C.04.01_Bid Abstract W912HY23B0007 PCO Signed 24 Feb 2023.pdf

PDF 308 KB Posted

Attached to
GALVESTON ENTRANCE CHANNEL AND HOUSTON SHIP CHANNEL BOLIVAR TO REDFISH HOPPER DREDGING, GALVESTON COUNTY, TEXAS
Solicitation number
W912HY23B0007
Issued by

About this file

This document is an abstract of offers for a federal solicitation to provide hopper dredging services for the Galveston Entrance Channel and Houston Ship Channel between Bolivar and Redfish in Galveston County, Texas. The U.S. Army Corps of Engineers Galveston District issued the solicitation on January 25, 2023 to obtain dredging and related services on an unrestricted basis. Three offers were received on February 24, 2023 for dredging and placement of material, sea turtle protection monitoring, and other services. The apparent low offer of $15,866,810 was submitted by Great Lakes Dredge & Dock Company, LLC at 6.14% above the independent government estimate. Manson Construction Co. offered $26,122,000 and Weeks Marine, Inc. bid $9,806,000 for the base work and option years.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT

PRICE TOTAL

1 JB $2,526,000.00 $2,526,000.00

564,000 CY $5.18 $2,921,520.00

237,000 CY $7.00 $1,659,000.00

174,000 CY $9.36 $1,628,640.00

627,000 CY $10.95 $6,865,650.00

1 JB $135,000.00 $135,000.00

1 JB $46,000.00 $46,000.00

1 JB 85,000.00 $85,000.00

$15,866,810.00

259,000 CY $4.43 $1,147,370.00

1 JB $18,000.00 $18,000.00

$1,165,370.00

$17,032,180.00

335,000 CY $9.85 $3,299,750.00

1 JB $27,000.00 $27,000.00

$3,326,750.00

$20,358,930.00

555,000 CY $9.09 $5,044,950.00

1 JB $36,000.00 $36,000.00

$5,080,950.00

$25,439,880.00

1 JB $1,881,000.00 $1,881,000.00

Sea Turtle Protection, Section 25

SCHEDULE NO. 1ITEM

TOTAL SCHEDULE NO.1 & OPTION NO.1

Dredging- Extended GEC, Section 19-22

OPTION NO. 1

Dredging- Inner/Outer Bar Channel and Bolivar Roads Channel, Section 5-7

TOTAL OPTION NO. 2

Sea Turtle Protection, Section 19-22

ABSTRACT OF OFFERS Page 1 of 4

Solicitation No.: W912HY22B0007 Date Issued: 25 Jan 2023 Date Opened: 24 Feb 2023 Issuing Office: USACE-Galveston Project Title: FY 23 Galveston Entrance Channel and HSC Bolivar to Redfish Hopper Dredging Galveston Harbor and Houston Ship Channel, Galveston, Texas, Unrestricted Procurement

Number of Amendments Issued: 0003 Government Estimate (Without Profit)

QUANTITY

TOTAL SCHEDULE NO. 1

TOTAL OPTION NO. 1

TOTAL SCHEDULE NO.1 & OPTION NO.1 & 2

OPTION NO. 3

Dredging TCSC, Section 23-24

0012 Sea Turtle Protection, Section 23-24

Dredging -GHC Only , Section 25

Dredging- HSC, Bolivar Roads to Redfish reef, Section 8-

ODMDS No. 1 Monitor Surveys

Sea Turtle Protection Section No. 8-18

NO. DESCRIPTION

Dredging- HSC, Bolivar Roads to Redfish reef, Section 14-18

0002 Dredging -GEC, Section 1-4 Mobilization and Demobilization

OPTION NO. 2

0007 Sea Turtle Protection Section No. 1-7

TOTAL OPTION NO. 3

TOTAL SCHEDULE NO.1 & OPTION NO. 1 & 2

OPTION NO. 4

Pipeline Management- Beach Placement Galveston

237,000 CY $7.19 $1,704,030.00

174,000 CY $8.15 $1,418,100.00

168,000 CY $8.94 $1,501,920.00

1 JB $43,000.00 $43,000.00

1 JB $196,000.00 $196,000.00

$6,744,050.00

$32,183,930.00

1 JB $16,000.00 $16,000.00

30 DAY $4,350.00 $130,500.00

$146,500.00

$32,330,430.00

1 JB $16,000.00 $16,000.00

30 DAY $4,350.00 $130,500.00

$146,500.00

$32,476,930.00

Sea Turtle Protection, Section 25

I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT ALL OFFERS RECEIVED IN RESPONSE TO THIS

SOLICITATION.

0022 Sea Turtle Protection, Section 23-24

Endangered Species Monitoring- Beach Placement Galveston

Depth of Closure Survey

* The apparent low bidder, Great Lakes Dredge & Dock Company, LLC, Inc, is 6.14% above the Government's Estimate.

Placement of Dredge Material at Galveston Island Beach N0.8-13 at Galveston Island Beach

Placement of Dredge Material at Galveston Island Beach N0.14-15 at Galveston Island Beach

OPTION NO. 5

Jo Ann McCue

CONTRACTING OFFICER

TOTAL SCHEDULE NO.1 & OPTION NO.1,2,3,4, &

Dredging TCSC, Section 23-24

TOTAL OPTION NO. 5

TOTAL OPTION NO. 6

TOTAL OPTION NO. 4

TOTAL SCHEDULE NO.1 & OPTION NO. 1,2,3,4,5,

& 6

Placement of Dredge Material at Galveston Island Beach N0.5-7 at Galveston Island Beach

OPTION NO. 6

Dredging -GHC Only , Section 25

TOTAL SCHEDULE NO.1 & OPTION NO.1,2,3 &4

1 JB $2,200,000.00 $2,200,000.00

564,000 CY $4.20 $2,368,800.00

237,000 CY $6.15 $1,457,550.00

174,000 CY $11.25 $1,957,500.00

627,000 CY $10.95 $6,865,650.00

1 JB $26,500.00 $26,500.00

1 JB $20,400.00 $20,400.00

1 JB 43,000.00 $43,000.00

$14,939,400.00

259,000 CY $4.00 $1,036,000.00

1 JB $7,700.00 $7,700.00

$1,043,700.00

$15,983,100.00

335,000 CY $11.95 $4,003,250.00

1 JB $23,200.00 $23,200.00

$4,026,450.00

$20,009,550.00

555,000 CY $7.00 $3,885,000.00

1 JB $22,800.00 $22,800.00

$3,907,800.00

$23,917,350.00

1 JB $3,275,000.00 $3,275,000.00

Project Title: FY 23 Galveston Entrance Channel and HSC Bolivar to Redfish Hopper Dredging Galveston Harbor and Houston Ship Channel, Galveston, Texas, Unrestricted Procurement

Offeror 1: Great Lakes Dredge & Dock Company, LLC Houston, TX 77024

Solicitation No.: W912HY22B0007 Date Issued: 25 Jan 2023 Date Opened: 24 Feb 2023 Issuing Office: USACE-Galveston

ABSTRACT OF OFFERS (CONT'D) Page 2 of 4

Business Size: Large

NO. DESCRIPTION QUANTITY

0001 Mobilization and Demobilization

ITEM SCHEDULE NO. 1

0002 Dredging -GEC, Section 1-4

Dredging- Inner/Outer Bar Channel and Bolivar Roads Channel, Section 5-7

Dredging- HSC, Bolivar Roads to Redfish reef, Section 8-

Dredging- HSC, Bolivar Roads to Redfish reef, Section 14-18

0006 ODMDS No. 1 Monitor Surveys 0007 Sea Turtle Protection Section No. 1-7

0008 Sea Turtle Protection Section No. 8-18

TOTAL SCHEDULE NO. 1

OPTION NO. 1

Dredging- Extended GEC, Section 19-22

Sea Turtle Protection, Section 19-22

TOTAL OPTION NO. 1

OPTION NO. 2

TOTAL SCHEDULE NO.1 & OPTION NO.1

Dredging TCSC, Section 23-24

0012 Sea Turtle Protection, Section 23-24

TOTAL OPTION NO. 2

OPTION NO. 3

TOTAL SCHEDULE NO.1 & OPTION NO.1 & 2

Dredging -GHC Only , Section 25

Sea Turtle Protection, Section 25

TOTAL OPTION NO. 3

OPTION NO. 4

TOTAL SCHEDULE NO.1 & OPTION NO. 1 & 2

Pipeline Management- Beach Placement Galveston

237,000 CY $9.55 $2,263,350.00

174,000 CY $13.70 $2,383,800.00

168,000 CY $13.85 $2,326,800.00

1 JB $83,000.00 $83,000.00

1 JB $5,100.00 $5,100.00

$10,337,050.00

$34,254,400.00

1 JB $28,800.00 $28,800.00

30 DAY $4,800.00 $144,000.00

$172,800.00

$34,427,200.00

1 JB $28,800.00 $28,800.00

30 DAY $4,800.00 $144,000.00

$172,800.00

$34,600,000.00

Endangered Species Monitoring- Beach Placement Galveston Depth of Closure Survey

TOTAL SCHEDULE NO.1 & OPTION NO. 1,2,3,4,5,

& 6

Dredging TCSC, Section 23-24

0022 Sea Turtle Protection, Section 23-24

Placement of Dredge Material at Galveston Island Beach N0.5-7 at Galveston Island Beach

Placement of Dredge Material at Galveston Island Beach N0.8-13 at Galveston Island Beach

Dredging- HSC, Bolivar Roads to Redfish reef, Section 14-18

TOTAL OPTION NO. 4

TOTAL OPTION NO. 6

OPTION NO. 6

Dredging -GHC Only , Section 25

Sea Turtle Protection, Section 25

TOTAL SCHEDULE NO.1 & OPTION NO.1,2,3 &4

OPTION NO. 5

TOTAL OPTION NO. 5

TOTAL SCHEDULE NO.1 & OPTION NO.1,2,3,4, &

1 JB $5,650,000.00 $5,650,000.00

564,000 CY $4.50 $2,538,000.00

237,000 CY $10.50 $2,488,500.00

174,000 CY $9.50 $1,653,000.00

627,000 CY $9.00 $5,643,000.00

1 JB $50,000.00 $50,000.00

1 JB $100,000.00 $100,000.00

1 JB 100,000.00 $100,000.00

$18,222,500.00

259,000 CY $5.00 $1,295,000.00

1 JB $25,000.00 $25,000.00

$1,320,000.00

$19,542,500.00

335,000 CY $4.50 $1,507,500.00

1 JB $15,000.00 $15,000.00

$1,522,500.00

$21,065,000.00

555,000 CY $4.50 $2,497,500.00

1 JB $15,000.00 $15,000.00

$2,512,500.00

$23,577,500.00

1 JB $1,950,000.00 $1,950,000.00

Pipeline Management- Beach Placement Galveston

Dredging- HSC, Bolivar Roads to Redfish reef, Section 8-

Dredging- HSC, Bolivar Roads to Redfish reef, Section 14-18

0006 ODMDS No. 1 Monitor Surveys

ITEM SCHEDULE NO. 1

NO. DESCRIPTION

ABSTRACT OF OFFERS (CONT'D) Page 3 of 4

Solicitation No.: W912HY22B0007 Date Issued: 25 Jan 2023 Date Opened: 24 Feb 2023 Issuing Office: USACE-Galveston Project Title: FY 23 Galveston Entrance Channel and HSC Bolivar to Redfish Hopper Dredging Galveston Harbor and Houston Ship Channel, Galveston, Texas, Unrestricted Procurement

Offeror 2: Manson Construction Co.

Business Size: Large

QUANTITY

0001 Mobilization and Demobilization

0007 Sea Turtle Protection Section No. 1-7

Sea Turtle Protection, Section 19-22

0008 Sea Turtle Protection Section No. 8-18

TOTAL SCHEDULE NO. 1

OPTION NO. 1

Dredging- Extended GEC, Section 19-22

0002 Dredging -GEC, Section 1-4

Dredging- Inner/Outer Bar Channel and Bolivar Roads Channel, Section 5-7

TOTAL SCHEDULE NO.1 & OPTION NO.1 & 2

0012 Sea Turtle Protection, Section 23-24

TOTAL OPTION NO. 2

TOTAL OPTION NO. 1

TOTAL SCHEDULE NO.1 & OPTION NO.1

OPTION NO. 2

Dredging TCSC, Section 23-24

OPTION NO. 3

Dredging -GHC Only , Section 25

Sea Turtle Protection, Section 25

TOTAL OPTION NO. 3

TOTAL SCHEDULE NO.1 & OPTION NO. 1 & 2

OPTION NO. 4

237,000 CY $19.00 $4,503,000.00

174,000 CY $30.00 $5,220,000.00

168,000 Cy $32.00 $5,376,000.00

1 JB $400,000.00 $400,000.00

1 JB $25,000.00 $25,000.00

$17,474,000.00

$41,051,500.00

1 JB $35,000.00 $35,000.00

30 DAY $5,000.00 $150,000.00

$185,000.00

$41,236,500.00

1 JB $35,000.00 $35,000.00

30 DAY $5,000.00 $150,000.00

$185,000.00

$41,421,500.00

Sea Turtle Protection, Section 25

TOTAL OPTION NO. 6

Dredging- HSC, Bolivar Roads to Redfish reef, Section 14-18

TOTAL SCHEDULE NO.1 & OPTION NO.1,2,3 &4

Depth of Closure Survey

TOTAL SCHEDULE NO.1 & OPTION NO. 1,2,3,4,5,

& 6

TOTAL OPTION NO. 5

TOTAL SCHEDULE NO.1 & OPTION NO.1,2,3,4, &

Dredging -GHC Only , Section 25

OPTION NO. 5

Dredging TCSC, Section 23-24

0022 Sea Turtle Protection, Section 23-24

OPTION NO. 6

TOTAL OPTION NO. 4

Dredging- HSC, Bolivar Roads to Redfish reef, Section 8-

Placement of Dredge Material at Galveston Island Beach N0.5-7 at Galveston Island Beach

Endangered Species Monitoring- Beach Placement Galveston0019

1 JB $4,950,000.00 $4,950,000.00

564,000 CY $10.00 $5,640,000.00

237,000 CY $13.00 $3,081,000.00

174,000 CY $16.50 $2,871,000.00

627,000 CY $15.00 $9,405,000.00

1 JB $75,000.00 $75,000.00

1 JB $50,000.00 $50,000.00

1 JB 50,000.00 $50,000.00

$26,122,000.00

259,000 CY $9.00 $2,331,000.00

1 JB $7,500.00 $7,500.00

$2,338,500.00

$28,460,500.00

335,000 CY $10.00 $3,350,000.00

1 JB $15,000.00 $15,000.00

$3,365,000.00

$31,825,500.00

555,000 CY $10.00 $5,550,000.00

1 JB $25,000.00 $25,000.00

$5,575,000.00

$37,400,500.00

1 JB $1,575,000.00 $1,575,000.00

TOTAL SCHEDULE NO.1 & OPTION NO. 1 & 2

Sea Turtle Protection, Section 25

OPTION NO. 3

Pipeline Management- Beach Placement Galveston

TOTAL OPTION NO. 3

ABSTRACT OF OFFERS (CONT'D) Page 4 of 4

0008 Sea Turtle Protection Section No. 8-18

TOTAL SCHEDULE NO. 1

OPTION NO. 1

Dredging- Extended GEC, Section 19-22

0002 Dredging -GEC, Section 1-4

Dredging- Inner/Outer Bar Channel and Bolivar Roads Channel, Section 5-7

Dredging- HSC, Bolivar Roads to Redfish reef, Section 8-

Dredging- HSC, Bolivar Roads to Redfish reef, Section 14-18

Sea Turtle Protection Section No. 1-7

TOTAL OPTION NO. 1

Dredging -GHC Only , Section 25

Sea Turtle Protection, Section 19-22

OPTION NO. 2

Dredging TCSC, Section 23-24

TOTAL SCHEDULE NO.1 & OPTION NO.1 & 2

TOTAL OPTION NO. 2

0012 Sea Turtle Protection, Section 23-24

TOTAL SCHEDULE NO.1 & OPTION NO.1

OPTION NO. 4

Solicitation No.: W912HY22B0007 Date Issued: 25 Jan 2023 Date Opened: 24 Feb 2023 Issuing Office: USACE-Galveston Project Title: FY 23 Galveston Entrance Channel and HSC Bolivar to Redfish Hopper Dredging Galveston Harbor and Houston Ship Channel, Galveston, Texas, Unrestricted Procurement

Offeror 3: Weeks Marine, Inc.

Business Size: Large

QUANTITY

0006 ODMDS No. 1 Monitor Surveys

ITEM SCHEDULE NO. 1

NO. DESCRIPTION

0001 Mobilization and Demobilization

237,000 CY $15.00 $3,555,000.00

174,000 CY $15.00 $2,610,000.00

168,000 CY $12.00 $2,016,000.00

1 JB $50,000.00 $50,000.00

1 JB $25,000.00 $25,000.00

*** $9,806,000.00

$47,206,500.00

1 JB $15,000.00 $15,000.00

30 DAY $5,500.00 $165,000.00

$180,000.00

$47,386,500.00

1 JB $15,000.00 $15,000.00

30 DAY $5,500.00 $165,000.00

$180,000.00

$47,566,500.00

Dredging- HSC, Bolivar Roads to Redfish reef, Section 8-

Dredging- HSC, Bolivar Roads to Redfish reef, Section 14-18

TOTAL OPTION NO. 4

OPTION NO. 5

TOTAL SCHEDULE NO.1 & OPTION NO.1,2,3 &4

Placement of Dredge Material at Galveston Island Beach N0.5-7 at Galveston Island Beach

Endangered Species Monitoring- Beach Placement Galveston Depth of Closure Survey

Dredging TCSC, Section 23-24

0022 Sea Turtle Protection, Section 23-24

TOTAL OPTION NO. 5

OPTION NO. 6

TOTAL SCHEDULE NO.1 & OPTION NO.1,2,3,4, &

Dredging -GHC Only , Section 25

Sea Turtle Protection, Section 25

TOTAL OPTION NO. 6

TOTAL SCHEDULE NO.1 & OPTION NO. 1,2,3,4,5,

& 6

*** corrected math error for option #4 which reflects in option #5, option #6 and over all total.

2023-02-24T18:07:18-0600
MCCUE.JO.ANN.1264566130

File details come from the government source that posted it. Updated .