This document is an amendment to a solicitation for pipeline dredging services along the Gulf Intracoastal Waterway in Texas. The amendment reschedules the bid opening to September 12, 2022 at 2:00 PM CDT and provides a revised bid schedule with seven options. The base requirement is for dredging approximately 1.4 million cubic yards along Sections 1-14. There are six single-year options for additional dredging work totaling approximately 1 million cubic yards. Pricing is to be provided per cubic yard dredged. The solicitation was issued by the U.S. Army Corps of Engineers Galveston District for dredging in Nueces, Kleberg, Kenedy, Willacy, and Cameron Counties in Texas. Completion times range from 15 to 35 additional calendar days for the optional work. Evaluation will include pricing for all options.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

BID OPENING WILL BE RESCHEDULED FOR MONDAY12 SEPT, 2022 AT 2:00 P.M. CDT

See Continuation Page

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HY22B0018

X 9B. DATED (SEE ITEM 11)

08-Aug-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

No. 0004

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-Sep-2022

CODE

US ARMY CORPS OF ENGINEERS

2000 FORT POINT ROAD

P.O. BOX 1229

GALVESTON TX 77553-1229

W912HY 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HY22B0018

A0004-2

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

1. The specifications for Solicitation No. W912HY22B0018, UNRESTRICTED PROCUREMENT

FOR FY 22 USACE, GALVESTON DISTRICT, GULF INTRACOASTAL WATERWAY,

TEXAS, CORPUS CHRISTI TO PORT ISABEL, PIPELINE DREDGING IN NUECES,

KLEBERG, KENEDY, WILLACY, AND CAMERON COUNTIES, TEXAS are hereby amended as follows:

*BID OPENING WILL BE RESCHEDULED FOR MONDAY 12 SEPT, 2022 AT 2:00 P.M. CDT

a) Specifications.

(1) DOCUMENT 00 11 00.00 45 - BID SCHEDULE - The enclosed Document 00 11 00.00 45 entitled BID SCHEDULE supersedes that issued with this Solicitation.

2. This amendment shall be attached to and become a part of the solicitation.

1 Encl:

1. DOCUMENT 00 11 00.00 45 - BID SCHEDULE

SWG FILE NO.: IWW 1175-0281 SOLICITATION: W912HY22B0018

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 11 00.00 45

BID SCHEDULE Amendment No. 0004

PART 1 GENERAL

1.1 BID SCHEDULE

1.1.1 Schedule No. 1

1.1.2 Option No. 1

1.1.3 Option No. 2 AM#4

1.1.4 Option No. 3

1.1.5 Option No. 4

1.1.6 Option No. 5

1.1.7 Option No. 6

1.2 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

-- End of Section Table of Contents --

DOCUMENT 00 11 00.00 45 Page 1

TO ACCOMPANY AMENDMENT NO. 0004 TO SOLICITATION: W912HY22B0018

THIS PAGE INTENTIONALLY LEFT BLANK

DOCUMENT 00 11 00.00 45 Page 2

00 11 00.00 45

BID SCHEDULE

Amendment No. 0004

PART 1 GENERAL

1.1 BID SCHEDULE

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.1 Schedule No. 1

Item No. Description Estimated Quantity

Unit Unit Price Estimated Amount

SCHEDULE NO. 1

0001 Mobilization and Demobilization 1 JOB SUM $___________

0002 Dredging GIWW Sections 1-14 1,411,000 C.Y. $_________ $___________

TOTAL SCHEDULE NO. 1 $___________

NOTE: Completion time stated in SECTION 00 73 00.01 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD is for Schedule No. 1 work.

DOCUMENT 00 11 00.00 45 Page 3

BID SCHEDULE (CONT'D)

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.2 Option No. 1

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 1

0003 Dredging Channel to Harlingen Sections 15-18

173,000 C.Y. $_________ $___________

TOTAL OPTION NO. 1 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NO. 1 $___________

NOTE FOR OPTI ON NO. 1: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or pr i or t o compl et i on of al l aut hor i zed wor k. An addi t i onal t i me of 29 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.

DOCUMENT 00 11 00.00 45 Page 4

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.3 Option No. 2 AM#4

Item No. Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 2

0004 Port Isabel Small Boat Harbor Section 19

20,000 C.Y. $_________ $___________

TOTAL OPTION NO. 2 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1 AND 2 $___________

NOTE FOR OPTI ON NO. 2: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or pr i or t o compl et i on of al l aut hor i zed wor k. An addi t i onal t i me of 15 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.

DOCUMENT 00 11 00.00 45 Page 5

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.4 Option No. 3

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 3

0005 Dredging Channel to Harlingen Docks (Section 20 Valero/Cemex/Simplot) (Section 21 Helena) (Section 22 Sugar) (Section 23 East Dock)

56,000 C.Y. $_________ $___________

TOTAL OPTION NO. 3 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1, 2, AND 3 $___________

NOTE FOR OPTI ON NO. 3: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or pr i or t o compl et i on of al l aut hor i zed wor k. An addi t i onal t i me of 15 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.

DOCUMENT 00 11 00.00 45 Page 6

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.5 Option No. 4

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 4

0006 Placement Area No.

18 Clearing and Grubbing

1 JOB SUM $___________

TOTAL OPTION NO.4 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1, 2, 3, AND 4 $___________

NOTE FOR OPTI ON NO. 4: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or pr i or t o compl et i on of al l aut hor i zed wor k. An addi t i onal t i me of 30 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.

DOCUMENT 00 11 00.00 45 Page 7

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.6 Option No. 5

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 5

0007 Placement Area No.

22 Clearing and Grubbing

1 JOB SUM $___________

TOTAL OPTION NO. 5 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1, 2, 3, 4, AND 5 $___________

NOTE FOR OPTI ON NO. 5: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or pr i or t o compl et i on of al l aut hor i zed wor k. An addi t i onal t i me of 22 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.

DOCUMENT 00 11 00.00 45 Page 8

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.7 Option No. 6

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 6

0008 Dredging Channel to Harlingen Sections 24-29

268,000 C.Y. $_________ $___________

TOTAL OPTION NO. 6 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1, 2, 3, 4, 5, AND 6 $___________

NOTE FOR OPTI ON NO. 6: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or pr i or t o compl et i on of al l aut hor i zed wor k. An addi t i onal t i me of 35 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.

DOCUMENT 00 11 00.00 45 Page 9

(TO BE ATTACHED TO STANDARD FORM 1442)

1.2 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

-- End of Document --

DOCUMENT 00 11 00.00 45 Page 10

B.08.03_W912HY22B0018 Amendment 0004 09072022
Amend 0004 page-2
00 11 00.00 45(just green)
00 11 00.00 45 - BID SCHEDULE Amendment No. 0004
00 11 00.00 45 - BID SCHEDULE
PART 1 GENERAL
1.1 BID SCHEDULE
1.1.1 Schedule No. 1
1.1.2 Option No. 1
1.1.3 Option No. 2 AM#4
1.1.4 Option No. 3
1.1.5 Option No. 4
1.1.6 Option No. 5
1.1.7 Option No. 6

1.2 EVALUATION OF OPTIONS July 1990 FAR 52.217-5

File details come from the government source that posted it. Updated .