ABSTRACT_W912HY26BA002.KOSigned.pdf

PDF 262 KB Posted

Attached to
Sabine-Neches Waterway, Texas, Sabine-Neches Maintenance Dredging
Solicitation number
W912HY26BA002
Issued by

About this file

This is an Abstract of Offers for a federal dredging contract solicitation issued by the U.S. Army Engineer District (USAED) Galveston. Solicitation number W912HY26BA002 was issued on 06/29/2026 with a bid opening date of 08/04/2026 for the Sabine-Neches Waterway maintenance dredging project in Texas. The solicitation included two amendments.

The contract encompasses dredging operations and associated services organized into Schedule 1 (base work), Option 1, and Option 2. Schedule 1 consists of ten line items including mobilization and demobilization ($2.975 million government estimate), pipeline management ($429,000), dredging of sections 89A and 90-93 (919,000 cubic yards at $5.66/CY), hickory cove marsh beneficial use activities including temporary berm containment and breach plug berm, silt fencing (9,750 linear feet at $27.01/LF), final marsh condition survey, flashboard riser structures, endangered species monitoring, and as-built drawings. The total government estimate for Schedule 1 is $13,858,887.50. Option 1 includes mobilization and demobilization for the Nelda Stark Unit placement, pipeline management, dredging of Section 305 (725,000 cubic yards), Nelda Stark beneficial use temporary berm containment, and related surveys and structures, totaling $7,416,250.00. Option 2 covers pipeline management, dredging of Section 706 (215,000 cubic yards), and standby services for Port Arthur dredging (72 hours), totaling $1,360,185.28. The complete contract value including all options is $22,635,322.78. Six offerors submitted bids: Callan Marine Limited ($58,281,486), Inland Dredging Company LLC ($34,874,400), Manson Construction Co ($59,898,975), Mike Hooks LLC ($31,233,110 as the apparent low bidder at 37.98% higher than government estimate), Orion Marine Construction Inc ($33,933,500), and Weeks Marine Inc ($55,136,000). All offerors were classified as other than small businesses.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT ESTIMATED

PRICE AMOUNT

1 JOB $2,975,000.00 2,975,000.00$

1 JOB 429,000.00$ 429,000.00$

919,000 CY 5.66$ 5,201,540.00$

1 JOB 257,000.00$ 257,000.00$

1 JOB 4,385,000.00$ 4,385,000.00$

9,750 LF 27.01$ 263,347.50$

1 JOB $ 50,000.00 $ 50,000.00

1 JOB 89,000.00$ 89,000.00$

1 JOB 194,000.00$ 194,000.00$

1 JOB 15,000.00$ 15,000.00$

13,858,887.50$

1 JOB $1,378,000.00 1,378,000.00$

1 JOB 541,000.00$ 541,000.00$

725,000 CY 6.29$ 4,560,250.00$

1 JOB 800,000.00$ 800,000.00$

1 JOB 33,000.00$ 33,000.00$

1 JOB 89,000.00$ 89,000.00$

1 JOB $ 15,000.00 $ 15,000.00

7,416,250.00$ 21,275,137.50$

1 JOB $337,000.00 $337,000.00

215,000 CY 3.93$ 844,950.00$

72 HR 2,475.49$ 178,235.28$

1,360,185.28$

22,635,322.78$

0017 Nelda Stark Unit Beneficial Use As-Built Drawings

Standby for Port of Port Arthur Dredging

Pipeline Management

Dredging, Section Nos 89A, and 90-93

0007 Final Marsh Condition Survey 0008 Flashboard Riser Structures

Mobilization and Demobilization

TOTAL SCHEDULE 1

Hickory Cove Marsh Beneficial Use - Temporary Berm Containment

Hickory Cove Marsh Beneficial Use - Breach Plug Berm

0006 Hickory Cove Marsh - Silt Fencing

0009 Endangered Species Monitoring 0010 Hickory Cove Marsh As-Built Drawings

ABSTRACT OF OFFERS

Solicitation No.: W912HY26BA002 Date Issued: 06/29/2026 Date Opened: 08/04/2026 Issuing Office: USAED- Galveston Page 1 of 7

Project Title: Sabine-Neches Waterway, Texas, Sabine-Neches Maintenance Dredging

Number of Amendments Issued: 2 GOVERNMENT ESTIMATE (Without Profit)

NO.

ESTIMATED

DESCRIPTION QUANTITY

ITEM

OPTION 1

Mobilization and Demobilization for Nelda Stark Unit Placement - Option 1

TOTAL OPTION 1

0012 Pipeline Management

0013 Dredging, Section No 305

Nelda Stark Beneficial Usse - Temporary Berm Containment

0015 Final Marsh Condition Survey

0016 Flashboard Riser Structures

TOTAL SCHEDULE 1 AND OPTION 1

OPTION 2

0018 Pipeline Management

0019 Dredging Section No 706

TOTAL OPTION 2

TOTAL SCHEDULE 1 AND OPTION 1 & 2

I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT ALL OFFERS RECEIVED TO THIS

SOLICITATION.

Mirian R. Tudor Contracting Officer

*The apparent low bidder, Mike Hooks LLC, is 37.98% higher than the Government Estimate.

1 JOB 7894000.00 7,894,000.00$

1 JOB 1,794,000.00$ 1,794,000.00$

919,000 CY 13.90$ 12,774,100.00$

1 JOB 1,394,000.00$ 1,394,000.00$

1 JOB 17,990,886.00$ 17,990,886.00$

9,750 LF 70.00$ 682,500.00$

1 JOB $ 45,000.00 $ 45,000.00

1 JOB 225,000.00$ 225,000.00$

1 JOB 630,000.00$ 630,000.00$

1 JOB 15,000.00$ 15,000.00$

43,444,486.00$

1 JOB 2200000.00 2,200,000.00$

1 JOB 325,000.00$ 325,000.00$

725,000 CY 7.50$ 5,437,500.00$

1 JOB 4,100,000.00$ 4,100,000.00$

1 JOB 20,000.00$ 20,000.00$

1 JOB 275,000.00$ 275,000.00$

1 JOB $ 15,000.00 $ 15,000.00

12,372,500.00$ 55,816,986.00$

1 JOB $600,000.00 $600,000.00

215,000 CY 7.50$ 1,612,500.00$

72 HR 3,500.00$ 252,000.00$

2,464,500.00$

58,281,486.00$

Issuing Office: USAED-Galveston Page 2 of 7 Solicitation No.: W912HY26BA002 Date Issued: 06/29/2026 Date Opened: 08/04/2026

ITEM ESTIMATED

Nelda Stark Beneficial Usse - Temporary Berm Dredging, Section No 305 Pipeline Management Mobilization and Demobilization for Nelda Stark Unit

Mobilization and Demobilization Pipeline Management

Business Size: Other than Small Business

QUANTITY

Final Marsh Condition Survey

OPTION 1

TOTAL SCHEDULE 1

Dredging Section No 706 Standby for Port of Port Arthur Dredging

TOTAL OPTION 2

TOTAL SCHEDULE 1 AND OPTION 1 & 2

OPTION 2

Pipeline Management0018

NO.

Offeror #1 : Callan Marine Limited (CAGE 64MM7)

DESCRIPTION

Dredging, Section Nos 89A, and 90-93 Hickory Cove Marsh Beneficial Use - Temporary Berm

0005 Hickory Cove Marsh Beneficial Use - Breach Plug 0006 Hickory Cove Marsh - Silt Fencing 0007 Final Marsh Condition Survey 0008 Flashboard Riser Structures 0009 Endangered Species Monitoring

TOTAL OPTION 1

TOTAL SCHEDULE 1 AND OPTION 1

0017 Nelda Stark Unit Beneficial Use As-Built Drawings

Hickory Cove Marsh As-Built Drawings0010

Flashboard Riser Structures

1 JOB $3,908,600.00 3,908,600.00$

1 JOB 1,715,000.00$ 1,715,000.00$

919,000 CY 7.00$ 6,433,000.00$

1 JOB 1,000,000.00$ 1,000,000.00$

1 JOB 6,725,000.00$ 6,725,000.00$

9,750 LF 40.00$ 390,000.00$

1 JOB $ 70,000.00 $ 70,000.00

1 JOB 400,000.00$ 400,000.00$

1 JOB 475,000.00$ 475,000.00$

1 JOB 70,000.00$ 70,000.00$

21,186,600.00$

1 JOB $700,000.00 700,000.00$

1 JOB 2,000,000.00$ 2,000,000.00$

725,000 CY 8.00$ 5,800,000.00$

1 JOB 1,990,000.00$ 1,990,000.00$

1 JOB 250,000.00$ 250,000.00$

1 JOB 400,000.00$ 400,000.00$

1 JOB $ 70,000.00 $ 70,000.00

11,210,000.00$ 32,396,600.00$

1 JOB $800,000.00 $800,000.00

215,000 CY 7.00$ 1,505,000.00$

72 HR 2,400.00$ 172,800.00$

2,477,800.00$

34,874,400.00$ TOTAL SCHEDULE 1 AND OPTION 1 & 2

TOTAL OPTION 2

Solicitation No.: W912HY26BA002 Date Issued: 06/29/2026 Date Opened: 08/04/2026 Issuing Office: USAED-Galveston Page 3 of 7 Offeror #2 : Inland Dredging Company LLC (CAGE 093F7) Business Size: Other than Small Business

ITEM ESTIMATED

NO. DESCRIPTION QUANTITY

Hickory Cove Marsh Beneficial Use - Breach Plug Hickory Cove Marsh Beneficial Use - Temporary Berm Dredging, Section Nos 89A, and 90-93 Pipeline Management Mobilization and Demobilization

Final Marsh Condition Survey Hickory Cove Marsh - Silt Fencing

TOTAL SCHEDULE 1

Hickory Cove Marsh As-Built Drawings Endangered Species Monitoring Flashboard Riser Structures

OPTION 1

0016 Flashboard Riser Structures

Final Marsh Condition Survey

Nelda Stark Beneficial Usse - Temporary Berm Containment

Dredging, Section No 305 Pipeline Management Mobilization and Demobilization for Nelda Stark Unit

0017 Nelda Stark Unit Beneficial Use As-Built Drawings

TOTAL OPTION 1

TOTAL SCHEDULE 1 AND OPTION 1

OPTION 2

0018 Pipeline Management 0019 Dredging Section No 706

0020 Standby for Port of Port Arthur Dredging

1 JOB $4,950,000.00 4,950,000.00$

1 JOB 5,700,000.00$ 5,700,000.00$

919,000 CY 8.25$ 7,581,750.00$

1 JOB 975,000.00$ 975,000.00$

1 JOB 14,500,000.00$ 14,500,000.00$

9,750 LF 69.50$ 677,625.00$

1 JOB $ 32,750.00 $ 32,750.00

1 JOB 42,000.00$ 42,000.00$

1 JOB 85,750.00$ 85,750.00$

1 JOB 1,700.00$ 1,700.00$

34,546,575.00$

1 JOB $3,500,000.00 3,500,000.00$

1 JOB 8,000,000.00$ 8,000,000.00$

725,000 CY 7.00$ 5,075,000.00$

1 JOB 3,750,000.00$ 3,750,000.00$

1 JOB 17,000.00$ 17,000.00$

1 JOB 75,000.00$ 75,000.00$

1 JOB $ 1,700.00 $ 1,700.00

20,418,700.00$ 54,965,275.00$

1 JOB $3,520,000.00 $3,520,000.00

215,000 CY 4.70$ 1,010,500.00$

72 HR 5,600.00$ 403,200.00$

4,933,700.00$

59,898,975.00$

0020 Standby for Port of Port Arthur Dredging

TOTAL OPTION 2

TOTAL SCHEDULE 1 AND OPTION 1 & 2

OPTION 2

0018 Pipeline Management 0019 Dredging Section No 706

0016 Flashboard Riser Structures 0017 Nelda Stark Unit Beneficial Use As-Built Drawings

TOTAL OPTION 1

TOTAL SCHEDULE 1 AND OPTION 1

0011 Mobilization and Demobilization for Nelda Stark Unit 0012 Pipeline Management 0013 Dredging, Section No 305 0014 Nelda Stark Beneficial Usse - Temporary Berm 0015 Final Marsh Condition Survey

TOTAL SCHEDULE 1

OPTION 1

0006 Hickory Cove Marsh - Silt Fencing 0007 Final Marsh Condition Survey 0008 Flashboard Riser Structures 0009 Endangered Species Monitoring 0010 Hickory Cove Marsh As-Built Drawings

0001 Mobilization and Demobilization 0002 Pipeline Management 0003 Dredging, Section Nos 89A, and 90-93 0004 Hickory Cove Marsh Beneficial Use - Temporary Berm 0005 Hickory Cove Marsh Beneficial Use - Breach Plug

Business Size: Other than Small Business

ITEM ESTIMATED

NO. DESCRIPTION QUANTITY

Solicitation No.: W912HY26BA002 Date Issued: 06/29/2026 Date Opened: 08/04/2026

Offeror #3 : Manson Construction Co (CAGE 0FCP9) Issuing Office: USAED-Galveston Page 4 of 7

1 JOB $3,650,000.00 3,650,000.00$

1 JOB 750,000.00$ 750,000.00$

919,000 CY 10.60$ 9,741,400.00$

1 JOB 759,000.00$ 759,000.00$

1 JOB 6,210,000.00$ 6,210,000.00$

9,750 LF 36.56$ 356,460.00$

1 JOB $ 60,000.00 $ 60,000.00

1 JOB 360,000.00$ 360,000.00$

1 JOB 200,000.00$ 200,000.00$

1 JOB 60,000.00$ 60,000.00$

22,146,860.00$

1 JOB $600,000.00 600,000.00$

1 JOB 300,000.00$ 300,000.00$

725,000 CY 5.75$ 4,168,750.00$

1 JOB 1,920,000.00$ 1,920,000.00$

1 JOB 60,000.00$ 60,000.00$

1 JOB 300,000.00$ 300,000.00$

1 JOB $ 60,000.00 $ 60,000.00

7,408,750.00$ 29,555,610.00$

1 JOB $250,000.00 $250,000.00

215,000 CY 5.30$ 1,139,500.00$

72 HR 4,000.00$ 288,000.00$

1,677,500.00$

31,233,110.00$

0020 Standby for Port of Port Arthur Dredging

TOTAL OPTION 2

TOTAL SCHEDULE 1 AND OPTION 1 & 2

OPTION 2

0018 Pipeline Management 0019 Dredging Section No 706

0016 Flashboard Riser Structures 0017 Nelda Stark Unit Beneficial Use As-Built Drawings

TOTAL OPTION 1

TOTAL SCHEDULE 1 AND OPTION 1

0011 Mobilization and Demobilization for Nelda Stark Unit 0012 Pipeline Management 0013 Dredging, Section No 305 0014 Nelda Stark Beneficial Usse - Temporary Berm 0015 Final Marsh Condition Survey

TOTAL SCHEDULE 1

OPTION 1

0006 Hickory Cove Marsh - Silt Fencing 0007 Final Marsh Condition Survey 0008 Flashboard Riser Structures 0009 Endangered Species Monitoring 0010 Hickory Cove Marsh As-Built Drawings

0001 Mobilization and Demobilization 0002 Pipeline Management 0003 Dredging, Section Nos 89A, and 90-93 0004 Hickory Cove Marsh Beneficial Use - Temporary Berm 0005 Hickory Cove Marsh Beneficial Use - Breach Plug

Issuing Office: USAED-Galveston Page 5 of 7 Offeror #4 : Mike Hooks LLC (CAGE 0CUN7) Business Size: Other than Small Business

ITEM ESTIMATED

NO. DESCRIPTION QUANTITY

Solicitation No.: W912HY26BA002 Date Issued: 06/29/2026 Date Opened: 08/04/2026

1 JOB $2,500,000.00 2,500,000.00$

1 JOB 750,000.00$ 750,000.00$

919,000 CY 4.50$ 4,135,500.00$

1 JOB 950,000.00$ 950,000.00$

1 JOB 14,000,000.00$ 14,000,000.00$

9,750 LF 50.00$ 487,500.00$

1 JOB $ 30,000.00 $ 30,000.00

1 JOB 200,000.00$ 200,000.00$

1 JOB 250,000.00$ 250,000.00$

1 JOB 15,000.00$ 15,000.00$

23,318,000.00$

1 JOB $550,000.00 550,000.00$

1 JOB 800,000.00$ 800,000.00$

725,000 CY 5.00$ 3,625,000.00$

1 JOB 3,000,000.00$ 3,000,000.00$

1 JOB 15,000.00$ 15,000.00$

1 JOB 200,000.00$ 200,000.00$

1 JOB $ 8,500.00 $ 8,500.00

8,198,500.00$ 31,516,500.00$

1 JOB $750,000.00 $750,000.00

215,000 CY 7.00$ 1,505,000.00$

72 HR 2,250.00$ 162,000.00$

2,417,000.00$

33,933,500.00$

Solicitation No.: W912HY26BA002 Date Issued: 06/29/2026 Date Opened: 08/04/2026 Issuing Office: USAED-Galveston Offeror #5 : Orion Marine Construction Inc (CAGE 0H5D1) Business Size: Other than Small Business

ITEM ESTIMATED

NO. DESCRIPTION QUANTITY

0001 Mobilization and Demobilization 0002 Pipeline Management 0003 Dredging, Section Nos 89A, and 90-93 0004 Hickory Cove Marsh Beneficial Use - Temporary Berm 0005 Hickory Cove Marsh Beneficial Use - Breach Plug 0006 Hickory Cove Marsh - Silt Fencing 0007 Final Marsh Condition Survey 0008 Flashboard Riser Structures 0009 Endangered Species Monitoring 0010 Hickory Cove Marsh As-Built Drawings

TOTAL SCHEDULE 1

OPTION 1

0011 Mobilization and Demobilization for Nelda Stark Unit 0012 Pipeline Management 0013 Dredging, Section No 305 0014 Nelda Stark Beneficial Usse - Temporary Berm 0015 Final Marsh Condition Survey 0016 Flashboard Riser Structures 0017 Nelda Stark Unit Beneficial Use As-Built Drawings

TOTAL OPTION 1

TOTAL SCHEDULE 1 AND OPTION 1

OPTION 2

0018 Pipeline Management 0019 Dredging Section No 706 0020 Standby for Port of Port Arthur Dredging

TOTAL OPTION 2

TOTAL SCHEDULE 1 AND OPTION 1 & 2

1 JOB $13,500,000.00 13,500,000.00$

1 JOB 1,250,000.00$ 1,250,000.00$

919,000 CY 10.00$ 9,190,000.00$

1 JOB 450,000.00$ 450,000.00$

1 JOB 14,500,000.00$ 14,500,000.00$

9,750 LF 100.00$ 975,000.00$

1 JOB $ 150,000.00 $ 150,000.00

1 JOB 150,000.00$ 150,000.00$

1 JOB 500,000.00$ 500,000.00$

1 JOB 30,000.00$ 30,000.00$

40,695,000.00$

1 JOB $2,000,000.00 2,000,000.00$

1 JOB 1,000,000.00$ 1,000,000.00$

725,000 CY 7.00$ 5,075,000.00$

1 JOB 2,250,000.00$ 2,250,000.00$

1 JOB 100,000.00$ 100,000.00$

1 JOB 30,000.00$ 30,000.00$

1 JOB $ 10,000.00 $ 10,000.00

10,465,000.00$ 51,160,000.00$

1 JOB $1,250,000.00 $1,250,000.00

215,000 CY 10.00$ 2,150,000.00$

72 HR 8,000.00$ 576,000.00$

3,976,000.00$

55,136,000.00$

Solicitation No.: W912HY26BA002 Date Issued: 06/29/2026 Date Opened: 08/04/2026 Issuing Office: USAED-Galveston Page 7 of 7 Offeror #6 : Weeks Marine Inc (CAGE 1RHV3) Business Size: Other than Small Business

ITEM ESTIMATED

NO. DESCRIPTION QUANTITY

0001 Mobilization and Demobilization 0002 Pipeline Management 0003 Dredging, Section Nos 89A, and 90-93 0004 Hickory Cove Marsh Beneficial Use - Temporary Berm 0005 Hickory Cove Marsh Beneficial Use - Breach Plug 0006 Hickory Cove Marsh - Silt Fencing 0007 Final Marsh Condition Survey 0008 Flashboard Riser Structures 0009 Endangered Species Monitoring 0010 Hickory Cove Marsh As-Built Drawings

TOTAL SCHEDULE 1

OPTION 1

0011 Mobilization and Demobilization for Nelda Stark Unit 0012 Pipeline Management 0013 Dredging, Section No 305 0014 Nelda Stark Beneficial Usse - Temporary Berm 0015 Final Marsh Condition Survey 0016 Flashboard Riser Structures 0017 Nelda Stark Unit Beneficial Use As-Built Drawings

TOTAL OPTION 1

TOTAL SCHEDULE 1 AND OPTION 1

0020 Standby for Port of Port Arthur Dredging

TOTAL OPTION 2

TOTAL SCHEDULE 1 AND OPTION 1 & 2

OPTION 2

0018 Pipeline Management 0019 Dredging Section No 706

2026-08-05T11:38:41-0500
TUDOR.MIRIAN.ROSA.1069051800

File details come from the government source that posted it. Updated .