This document is a PowerPoint presentation outlining a federal contract opportunity for fronting protection of pumping stations in Port Arthur, Texas. The contract is solicitation number W912HY23R5223 from the U.S. Army Corps of Engineers Galveston District. It involves fronting protection structures, levee raises, floodwall replacements, sheet pile cut-off walls, stone armoring, road replacements, and gate/culvert replacements across multiple zones for pumping stations along the Sabine Pass to Galveston Bay hurricane and storm damage risk reduction system. The pre-proposal conference was held on February 16, 2023 and the project site visit conducted the same day. Proposals are due by March 25, 2023 and contract award is scheduled for June 15, 2023. The magnitude of construction is estimated between $25-100 million. The presentation provides detailed descriptions of work at the Alligator, Lakeside and Rhodair pumping stations as well as other areas. It outlines the bidding and evaluation process and includes specifications, drawings and other relevant information for prospective offerors.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Champions of the Coast!
Garrett J. Sullivan Project Manager
16 February 2023
Sabine Pass to Galveston Bay (S2G) Port Arthur, Texas
PAV03A Pre-Proposal Conference Solicitation No. W912HY-23-R-5223
Design-Bid-Build Contract
Port Arthur
Port Arthur Non-Federal Sponsor – USACE Partner
USACE – Galveston District Jefferson County
Drainage District No. 7
Port Arthur PAV03A Project: Solicitation No. W912HY-23-R-5223
Port Arthur PAV03A Project Pre-Proposal Conference Agenda
S2G Port Arthur Program Overview PAV03A Project Overview Bid Solicitation Schedule Important Specification Provisions Questions/Open Discussion Adjourn Pre-Proposal Meeting Conduct Site Visit to PAV03A Project Area
PAV03A Project Overview Bid Solicitation Schedule Important Specification Provisions Questions/Open Discussion
The Threat from Hurricane’s and Rising Sea Levels
The S2G Program was authorized by the Water Resources Development Act of 2018 and funded for construction through the Bipartisan Budget Act of 2018. Funding for Port Arthur projects equals $863.56 Million.
10 Contract Areas
Major Program Components
• 5.5 Miles of Earthen Levee
• 5.7 Miles of New Floodwall
• 26 New Closure Structures
• Erosion Protection
The objectives of the overall S2G Program include:
• Reducing risks to human life from coastal storm surge.
• Reducing economic damages to residents, businesses, and infrastructure.
• Enhancing energy security by reducing storm surge risk to petrochemical facilities.
• Reducing adverse physical economic impacts to waterways used for recreational and commercial purposes.
PAV03A Project Overview Bid Solicitation Schedule Important Specification Provisions Questions/Open Discussion
The S2G Program was authorized by the Water Resources Development Act of 2018 and funded for construction through the Bipartisan Budget Act of 2018. Funding for Port Arthur projects equals $863.56 Million.
10 Contract Areas
Major Program Components
• 5.5 Miles of Earthen Levee
• 5.7 Miles of New Floodwall
• 26 New Closure Structures
• Erosion Protection
The objectives of the overall S2G Program include:
• Reducing risks to human life from coastal storm surge.
• Reducing economic damages to residents, businesses, and infrastructure.
• Enhancing energy security by reducing storm surge risk to petrochemical facilities.
• Reducing adverse physical economic impacts to waterways used for recreational and commercial purposes.
Alligator Pump Station
Zone 5
Lakeside Pump StationZone 6
Zone 8 Replace FM365 Road Closure Gate, Gate Well Structure and Culvert
PAV03A Project Zones 5-6-7-8Rhodair Pump StationZone 7
Port Arthur PAV03A Project: General Description of the Work
Port Arthur PAV03A Project Overview: Bid Schedule
Bid Schedule
Port Arthur PAV03A Project Overview: Design-Bid-Build Contract
Major Project Elements - PAV03A Contract
• Fronting Protection for 3 Pump Stations (Alligator, Lakeside, and Rhodair) ~ 1,000 ft (Zones 5, 6, and 7)
• Earthen Levee Raise ~ 370 ft. (Various Areas)
• Concrete Floodwall Replacement ~ 950 ft (Zones 5, 6, & 7)
• Sheet Pile Cut-Off Wall Installation (Zones 5, 6, 7 ,& 8)
• Levee System Stone Armoring Protection (Zones 5, 6, 7, & 8)
• Levee All-Weather Surface Road Replace (Zone 5, 6, & 7)
• FM365 Road Closure Gate Replacement (Zone 8)
• Gate Well Structure and Culvert Replacement (Zone 8)
Alligator Pump Station Improvements
Zone 5
Lakeside Pump Station ImprovementsZone 6
Zone 8 Replace FM365 Road Closure Gate, Gate Well Structure and Culvert
Rhodair Pump Station Improvements
Zone 7
Alligator Pumping Station
Temporary Cofferdam shown here is No Longer In-Place
Note: A portion of Sheet Pile walls was not removed, but Cut-Off below the water level
Temporary Structures
2 Stage Temporary Cofferdam
Lakeside Pumping Station
Demolition Plan
Construction PlanProject Elements - PAV03A Alligator Pump Station (Zone 5)
• Fronting Protection Structure (Type 5-2)
• Concrete Floodwall Replacement (Type 5-1)
• Sheet Pile Cut-Off Wall Installation
• Levee Embankment Fill
• Levee System Stone Armoring Protection (24” Stone)
• Levee All-Weather Surface Road Replacement (2” HMA Type D)
Fronting Protection Structure (Type 5-2)
Construction Plan
Project Elements - PAV03A Alligator Pump Station (Zone 5)
• Fronting Protection Structure (Type 5-2)
• Concrete Floodwall Replacement (Type 5-1)
• Sheet Pile Cut-Off Wall Installation
• Levee Embankment Fill
• Levee System Stone Armoring Protection (24” Stone)
• Levee All-Weather Surface Road Replacement (2” HMA Type D)
Fronting Protection Structure (Type 5-2) All Weather Surface Road Replacement
Section B1 / CF366
All Weather Surface Road Replacement
Sheet Pile Cut-Off Wall
Construction Plan
Project Elements - PAV03A Alligator Pump Station (Zone 5)
• Fronting Protection Structure (Type 5-2)
• Concrete Floodwall Replacement (Type 5-1)
• Sheet Pile Cut-Off Wall Installation
• Levee Embankment Fill
• Levee System Stone Armoring Protection (24” Stone)
• Levee All-Weather Surface Road Replacement (2” HMA Type D)
Concrete Floodwall (Type 5-1)
Stone Armoring
Alligator Pump Station Improvements
Zone 5
Lakeside Pump Station ImprovementsZone 6
Major Project Elements - PAV03A Contract
• Fronting Protection for 3 Pump Stations (Alligator, Lakeside, and Rhodair) ~ 1,000 ft (Zones 5, 6, and 7)
• Earthen Levee Raise ~ 370 ft. (Various Areas)
• Concrete Floodwall Replacement ~ 950 ft (Zones 5, 6, & 7)
• Sheet Pile Cut-Off Wall Installation (Zones 5, 6, 7 ,& 8)
• Levee System Stone Armoring Protection (Zones 5, 6, 7, & 8)
• Levee All-Weather Surface Road Replacement (Zone 5, 6, & 7)
• FM365 Road Closure Gate Replacement (Zone 8)
• Gate Well Structure and Culvert Replacement (Zone 8)
3 Stage Temporary Cofferdam
Construction Plan
Project Elements - PAV03A Lakeside Pump Station (Zone 6)
• Fronting Protection Structure – Concrete Floodwall (Type 6-1)
• Fronting Protection Structure – Concrete Floodwall (Type 6-2)
• Sheet Pile Cut-Off Wall Installation
• Levee Embankment Fill
• Levee System Stone Armoring Protection (24” Stone)
• Levee All-Weather Surface Road Replacement (2” HMA Type D)
Stone ArmoringStone Armoring
Concrete Floodwall (Type 6-1)
Concrete Floodwall (Type 6-2) All Weather Surface Road Replacement
Construction Plan
Project Elements - PAV03A Lakeside Pump Station (Zone 6)
• Fronting Protection Structure – Concrete Floodwall (Type 6-1)
• Fronting Protection Structure – Concrete Floodwall (Type 6-2)
• Sheet Pile Cut-Off Wall Installation
• Levee Embankment Fill
• Levee System Stone Armoring Protection (24” Stone)
• Levee All-Weather Surface Road Replacement (2” HMA Type D)
All Weather Surface Road Replacement
Stone Armoring
Concrete Floodwall (Type 6-1)
Concrete Floodwall (Type 6-2)
Zone 5
Lakeside Pump Station ImprovementsZone 6
Rhodair Pump Station Improvements
Zone 7
Major Project Elements - PAV03A Contract
• Fronting Protection for 3 Pump Stations (Alligator, Lakeside, and Rhodair) ~ 1,000 ft (Zones 5, 6, and 7)
• Earthen Levee Raise ~ 370 ft. (Various Areas)
• Concrete Floodwall Replacement ~ 950 ft (Zones 5, 6, & 7)
• Sheet Pile Cut-Off Wall Installation (Zones 5, 6, 7 ,& 8)
• Levee System Stone Armoring Protection (Zones 5, 6, 7, & 8)
• Levee All-Weather Surface Road Replacement (Zone 5, 6, & 7)
Rhodair Pumping Station
3 Stage Temporary Cofferdam
Construction Plan
Project Elements - PAV03A Rhodair Pump Station (Zone 7)
• Fronting Protection Structure – Concrete Floodwall (Type 7-1)
• Fronting Protection Structure – Concrete Floodwall (Type 7-2)
• Sheet Pile Cut-Off Wall Installation
• Levee Embankment Fill
• Levee System Stone Armoring Protection (24” Stone)
• Levee All-Weather Surface Road Replacement (2” HMA Type D)
Concrete Floodwall (Type 7-2)
Concrete Floodwall (Type 7-1)
Sheet Pile Cut-Off Wall
Stone Armoring
All Weather Surface Road Replacement
Construction Plan
Project Elements - PAV03A Rhodair Pump Station (Zone 7)
• Fronting Protection Structure – Concrete Floodwall (Type 7-1)
• Fronting Protection Structure – Concrete Floodwall (Type 7-2)
• Sheet Pile Cut-Off Wall Installation
• Levee Embankment Fill
• Levee System Stone Armoring Protection (24” Stone)
• Levee All-Weather Surface Road Replacement (2” HMA Type D)
Stone Armoring
All Weather Surface Road ReplacementConcrete Floodwall (Type 7-1)
Concrete Floodwall (Type 7-2)
Zone 5
Lakeside Pump Station ImprovementsZone 6
Zone 8 Replace FM365 Road Closure Gate
Gate Well Structure & Culvert
Rhodair Pump Station Improvements
Zone 7
Major Project Elements - PAV03A Contract
• Fronting Protection for 3 Pump Stations (Alligator, Lakeside, and Rhodair) ~ 1,000 ft (Zones 5, 6, and 7)
• Earthen Levee Raise ~ 370 ft. (Various Areas)
• Concrete Floodwall Replacement ~ 950 ft (Zones 5, 6, & 7)
• Sheet Pile Cut-Off Wall Installation (Zones 5, 6, 7 ,& 8)
• Levee System Stone Armoring Protection (Zones 5, 6, 7, & 8)
• Levee All-Weather Surface Road Replace (Zone 5, 6, & 7)
NOTE FOR OPTION 2: The Government may exercise this Option by written notice to the Contractor within 365 days after notice to proceed. No additional days will be added to the contract for completion of Option 2
NOTE FOR OPTION 3: The Government may exercise this Option by written notice to the Contractor within 365 days after notice to proceed. No additional days will be added to the contract for completion of Option 3
FM365 Closure Gate
Rhodair Pumping Station
TXDOT Bridge Replacement and Road Raise @ FM365 Levee Crossing
FM365 Closure Gate
Concrete Floodwall Concrete Floodwall
Port Arthur PAV03A Project Overview: Design-Bid-Build Contract
FM365 Road Closure Gate Construction Plan
Bid Option 3
Project Elements - PAV03A FM365 Road Closure Gate (Zone 8)
• Concrete Floodwall and Closure Gates
• Levee Embankment Fill
• Sheet Pile Cut-Off Wall Installation
• Levee System Stone Armoring Protection (24” Stone)
Stone ArmoringStone Armoring Closure Gates
Gate Well and Culvert Construction Plan
Bid Option 2
PAV03A Project Overview Bid Solicitation Schedule Important Specification Provisions Questions/Open Discussion
Port Arthur PAV03A Project: Bid Solicitation Schedule
2 Feb. 2023: Issue Proposal Documents for Bid
16 Feb. 2023: Pre-Proposal Conference and Project Site Visit
25 Mar. 2023: Receive Proposals
27 Mar. 2023: Source Selection Eval. Board Proposal evaluation commences
15 Jun. 2023: Award Construction Contract
The magnitude of construction for this project is between $25M to $100M
PAV03A Project Overview Bid Solicitation Schedule Important Specification Provisions Questions/Open Discussion
Port Arthur PAV03A Project: Bidder Inquiries
Port Arthur PAV03A Project: Bidder Inquiries
Port Arthur PAV03A Project: Bidding Requirements
Port Arthur PAV03A Project: Basis of Award
Port Arthur PAV03A Project: Price Proposal
Port Arthur PAV03A Project: Price Proposal
Port Arthur PAV03A Project: Technical Proposal
Port Arthur PAV03A Project: Past Performance Assessment
Port Arthur PAV03A Project: USACE Past Performance Quest.
Port Arthur PAV03A Project: Small Business Participation
Port Arthur PAV03A Project: Small Business Participation
Port Arthur PAV03A Project: Geotechnical Engineering Report
Port Arthur PAV03A Project: Important Spec. Provisions
Contract Wages are Subject to the Davis-Bacon Act
Questions / Open Discussion https://www.swg.usace.army.mil/S2G/Port Arthur/
NOTE: Nothing Presented today during this Pre-Proposal Conference or discussed during the follow-on Project Site Tour is binding on the Government unless the Contractor(s) provide their inquiry through the Bidder Inquiries Portal (ProjNet) and the Government provides an Official Response.
https://www.swg.usace.army.mil/S2G/Port%20Arthur/
| Sabine Pass to Galveston Bay�(S2G) Port Arthur, Texas�PAV03A Pre-Proposal Conference�Solicitation No. W912HY-23-R-5223�Design-Bid-Build Contract |
| Port Arthur Non-Federal Sponsor – USACE Partner |
| Port Arthur PAV03A Project: Solicitation No. W912HY-23-R-5223 |
| Port Arthur PAV03A Project Pre-Proposal Conference Agenda |
| Port Arthur PAV03A Project Pre-Proposal Conference Agenda |
| The Threat from Hurricane’s and Rising Sea Levels |
| S2G Port Arthur Program Overview |
| Port Arthur PAV03A Project Pre-Proposal Conference Agenda |
| S2G Port Arthur Program Overview |
| Port Arthur PAV03A Project: General Description of the Work |
| Port Arthur PAV03A Project Overview: Bid Schedule |
| Port Arthur PAV03A Project Overview: Bid Schedule |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Bid Schedule |
| Port Arthur PAV03A Project Overview: Bid Schedule |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Overview: Design-Bid-Build Contract |
| Port Arthur PAV03A Project Pre-Proposal Conference Agenda |
| Port Arthur PAV03A Project: Bid Solicitation Schedule |
| Port Arthur PAV03A Project Pre-Proposal Conference Agenda |
| Port Arthur PAV03A Project: Bidder Inquiries |
| Port Arthur PAV03A Project: Bidder Inquiries |
| Port Arthur PAV03A Project: Bidding Requirements |
| Port Arthur PAV03A Project: Bidding Requirements |
| Port Arthur PAV03A Project: Bidding Requirements |
| Port Arthur PAV03A Project: Basis of Award |
| Port Arthur PAV03A Project: Price Proposal |
| Port Arthur PAV03A Project: Price Proposal |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Past Performance Assessment |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: USACE Past Performance Quest. |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Technical Proposal |
| Port Arthur PAV03A Project: Small Business Participation |
| Port Arthur PAV03A Project: Small Business Participation |
| Port Arthur PAV03A Project: Geotechnical Engineering Report |
| Port Arthur PAV03A Project: Important Spec. Provisions |
| Port Arthur PAV03A Project: Important Spec. Provisions |
| Port Arthur PAV03A Project: Important Spec. Provisions |
| Port Arthur PAV03A Project: Important Spec. Provisions |
| Port Arthur PAV03A Project: Important Spec. Provisions |
| Port Arthur PAV03A Project: Important Spec. Provisions |
| Port Arthur PAV03A Project: Important Spec. Provisions |
| Questions / Open Discussion |