' with electrical, heating, telephone); a Quality Control Manager's office (approximately 200 square feet with computer station and plan table); a Government Resident Engineer's office (approximately 400 square feet with utilities and communications); and site restoration upon project completion. Working hours are limited to dawn until dusk, Monday through Saturday, with no work on federal holidays or Sundays without written approval. The contractor must implement cybersecurity measures including: contractor computer equipment with supported operating systems, current anti-malware software, and complex passwords (minimum 8 characters with uppercase, lowercase, numbers, and special characters); temporary IP networks that do not extend outside the project site; contractor-provided Wi-Fi networks using WPA2 security for Government personnel; and submission of cybersecurity compliance statements. Additional requirements address Condition of Readiness protocols for sustained winds of 58 mph or greater, traffic management, dust control, site security, weather protection, and comprehensive site cleanup and restoration upon completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SWG FILE NO.: HSC 0401-0609 SOLICITATION NO.: W912HY26BA004
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 50 00
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS AMENDMENT NO. 0003
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 CONSTRUCTION SITE PLAN
1.4 WORKING HOURS
1.5 DOD CONDITION OF READINESS (COR)
1.6 CYBERSECURITY DURING CONSTRUCTION
1.6.1 Contractor Computer Equipment
1.6.1.1 Operating System
1.6.1.2 Anti-Malware Software
1.6.1.3 Passwords and Passphrases
1.6.1.4 Contractor Computer Cybersecurity Compliance Statements
1.6.2 Temporary IP Networks
1.6.2.1 Network Boundaries and Connections
1.6.3 Government Access to Network
1.6.4 Temporary Wireless IP Networks
1.6.4.1 Contractor Provided Wi-Fi Network
1.6.4.2 Temporary Wireless IP Networks Security
1.6.5 Passwords and Passphrases
1.6.6 Contractor Temporary Network Cybersecurity Compliance
Statements
PART 2 PRODUCTS
2.1 TEMPORARY SIGNAGE
2.1.1 Bulletin Board
2.1.2 Project Identification Signs
2.1.3 Warning Signs
2.2 TEMPORARY TRAFFIC CONTROL
2.2.1 Haul Roads and Access Ramps
2.2.2 Barricades
2.3 FENCING
2.3.1 Polyethylene Mesh Safety Fencing
2.3.2 Chain Link Panel Fencing
2.3.3 Post-Driven Chain Link Fencing
2.4 TEMPORARY WIRING
PART 3 EXECUTION
3.1 AVAILABILITY AND USE OF UTILITY SERVICES
3.1.1 Temporary Utilities
3.1.2 Sanitation
3.1.3 Telephone
3.1.4 Fire Protection
3.2 STATION OPERATION AFFECT ON CONTRACTOR OPERATIONS
SECTION 01 50 00 Page 1
TO ACCOMPANY AMENDMENT 0003 TO SOLICITATION W912HY26BA004
3.2.1 Restricted Access Areas
3.3 TRAFFIC PROVISIONS
3.3.1 Maintenance of Traffic
3.3.2 Protection of Traffic
3.3.3 Rush Hour Restrictions
3.3.4 Dust Control
3.4 CONTRACTOR'S TEMPORARY FACILITIES
3.4.1 Administrative Field Offices (AM#3)
3.4.2 Quality Control Manager Records and Field Office
3.4.3 Storage Area
3.4.4 Supplemental Storage Area
3.4.5 Appearance of Trailers
3.4.6 Safety Systems
3.4.7 Weather Protection of Temporary Facilities and Stored Materials
3.4.7.1 Building and Site Storm Protection
3.5 GOVERNMENT FIELD OFFICE
3.5.1 Resident Engineer's Office
3.5.2 Trailer-Type Mobile Office
3.6 PLANT COMMUNICATIONS
3.7 TEMPORARY PROJECT SAFETY FENCING
3.8 CLEANUP
3.9 RESTORATION OF STORAGE AREA
-- End of Section Table of Contents --
SECTION 01 50 00 Page 2
SECTION 01 50 00
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
AMENDMENT NO. 0003
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2023; ERTA 1 2024; TIA 24-1; TIA 25-2)
National Electrical Code
NFPA 241 (2022; ERTA 22-1) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)
MUTCD (2009; Rev 2012) Manual on Uniform Traffic Control Devices
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Construction Site Plan ; G, RO
Haul Road and Access Ramp Plan ; G, RO
Contractor Computer Cybersecurity Compliance Statements ; G, RO
Contractor Temporary Network Cybersecurity Compliance Statements ; G, RO
1.3 CONSTRUCTION SITE PLAN
Prior to the start of work, submit for Government approval a site plan
SECTION 01 50 00 Page 3 showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
1.4 WORKING HOURS
Limit working hours from dawn until dusk, Monday through Saturday. No work will be accomplished on Federal holidays or Sundays without written approval. Requests for work during restricted times need to be submitted a minimum of 5 calendar days in advance.
1.5 DOD CONDITION OF READINESS (COR)
DOD will set the Condition of Readiness (COR) based on the weather forecast for sustained winds 50 knots ( 58 mph ) or greater. Contact the Contracting Officer for the current COR setting.
Monitor weather conditions a minimum of twice a day and take appropriate actions according to the approved Emergency Plan in the accepted Accident Prevention Plan, EM 385-1-1 Emergency Plan requirements and the instructions below.
Unless otherwise directed by the Contracting Officer, comply with:
a. Condition FOUR (Sustained winds of 58 mph or greater expected within 72 hours): Normal daily jobsite cleanup and good housekeeping practices. Collect and store in piles or containers scrap lumber, waste material, and rubbish for removal and disposal at the close of each work day. Maintain the construction site including storage areas, free of accumulation of debris. Stack form lumber in neat piles less than 3.3 feet high. Remove all debris, trash, or objects that could become missile hazards. Review requirements pertaining to "Condition THREE" and continue action as necessary to attain "Condition FOUR" readiness. Contact Contracting Officer for weather and COR updates and completion of required actions.
b. Condition THREE (Sustained winds of 58 mph or greater expected within 48 hours): Maintain "Condition FOUR" requirements and commence securing operations necessary for "Condition ONE" which cannot be completed within 18 hours. Cease all routine activities which might interfere with securing operations. Commence securing and stow all gear and portable equipment. Make preparations for securing buildings. Reinforce or remove formwork and scaffolding. Secure machinery, tools, equipment, materials, or remove from the jobsite.
Expend every effort to clear all missile hazards and loose equipment from general base areas. Contact Contracting Officer for weather and COR updates and completion of required actions. Review requirements pertaining to "Condition TWO" and continue action as necessary to attain "Condition THREE" readiness.
c. Condition TWO (Sustained winds of 58 mph or greater expected within 24 hours): Secure the jobsite, and leave Government premises.
SECTION 01 50 00 Page 4
d. Condition ONE. (Sustained winds of 58 mph or greater expected within 12 hours): Contractor access to the jobsite and Government premises is prohibited.
1.6 CYBERSECURITY DURING CONSTRUCTION
Meet the following requirements throughout the construction process.
1.6.1 Contractor Computer Equipment
Contractor owned computers may be used for construction. When used, contractor computers must meet the following requirements:
1.6.1.1 Operating System
The operating system must be an operating system currently supported by the manufacturer of the operating system. The operating system must be current on security patches and operating system manufacturer required updates.
1.6.1.2 Anti-Malware Software
The computer must run anti-malware software from a reputable software manufacturer. Anti-malware software must be a version currently supported by the software manufacturer, must be current on all patches and updates, and must use the latest definitions file. All computers used on this project must be scanned using the installed software at least once per day.
1.6.1.3 Passwords and Passphrases
The passwords and passphrases for all computers must be changed from their default values. Passwords must be a minimum of eight characters with a minimum of one uppercase letter, one lowercase letter, one number and one special character.
1.6.1.4 Contractor Computer Cybersecurity Compliance Statements
Provide a single submittal containing completed Contractor Computer Cybersecurity Compliance Statements for each company using contractor owned computers. Contractor Computer Cybersecurity Compliance Statements must use the template published at https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/ufgs-01-50-00 Each Statement must be signed by a cybersecurity representative for the relevant company.
1.6.2 Temporary IP Networks
Temporary Contractor-installed IP networks may be used during construction. When used, temporary contractor-installed IP networks must meet the following requirements:
1.6.2.1 Network Boundaries and Connections
The network must not extend outside the project site and must not connect to any IP network other than IP networks provided under this project or Government furnished IP networks provided for this purpose. Any and all
SECTION 01 50 00 Page 5 network access from outside the project site is prohibited.
1.6.3 Government Access to Network
Government personnel, as defined, prescribed, and identified by the Contracting Officer, must be allowed to have complete and immediate access to the network at any time in order to verify compliance with this specification. If there is a Government agency responsible for network access, identify that agency.
1.6.4 Temporary Wireless IP Networks
1.6.4.1 Contractor Provided Wi-Fi Network
Provide standalone Wi-Fi network for authorized Government personnel.
Network access must be available throughout the jobsite and for the entire Contract period. The Government will use the Wi-Fi service for coordination in the field and related activities. Do not attach or connect the temporary Wi-Fi network to Government networks or systems unrelated to construction activities.
Password information must adhere to requirements outlined in Paragraph PASSWORDS AND PASSPHRASES. Provide password and Wi-Fi network name (SSID) to the Contracting Officer for Government personnel access. Wi-Fi performance must be capable of handling bandwidth to support Government and Contractor activities, including drawing and model access onsite.
Provide a point of contact for reporting Wi-Fi outages.
1.6.4.2 Temporary Wireless IP Networks Security
In addition to the other requirements on temporary IP networks, temporary wireless IP (WiFi) networks must not interfere with existing wireless network and must use WPA2 security. Network names (SSID) for wireless networks must be changed from their default values.
1.6.5 Passwords and Passphrases
The passwords and passphrases for all network devices and network access must be changed from their default values. Passwords must be a minimum 8 characters with a minimum of one uppercase letter, one lowercase letter, one number and one special character.
1.6.6 Contractor Temporary Network Cybersecurity Compliance Statements
Provide a single submittal containing completed Contractor Temporary Network Cybersecurity Compliance Statements for each company implementing a temporary IP network. Contractor Temporary Network Cybersecurity Compliance Statements must use the template published at https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/ufgs-01-50-00 Each Statement must be signed by a cybersecurity representative for the relevant company. If no temporary IP networks will be used, provide a single copy of the Statement indicating this.
SECTION 01 50 00 Page 6
PART 2 PRODUCTS
2.1 TEMPORARY SIGNAGE
2.1.1 Bulletin Board
Prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the Contract, Wage Rate Information poster, Safety and Health Information as required by EM 385-1-1 and other information approved by the Contracting Officer. Coordinate requirements herein with 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS. Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, and in location as approved by the Contracting Officer.
2.1.2 Project Identification Signs
The requirements for the signs, their content, and location are as specified in Section 01 58 13.01 45 PROJECT IDENTIFICATION. Erect signs within 15 days after receipt of the notice to proceed. Correct the data required by the safety sign daily, with light colored metallic or non-metallic numerals.
2.1.3 Warning Signs
Post temporary signs, tags, and labels to give workers and the public adequate warning and caution of construction hazards according to the EM 385-1-1 . Attach signs to the perimeter fencing every 150 feet warning the public of the presence of construction hazards. Signs must require unauthorized persons to keep out of the construction site. Correct the data required by safety signs daily. Post signs at all points of entry designating the construction site as a hard hat area.
2.2 TEMPORARY TRAFFIC CONTROL
2.2.1 Haul Roads and Access Ramps
Construct access and haul roads necessary for proper prosecution of the work under this Contract in accordance with EM 385-1-1 . Construct with suitable grades and widths; avoid sharp curves, blind corners, and dangerous cross traffic. Submit haul road and access ramp plan for approval. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and haul roads are subject to approval by the Contracting Officer. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations.
2.2.2 Barricades
Erect and maintain temporary barricades to limit public access to hazardous areas. Barricades are required whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of
SECTION 01 50 00 Page 7 the hazard during both day and night.
2.3 FENCING
Provide fencing along the construction site and at all open excavations and tunnels to control access by unauthorized personnel. Safety fencing must be highly visible to be seen by pedestrians and vehicular traffic.
All fencing must meet the requirements of EM 385-1-1 . Remove the fence upon completion and acceptance of the work.
To block public view of the construction, enclose the project work area and Contractor lay-down area with a 8 foot high chain link fence and gates with brown, UV light resistant, plastic fabric mesh netting (similar to tennis court or other screening).
2.3.1 Polyethylene Mesh Safety Fencing
Temporary safety fencing must be a high visibility orange colored, high density polyethylene grid, a minimum of 48 inches high and maximum mesh size of 2 inches . Fencing must extend from the grade to a minimum of 48 inches above the grade and be tightly secured to T-posts spaced as necessary to maintain a rigid and taut fence. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.2 Chain Link Panel Fencing
Temporary panel fencing must be galvanized steel chain link panels 8 feet high. Multiple fencing panels may be linked together at the bases to form long spans as needed. Each panel base must be weighted down using sand bags or other suitable materials in order for the fencing to withstand anticipated winds while remaining upright. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.3 Post-Driven Chain Link Fencing
Temporary post-driven fencing must be galvanized chain link fencing 8 feet high supported by an tightly secured to galvanized steel posts driven below grade. Fence posts must be located on minimum 10 foot centers.
Posts may be set in various surfaces such as sand, soil, asphalt or concrete as necessary. Chain link fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection. Completely remove fencing and posts at the completion of construction and restore surfaces disturbed or damaged to its original condition. Locate and identify underground utilities prior to setting fence posts. Equip fence with a lockable gate. Gate must remain locked when construction personnel are not present.
2.4 TEMPORARY WIRING
Provide temporary wiring in accordance with EM 385-1-1 , NFPA 241 and NFPA 70 . Include monthly inspection and testing of all equipment and apparatus.
SECTION 01 50 00 Page 8
PART 3 EXECUTION
3.1 AVAILABILITY AND USE OF UTILITY SERVICES
3.1.1 Temporary Utilities
Provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.
3.1.2 Sanitation
Provide and maintain within the construction area minimum field-type sanitary facilities in accordance with EM 385-1-1 . Locate the facilities behind the construction fence or out of the public view. Clean units and empty wastes at least once a week or more frequently into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility. Obtain approval from the system owner prior to discharge into a municipal, district, or commercial sanitary sewer system. Penalties or fines associated with improper discharge will be the responsibility of the Contractor. Coordinate with the Contracting Officer and follow station regulations and procedures when discharging into the station sanitary sewer system. Maintain these conveniences at all times.
Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.
3.1.3 Telephone
Make arrangements and pay all costs for telephone facilities desired.
3.1.4 Fire Protection
Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.
3.2 STATION OPERATION AFFECT ON CONTRACTOR OPERATIONS
3.2.1 Restricted Access Areas
The Government will monitor work in areas indicated. Notify Contracting Officer at least 14 calendar days prior to starting work in these areas.
3.3 TRAFFIC PROVISIONS
3.3.1 Maintenance of Traffic
a. Conduct operations in a manner that will not close a thoroughfare or interfere with traffic on railways or highways except with written permission of the Contracting Officer at least 15 calendar days prior to the proposed modification date, for Government approval detailing the proposed controls to traffic movement for approval. The plan must be in accordance with State and local regulations and the MUTCD, Part VI. Make all notifications and obtain all permits required for modification to traffic movements outside Station's jurisdiction.
Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.
SECTION 01 50 00 Page 9
b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer prior to starting any activity that will obstruct traffic.
c. Provide, erect, and maintain, at Contractor's expense, lights, barriers, signals, passageways, detours, Life Safety Signage, overhead protection, and other items that may be required by the authority having jurisdiction.
d. Provide cones, signs, barricades, lights, or other traffic control devices and personnel required to control traffic. Do not use foil-backed material for temporary pavement marking because of its potential to conduct electricity during accidents involving downed power lines.
3.3.2 Protection of Traffic
Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Provide self-illuminated (lighted) barricades during hours of darkness. All personnel working in roadways will wear brightly-colored vests or other high visibility apparel in accordance with EM 385-1-1 . Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of damage to roads caused by construction operations.
3.3.3 Rush Hour Restrictions
Do not interfere with the peak traffic flows preceding and during normal operations without notification to and approval by the Contracting Officer.
3.3.4 Dust Control
Dust control methods and procedures must be approved by the Contracting Officer. Coordinate dust control methods.
3.4 CONTRACTOR'S TEMPORARY FACILITIES
Contractor is responsible for security of their property. Due to a history of theft at the job site, the Contractor assumes full responsibility for establishing and implementing all necessary security plans, measures, and procedures to protect the site. Provide adequate outside security lighting at the temporary facilities. Trailers must be anchored to resist high winds and meet applicable state or local standards for anchoring mobile trailers. Coordinate anchoring with EM 385-1-1 . The Contract Clause entitled "FAR 52.236-10, Operations and Storage Areas" and the following apply:
SECTION 01 50 00 Page 10
3.4.1 Administrative Field Offices (AM#3)
Provide and maintain administrative field office facilities within the construction area at the designated site. Government office and warehouse facilities will not be available to the Contractor's personnel. Government office and warehouse facilities will be available to the Contractor's personnel.
In the event a new building is constructed for the temporary project field office, it must be a minimum 12 feet in width, 16 feet in length and have a minimum of 7 feet headroom. Equip the building with approved electrical wiring, at least one double convenience outlet and the required switches and fuses to provide 110-120 volt power. Provide a work table with stool, desk with chair, two additional chairs, and one legal size file cabinet that can be locked. The building must be waterproof, supplied with a heater, have a minimum of two doors, electric lights, a telephone, a battery-operated smoke detector alarm, a sufficient number of adjustable windows for adequate light and ventilation, and a supply of approved drinking water. Provide approved sanitary facilities. Screen the windows and doors and provide the doors with deadbolt type locking devices or a padlock and heavy-duty hasp bolted to the door. Door hinge pins must be non-removable. Arrange the windows to open and to be securely fastened from the inside. Protect glass panels in windows by bars or heavy mesh screens to prevent easy access. In warm weather, provide air conditioning capable of maintaining the office at 50 percent relative humidity and a room temperature 20 degrees F below the outside temperature when the outside temperature is 95 degrees F . Unless otherwise directed by the Contracting Officer, remove the building from the site upon completion and acceptance of the work.
3.4.2 Quality Control Manager Records and Field Office
Provide on the jobsite an office with approximately 200 square feet of useful floor area for the exclusive use of the QC Manager. Provide a weathertight structure with adequate heating and cooling, toilet facilities, lighting, ventilation, a 4 by 8 foot plan table, a standard size office desk and chair, computer station, and working communications facilities. Provide either a 1,500 watt radiant heater and a window-mounted air conditioner rated at 9,000 Btus minimum or a window-mounted heat pump of the same minimum heating and cooling ratings.
Provide a door with a cylinder lock and windows with locking hardware.
Make utility connections. Locate as directed. File quality control records in the office and make available at all times to the Government.
After completion of the work, remove the entire structure from the site.
3.4.3 Storage Area
Construct a temporary 6 foot high chain link fence around trailers and materials. Include plastic strip inserts, colored green, so that visibility through the fence is obstructed. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Do not place or store trailers, materials, or equipment outside the fenced area unless such trailers, materials, or equipment are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the installation boundaries. Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on the current day.
Do not stockpile materials outside the fence in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting
SECTION 01 50 00 Page 11 equipment, cranes, trucks, and like equipment within the fenced area at the end of each work day.
Keep fencing in a state of good repair and proper alignment. If the Contractor elects to traverse grassed or unpaved areas which are not established roadways with construction equipment or other vehicles, cover the grassed or unpaved areas with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways; gravel gradation must be at the Contractor's discretion. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, structures, under trailers, and in areas not accessible to mowers must be edged or trimmed neatly.
3.4.4 Supplemental Storage Area
Upon request, and pending availability, the Contracting Officer will designate another or supplemental area for the use and storage of trailers, equipment, and materials. This area may not be in close proximity of the construction site but will be within the installation boundaries. Maintain the area in a clean and orderly fashion and secured if needed to protect supplies and equipment. Utilities will not be provided to this area by the Government.
3.4.5 Appearance of Trailers
a. Trailers must be roadworthy and comply with all appropriate state and local vehicle requirements. Trailers which are rusted, have peeling paint or are otherwise in need of repair will not be allowed on Installation property. Trailers must present a clean and neat exterior appearance and be in a state of good repair.
b. Maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal at the Contractor's expense.
3.4.6 Safety Systems
Protect the integrity of all installed safety systems or personnel safety devices. Obtain prior approval from the Contracting Officer if entrance into systems serving safety devices is required. If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish Contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer.
3.4.7 Weather Protection of Temporary Facilities and Stored Materials
Take necessary precautions to ensure that roof openings and other critical openings in the building are monitored carefully. Take immediate actions required to seal off such openings when rain or other detrimental weather is imminent, and at the end of each workday. Ensure that the openings are completely sealed off to protect materials and equipment in the building from damage.
3.4.7.1 Building and Site Storm Protection
When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.
Precautions must include, but are not limited to, closing openings;
SECTION 01 50 00 Page 12 removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work. Close openings in the work when storms of lesser intensity pose a threat to the work or any nearby Government property.
3.5 GOVERNMENT FIELD OFFICE
3.5.1 Resident Engineer's Office
Provide the Government Resident Engineer with an office, approximately 400 square feet in floor area, located where directed and providing space heat, air conditioning unit, electric light and power, and toilet facilities consisting of one lavatory and one water closet complete with connections to water and sewer mains. If a sewer main is not available, then it may be substituted for a chemical toilet. If a water main is not available, then it may be substituted for a sufficient supply of potable water to last the duration of construction. Provide a mail slot in the door or a lockable mail box mounted on the surface of the door. Include a 4 by 8 foot plan table, computer work space a standard size office desk and chair, telephone and internet connection. At completion of the project, the office will remain the property of the Contractor and be removed from the site. Utilities must be connected and disconnected in accordance with local codes and to the satisfaction of the Contracting Officer. Compliance with safety and appearance requirements for temporary facilities stated in previous paragraphs is required.
3.5.2 Trailer-Type Mobile Office
The option is available to, furnish and maintain a trailer-type mobile office acceptable to the Contracting Officer to meet the requirements of the minimum facilities specified above. Securely anchor the trailer to the ground at all four corners to guard against movement during high winds. Coordinate requirements for proper anchoring with EM 385-1-1 .
3.6 PLANT COMMUNICATIONS
Whenever the individual elements of the plant are located so that operation by normal voice between these elements is not satisfactory, install a satisfactory means of communication, such as telephone or other suitable devices and make available for use by Government personnel.
3.7 TEMPORARY PROJECT SAFETY FENCING
As soon as practicable, but not later than 15 days after the date established for commencement of work, furnish and erect temporary project safety fencing at the work site. Maintain the safety fencing during the life of the Contract and, upon completion and acceptance of the work, remove from the work site.
3.8 CLEANUP
Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store all salvageable materials resulting from demolition activities within the fenced area
SECTION 01 50 00 Page 13 described above or at the supplemental storage area. Neatly stack stored materials not in trailers, whether new or salvaged.
3.9 RESTORATION OF STORAGE AREA
Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and all other temporary products from the site.
After removal of trailers, materials, and equipment from within the fenced area, remove the fence. Restore areas used during the performance of the Contract to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including top soil and seeding as necessary.
-- End of Section --
SECTION 01 50 00 Page 14
| 01 50 00 - TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS AMENDMENT NO. 0003 |
| 01 50 00 - TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 CONSTRUCTION SITE PLAN |
| 1.4 WORKING HOURS |
| 1.5 DOD CONDITION OF READINESS COR |
| 1.6 CYBERSECURITY DURING CONSTRUCTION |
| 1.6.1 Contractor Computer Equipment |
| 1.6.1.1 Operating System |
| 1.6.1.2 Anti-Malware Software |
| 1.6.1.3 Passwords and Passphrases |
| 1.6.1.4 Contractor Computer Cybersecurity Compliance Statements |
| 1.6.2 Temporary IP Networks |
| 1.6.2.1 Network Boundaries and Connections |
| 1.6.3 Government Access to Network |
| 1.6.4 Temporary Wireless IP Networks |
| 1.6.4.1 Contractor Provided Wi-Fi Network |
| 1.6.4.2 Temporary Wireless IP Networks Security |
| 1.6.5 Passwords and Passphrases |
| 1.6.6 Contractor Temporary Network Cybersecurity Compliance Statements |
| PART 2 PRODUCTS |
| 2.1 TEMPORARY SIGNAGE |
| 2.1.1 Bulletin Board |
| 2.1.2 Project Identification Signs |
| 2.1.3 Warning Signs |
| 2.2 TEMPORARY TRAFFIC CONTROL |
| 2.2.1 Haul Roads and Access Ramps |
| 2.2.2 Barricades |
| 2.3 FENCING |
| 2.3.1 Polyethylene Mesh Safety Fencing |
| 2.3.2 Chain Link Panel Fencing |
| 2.3.3 Post-Driven Chain Link Fencing |
2.4 TEMPORARY WIRING
| PART 3 EXECUTION |
| 3.1 AVAILABILITY AND USE OF UTILITY SERVICES |
| 3.1.1 Temporary Utilities |
| 3.1.2 Sanitation |
| 3.1.3 Telephone |
| 3.1.4 Fire Protection |
| 3.2 STATION OPERATION AFFECT ON CONTRACTOR OPERATIONS |
| 3.2.1 Restricted Access Areas |
| 3.3 TRAFFIC PROVISIONS |
| 3.3.1 Maintenance of Traffic |
| 3.3.2 Protection of Traffic |
| 3.3.3 Rush Hour Restrictions |
| 3.3.4 Dust Control |
| 3.4 CONTRACTOR'S TEMPORARY FACILITIES |
| 3.4.1 Administrative Field Offices AM#3 |
| 3.4.2 Quality Control Manager Records and Field Office |
| 3.4.3 Storage Area |
| 3.4.4 Supplemental Storage Area |
| 3.4.5 Appearance of Trailers |
| 3.4.6 Safety Systems |
| 3.4.7 Weather Protection of Temporary Facilities and Stored Materials |
| 3.4.7.1 Building and Site Storm Protection |
| 3.5 GOVERNMENT FIELD OFFICE |
| 3.5.1 Resident Engineer's Office |
| 3.5.2 Trailer-Type Mobile Office |