C.04.01 Bid Abtract W912HY21B0010_5 Options_20210427-PCO signed.pdf

PDF 289 KB Posted

Attached to
CEDAR BAYOU, TX CONSTRUCTION
Solicitation number
W912HY21B0010
Issued by

About this file

This document summarizes bids received in response to Solicitation Number W912HY21B0010 from the Department of the Army Corps of Engineers Engineering District Galveston for construction services related to Cedar Bayou, Texas.

The apparent low bidder was Rigid Constructors, LLC at $26,276,454.30, which represents a 22.76% savings versus the government estimate. The solicitation sought bids for mobilization, pre-dredging surveys, demolition of existing structures, construction of new structures, clearing and grubbing, stripping, turfing, dredging, excavation, riprap installation, and other services across five option periods. Maloney Odin Joint Venture bid $39,389,262.00 while Orion Construction, L.P. bid $59,483,299.69 and Standard Constructors, Inc. bid $59,729,131.00. The contract was set aside for small businesses. Award is anticipated based on best value considering price and other factors.

View the file

Other files

File Type Posted
Bid Abstract W912HY21B0010_Cedar Bayou Channel Improvement-Corrected-17-May-2021-PCO signed.pdf PDF
Bid Abtract W912HY21B0010_Cedar Bayou Improvements-Corrected-PCO signed-29-Apr-2021.pdf PDF
W912HY21B0010-Amendment-0002.pdf PDF
PA-1 LiDAR EG.txt TXT text file
Cedar Bayou Channel - North-1.txt TXT text file
Cedar Bayou Channel - South-1.txt TXT text file
Devils Elbow LiDAR 2018 - 2.txt TXT text file
PA-2 LiDAR EG.txt TXT text file
Ijams Lake 8-2020.txt TXT text file
Cedar Byaou Channel - South-2.txt TXT text file
Cedar Bayou Channel - North-2.txt TXT text file
Devils Elbow LiDAR 2018 - 4.txt TXT text file
W912HY21B0010 Amendment 1.pdf PDF
W912HY21B0010 - PLANS.pdf PDF
W912HY21B0010 - SPECS.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT

PRICE TOTAL

1 JB SUM $2,139,420.00

1 JB SUM $96,273.00

1 JB SUM $148,587.00

1 JB SUM $395,348.00

1 JB SUM $395,348.00

1 JB SUM $296,380.00

1 JB SUM $451,018.00

1 JB SUM $451,018.00

1 JB SUM $133,723.00

1 JB SUM $317,652.00

1 JB SUM $145,861.00

1 JB SUM $59,040.00

1 JB SUM $160,504.00

1 JB SUM $160,504.00

1 JB SUM $18,551.00

1 JB SUM $10,285.00

1 JB SUM $230,151.00

1 JB SUM $24,399.00

1 JB SUM $24,399.00

1 JB SUM $245,019.00

1 JB SUM $245,019.00

80 LF $54.85 $4,388.00

80 LF $54.85 $4,388.00

260,000 CY $11.63 $3,023,800.00

205,000 CY $11.78 $2,414,900.00

48,500 CY $8.30 $402,550.00

115,000 CY $5.65 $649,750.00

8,500 SF $12.82 $108,970.00

1,200 SY $9.56 $11,472.00

729,514 CY $7.36 $5,369,223.04

236,000 CY $5.34 $1,260,240.00

117 TON $109.38 $12,797.46

200 TON $109.38 $21,876.00

160 TON $109.38 $17,500.80

80 TON $104.50 $8,360.00

48,000 TON $109.38 $5,250,240.00

15,000 TON $104.50 $1,567,500.00

$26,276,454.30

4,612 CY $5.15 $23,751.80

$23,751.80

1,938 CY $8.14 $15,775.32

$15,775.32

1,914 CY $7.25 $13,876.50

$13,876.50

2,210 CY $7.48 $16,530.80

$16,530.80

1 JB SUM $60,490.00

$60,490.00

$26,406,878.72

Semi-Compacted Dike Ijams Lake

Uncompacted Berm Ijams Lake

Articulating Concrete Block

Geotextile

Pipeline Dredging Sections 1-5

Riprap PA-2

Riprap Ijams Lake

Blanket Stone Ijams Lake Dike

Riprap Devil's Elbow Cutoff

TOTAL OPTION NO. 4

TOTAL OPTION NO. 5

Stripping PA-1

Stripping PA-2

Stripping Devil's Elbow

Turfing PA-1

Turfing PA-2

Turfing Ijams Lake

Turfing at Devil's Elbow Cut

Mechanical Excavation

Riprap PA-1

Ijams Lake Site Management

Soil Laboratory Testing PA-1

Soil Laboratory Testing PA-2

Site Management PA-1

Site Management PA-2

Soil Boring PA-1

Soil Boring PA-2

Semi-Compacted Containment Dike Raise PA-1

Semi-Compacted Containment Dike Raise PA-2

OPTION NO. 2

OPTION NO. 5

TOTAL OPTION NO. 2

0042 Ijams Lake Breaches

Pipeline Dredging Section 5

TOTAL OPTION NO. 3

OPTION NO. 3

DESCRIPTION QUANTITY

SCHEDULE NO. 1ITEM

0004 New Drop-Outlet Structure PA1

Clearing and Grubbing PA-2

Clearing and Grubbing Devil's Elbow

New Drop-Outlet Structure PA-2

Pipeline Management

Clearing and Grubbing PA-1

ABSTRACT OF OFFERS Page 1 of 5

Solicitation No.: W912HY21B0010 Date Issued: 10 Mar 2021 Date Opened: 27 Apr 2021 Issuing Office: USAED-Galveston Project Title: Unrestricted Procurement for Cedar Bayou Navigation Channel, Chambers and Harris Counties, Texas, Pipeline Dredging

TOTAL OPTION NO. 1

0001 Mobilization and Demobilization

Pre-Dredging Hazard Survey

Demolition of Existing Drop-Outlet Structure PA-1

Blanket Stone Devil's Elbow Cutoff

Number of Amendments Issued: 0001 and 0002

Government Estimate (Without Profit)

NO.

* The apparent low bidder, Rigid Constructors, LLC is 22.76 % below the Government's Estimate.

I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.

ALDRICH NICHOLS

CONTRACTING OFFICER

TOTAL SCHEDULE NO. 1 & OPTION NOS. 1

THRU 5

Pipeline Dredging Section 3

0039 Pipeline Dredging Section 4

Pipeline Dredging Section 5

OPTION NO. 1

TOTAL SCHEDULE NO. 1

OPTION NO. 4

1 JB SUM $1,340,000.00

1 JB SUM $20,000.00

1 JB SUM $60,000.00

1 JB SUM $380,000.00

1 JB SUM $380,000.00

1 JB SUM $364,750.00

1 JB SUM $345,000.00

1 JB SUM $360,000.00

1 JB SUM $150,000.00

1 JB SUM $147,900.00

1 JB SUM $154,900.00

1 JB SUM $64,600.00

1 JB SUM $40,000.00

1 JB SUM $40,000.00

1 JB SUM $40,000.00

1 JB SUM $20,000.00

1 JB SUM $120,000.00

1 JB SUM $15,000.00

1 JB SUM $15,000.00

1 JB SUM $35,000.00

1 JB SUM $35,000.00

80 LF $200.00 $16,000.00

80 LF $200.00 $16,000.00

260,000 CY $7.50 $1,950,000.00

205,000 CY $5.50 $1,127,500.00

48,500 CY $4.50 $218,250.00

115,000 CY $3.00 $345,000.00

8,500 SF $6.00 $51,000.00

1,200 SY $5.00 $6,000.00

729,514 CY $7.00 $5,106,598.00

236,000 CY $13.78 $3,252,080.00

117 TON $65.00 $7,605.00

200 TON $65.00 $13,000.00

160 TON $65.00 $10,400.00

80 TON $60.00 $4,800.00

48,000 TON $65.00 $3,120,000.00

15,000 TON $60.00 $900,000.00

$20,271,383.00

4,612 CY $7.00 $32,284.00

$32,284.00

1,938 CY $7.00 $13,566.00

$13,566.00

1,914 CY $7.00 $13,398.00

$13,398.00

2,210 CY $7.00 $15,470.00

$15,470.00

1 JB SUM $50,000.00

$50,000.00

$20,396,101.00

Riprap Ijams Lake

Blanket Stone Ijams Lake Dike

0015 Turfing Ijams Lake

Clearing and Grubbing PA-2

Pre-Dredging Hazard Survey

0007 Clearing and Grubbing PA-1 0006 Pipeline Management

Semi-Compacted Containment Dike Raise PA-1

TOTAL OPTION NO. 1

Riprap Devil's Elbow Cutoff

Blanket Stone Devil's Elbow Cutoff

Articulating Concrete Block

OPTION NO. 1

OPTION NO. 5

TOTAL OPTION NO. 4

OPTION NO. 4

0040 Pipeline Dredging Section 5

TOTAL OPTION NO. 3

Pipeline Dredging Section 5

Mechanical Excavation

TOTAL SCHEDULE NO. 1

Riprap PA-1

OPTION NO. 2

0039 Pipeline Dredging Section 4

TOTAL OPTION NO. 2

OPTION NO. 3

Demolition of Existing Drop-Outlet Structure PA-1

Site Management PA-2

NO.

0012 Stripping Devil's Elbow

Semi-Compacted Dike Ijams Lake

0030 Pipeline Dredging Sections 1-5

Uncompacted Berm Ijams Lake

Soil Boring PA-2

Clearing and Grubbing Devil's Elbow

ABSTRACT OF OFFERS (CONT'D) Page 2 of 5

Offeror: Rigid Constructors, LLC Opelouses, LA Business Size:

Solicitation No.: W912HY21B0010 Date Issued: 10 Mar 2021 Date Opened: 27 Apr 2021

New Drop-Outlet Structure PA1

New Drop-Outlet Structure PA-2

Project Title: Unrestricted Procurement for Cedar Bayou Navigation Channel, Chambers and Harris Counties, Texas, Pipeline Dredging Issuing Office: USAED-Galveston

QUANTITY

Mobilization and Demobilization

DESCRIPTION

ITEM SCHEDULE NO. 1

0022 Soil Boring PA-1

0029 Geotextile

TOTAL OPTION NO. 5

Semi-Compacted Containment Dike Raise PA-2

Pipeline Dredging Section 3

TOTAL SCHEDULE NO. 1 & OPTION NOS. 1

THRU 5

Riprap PA-2

Ijams Lake Breaches

0018 Soil Laboratory Testing PA-1

Stripping PA-1

Stripping PA-2

0017 Ijams Lake Site Management

Turfing at Devil's Elbow Cut

Turfing PA-2 0013 Turfing PA-1

0019 Soil Laboratory Testing PA-2

0020 Site Management PA-1

Small Business

"Apparent Low Bidder"

M3CTXAAN

Highlight

M3CTXAAN

Highlight

M3CTXAAN

Highlight

M3CTXAAN

Highlight

1 JB SUM $2,650,000.00

1 JB SUM $185,000.00

1 JB SUM $60,000.00

1 JB SUM $950,000.00

1 JB SUM $950,000.00

1 JB SUM $100,000.00

1 JB SUM $600,000.00

1 JB SUM $535,000.00

1 JB SUM $150,000.00

1 JB SUM $600,000.00

1 JB SUM $535,000.00

1 JB SUM $150,000.00

1 JB SUM $25,000.00

1 JB SUM $25,000.00

1 JB SUM $25,000.00

1 JB SUM $5,000.00

1 JB SUM $250,000.00

1 JB SUM $5,500.00

1 JB SUM $5,500.00

1 JB SUM $150,000.00

1 JB SUM $150,000.00

80 LF $180.00 $14,400.00

80 LF $180.00 $14,400.00

260,000 CY $5.50 $1,430,000.00

205,000 CY $5.50 $1,127,500.00

48,500 CY $5.50 $266,750.00

115,000 CY $6.50 $747,500.00

8,500 SF $12.00 $102,000.00

1,200 SY $2.00 $2,400.00

729,514 CY $15.00 $10,942,710.00

236,000 CY $13.40 $3,162,400.00

117 TON $300.00 $35,100.00

200 TON $300.00 $60,000.00

160 TON $300.00 $48,000.00

80 TON $200.00 $16,000.00

48,000 TON $130.00 $6,240,000.00

15,000 TON $90.00 $1,350,000.00

$33,665,160.00

4,612 CY $15.00 $69,180.00

$69,180.00

1,938 CY $15.00 $29,070.00

$29,070.00

1,914 CY $15.00 $28,710.00

$28,710.00

2,210 CY $15.00 $33,150.00

$33,150.00

1 JB SUM $30,000.00

$30,000.00

$33,855,270.00

TOTAL OPTION NO. 2

OPTION NO. 1

Pipeline Dredging Section 3

TOTAL OPTION NO. 1

OPTION NO. 2

0039 Pipeline Dredging Section 4

0034 Riprap Ijams Lake

0035 Blanket Stone Ijams Lake Dike

0036 Riprap Devil's Elbow Cutoff

0037 Blanket Stone Devil's Elbow Cutoff

TOTAL SCHEDULE NO. 1

Turfing Ijams Lake

0032 Riprap PA-1

0029 Geotextile

0030 Pipeline Dredging Sections 1-5

TOTAL SCHEDULE NO. 1 & OPTION NOS. 1

THRU 5

OPTION NO. 5

0042 Ijams Lake Breaches

TOTAL OPTION NO. 5

0041 Pipeline Dredging Section 5

TOTAL OPTION NO. 4

OPTION NO. 3

0040 Pipeline Dredging Section 5

TOTAL OPTION NO. 3

OPTION NO. 4

0033 Riprap PA-2

0031 Mechanical Excavation

Semi-Compacted Containment Dike Raise PA-1

0026 Semi-Compacted Dike Ijams Lake

0027 Uncompacted Berm Ijams Lake

0028 Articulating Concrete Block

0018 Soil Laboratory Testing PA-1

0021 Site Management PA-2

0022 Soil Boring PA-1

0023 Soil Boring PA-2

0019 Soil Laboratory Testing PA-2

0012 Stripping Devil's Elbow

Turfing PA-2

Turfing at Devil's Elbow Cut

0017 Ijams Lake Site Management

0013 Turfing PA-1

0007 Clearing and Grubbing PA-1

0008 Clearing and Grubbing PA-2

0009 Clearing and Grubbing Devil's Elbow

0010 Stripping PA-1

0011 Stripping PA-2

0002 Pre-Dredging Hazard Survey

Demolition of Existing Drop-Outlet Structure PA-1

0004 New Drop-Outlet Structure PA1

0005 New Drop-Outlet Structure PA-2

0006 Pipeline Management

Business Size:

ITEM SCHEDULE NO. 1

NO. DESCRIPTION QUANTITY

0001 Mobilization and Demobilization

ABSTRACT OF OFFERS (CONT'D) Page 3 of 5

Solicitation No.: W912HY21B0010 Date Issued: 10 Mar 2021 Date Opened: 27 Apr 2021 Issuing Office: USAED-Galveston Project Title: Unrestricted Procurement for Cedar Bayou Navigation Channel, Chambers and Harris Counties, Texas, Pipeline Dredging

Offeror: Maloney Odin Joint Venture Novato, CA

Semi-Compacted Containment Dike Raise PA-2

0020 Site Management PA-1

Other than Small Business

1 JB SUM $4,600,000.00

1 JB SUM $75,000.00

1 JB SUM $150,000.00

1 JB SUM $700,000.00

1 JB SUM $700,000.00

1 JB SUM $850,000.00

1 JB SUM $800,000.00

1 JB SUM $850,000.00

1 JB SUM $850,000.00

1 JB SUM $290,000.00

1 JB SUM $230,000.00

1 JB SUM $100,000.00

1 JB SUM $230,000.00

1 JB SUM $200,000.00

1 JB SUM $270,000.00

1 JB SUM $100,000.00

1 JB SUM $400,000.00

1 JB SUM $15,000.00

1 JB SUM $15,000.00

1 JB SUM $200,000.00

1 JB SUM $80,000.00

80 LF $200.00 $16,000.00

80 LF $200.00 $16,000.00

260,000 CY $9.50 $2,470,000.00

205,000 CY $7.50 $1,537,500.00

48,500 CY $8.00 $388,000.00

115,000 CY $10.00 $1,150,000.00

8,500 SF $20.00 $170,000.00

1,200 SY $12.00 $14,400.00

729,514 CY $15.00 $10,942,710.00

236,000 CY $25.00 $5,900,000.00

117 TON $116.00 $13,572.00

200 TON $116.00 $23,200.00

160 TON $138.00 $22,080.00

80 TON $135.00 $10,800.00

48,000 TON $80.00 $3,840,000.00

15,000 TON $78.00 $1,170,000.00

$39,389,262.00

4,612 CY $15.00 $69,180.00

$69,180.00

1,938 CY $15.00 $29,070.00

$29,070.00

1,914 CY $15.00 $28,710.00

$28,710.00

2,210 CY $15.00 $33,150.00

$33,150.00

1 JB SUM $12,000.00

$12,000.00

$39,561,372.00

ABSTRACT OF OFFERS (CONT'D) Page 4 of 5

Solicitation No.: W912HY21B0010 Date Issued: 10 Mar 2021 Date Opened: 27 Apr 2021 Issuing Office: USAED-Galveston Project Title: Unrestricted Procurement for Cedar Bayou Navigation Channel, Chambers and Harris Counties, Texas, Pipeline Dredging

Offeror: Orion Construction, L.P Deer Park, TX Business Size:

ITEM

SCHEDULE NO. 1

NO. DESCRIPTION QUANTITY

Mobilization and Demobilization

Pre-Dredging Hazard Survey

Demolition of Existing Drop-Outlet Structure PA-1

New Drop-Outlet Structure PA1

New Drop-Outlet Structure PA-2

Pipeline Management

Clearing and Grubbing PA-1

Clearing and Grubbing PA-2

Clearing and Grubbing Devil's Elbow

Stripping PA-1

Stripping PA-2

Stripping Devil's Elbow

Turfing PA-1

Turfing PA-2

Turfing Ijams Lake

Turfing at Devil's Elbow Cut

Ijams Lake Site Management

Soil Laboratory Testing PA-1

Soil Laboratory Testing PA-2

Site Management PA-1

Site Management PA-2

Soil Boring PA-1

Soil Boring PA-2

Semi-Compacted Containment Dike Raise PA-1

Semi-Compacted Containment Dike Raise PA-2

Semi-Compacted Dike Ijams Lake

0027 Uncompacted Berm Ijams Lake 0028 Articulating Concrete Block 0029 Geotextile 0030 Pipeline Dredging Sections 1-5 0031 Mechanical Excavation 0032 Riprap PA-1 0033 Riprap PA-2 0034 Riprap Ijams Lake 0035 Blanket Stone Ijams Lake Dike 0036 Riprap Devil's Elbow Cutoff 0037 Blanket Stone Devil's Elbow Cutoff

TOTAL SCHEDULE NO. 1

OPTION NO. 1

0038 Pipeline Dredging Section 3

TOTAL OPTION NO. 1

OPTION NO. 2

0039 Pipeline Dredging Section 4

TOTAL OPTION NO. 2

OPTION NO. 3

0040 Pipeline Dredging Section 5

TOTAL OPTION NO. 3

OPTION NO. 4

0041 Pipeline Dredging Section 5

TOTAL OPTION NO. 4

OPTION NO. 5

0042 Ijams Lake Breaches

TOTAL OPTION NO. 5

TOTAL SCHEDULE NO. 1 & OPTION NOS. 1

THRU 5

Other than Small Business

1 JB SUM $10,063,338.05

1 JB SUM $78,394.11

1 JB SUM $20,124.45

1 JB SUM $334,919.45

1 JB SUM $334,919.45

1 JB SUM $1,672,407.64

1 JB SUM $440,966.86

1 JB SUM $384,836.68

1 JB SUM $133,269.98

1 JB SUM $905,941.39

1 JB SUM $794,685.44

1 JB SUM $216,150.38

1 JB SUM $64,186.34

1 JB SUM $64,186.34

1 JB SUM $406,100.28

1 JB SUM $392,134.37

1 JB SUM $261,313.70

1 JB SUM $326,642.12

1 JB SUM $326,642.12

1 JB SUM $78,644.34

1 JB SUM $78,644.34

80 LF $40.83 $3,266.40

80 LF $40.83 $3,266.40

260,000 CY $8.73 $2,269,800.00

205,000 CY $8.73 $1,789,650.00

48,500 CY $46.82 $2,270,770.00

115,000 CY $24.81 $2,853,150.00

8,500 SF $142.28 $1,209,380.00

1,200 SY $6.25 $7,500.00

729,514 CY $17.60 $12,839,446.40

236,000 CY $34.59 $8,163,240.00

117 TON $202.18 $23,655.06

200 TON $202.19 $40,438.00

160 TON $264.68 $42,348.80

80 TON $311.51 $24,920.80

48,000 TON $178.74 $8,579,520.00

15,000 TON $132.30 $1,984,500.00

$59,483,299.69

4,612 CY $20.91 $96,436.92

$96,436.92

1,938 CY $20.91 $40,523.58

$40,523.58

1,914 CY $20.91 $40,021.74

$40,021.74

2,210 CY $20.91 $46,211.10

$46,211.10

1 JB SUM $22,637.97

$22,637.97

$59,729,131.00

ABSTRACT OF OFFERS (CONT'D) Page 5 of 5

Solicitation No.: W912HY21B0010 Date Issued: 10 Mar 2021 Date Opened: 27 Apr 2021 Issuing Office: USAED-Galveston Project Title: Unrestricted Procurement for Cedar Bayou Navigation Channel, Chambers and Harris Counties, Texas, Pipeline Dredging

Offeror: Standard Constructors, Inc Houston, TX Business Size:

ITEM SCHEDULE NO. 1

NO. DESCRIPTION QUANTITY

0001 Mobilization and Demobilization 0002 Pre-Dredging Hazard Survey 0003 Demolition of Existing Drop-Outlet Structure PA-1 0004 New Drop-Outlet Structure PA1 0005 New Drop-Outlet Structure PA-2 0006 Pipeline Management 0007 Clearing and Grubbing PA-1 0008 Clearing and Grubbing PA-2 0009 Clearing and Grubbing Devil's Elbow 0010 Stripping PA-1 0011 Stripping PA-2 0012 Stripping Devil's Elbow 0013 Turfing PA-1 0014 Turfing PA-2 0015 Turfing Ijams Lake 0016 Turfing at Devil's Elbow Cut 0017 Ijams Lake Site Management 0018 Soil Laboratory Testing PA-1 0019 Soil Laboratory Testing PA-2 0020 Site Management PA-1 0021 Site Management PA-2 0022 Soil Boring PA-1 0023 Soil Boring PA-2 0024 Semi-Compacted Containment Dike Raise PA-1 0025 Semi-Compacted Containment Dike Raise PA-2 0026 Semi-Compacted Dike Ijams Lake 0027 Uncompacted Berm Ijams Lake 0028 Articulating Concrete Block 0029 Geotextile 0030 Pipeline Dredging Sections 1-5 0031 Mechanical Excavation 0032 Riprap PA-1 0033 Riprap PA-2 0034 Riprap Ijams Lake 0035 Blanket Stone Ijams Lake Dike 0036 Riprap Devil's Elbow Cutoff 0037 Blanket Stone Devil's Elbow Cutoff

TOTAL SCHEDULE NO. 1

OPTION NO. 1

0038 Pipeline Dredging Section 3

TOTAL OPTION NO. 1

OPTION NO. 2

0039 Pipeline Dredging Section 4

TOTAL OPTION NO. 2

OPTION NO. 3

0040 Pipeline Dredging Section 5

TOTAL OPTION NO. 3

OPTION NO. 4

TOTAL OPTION NO. 5

TOTAL SCHEDULE NO. 1 & OPTION NOS. 1

THRU 5

0041 Pipeline Dredging Section 5

TOTAL OPTION NO. 4

OPTION NO. 5

0042 Ijams Lake Breaches

Small Business

2021-04-27T20:52:39-0500
NICHOLS.ALDRICH.ANTONIA.1114683899